The United States appeals from the judgment of the United States Court of Federal Claims awarding damages of $132,398,200 to plaintiff James M. Fail for the government’s breach of contract.
Bluebonnet Sav. Bank, FSB v. United States,
I
This case is one of a number of “Wins-tar” cases arising from the savings and loan crisis of the 1980s.
See generally United States v. Winstar Corp.,
In 1989, however, Congress enacted the Financial Institutions Reform, Recovery, and Enforcement Act (“FIRREA”). The new statute and its regulations limited Bluebonnet’s ability to pay dividends and increased Bluebonnet’s capital level requirements. Mr. Fail, CFSB Corporation (now renamed Stone Capital, Inc.), and Bluebonnet filed suit charging that the enforcement of FIRREA and its regulations had the effect of breaching the contract offering regulatory forbearances. The plaintiffs claimed that as a result of the breach they experienced increased costs in financing their required cash infusions into Bluebonnet.
Mr. Fail had financed part of the initial cash infusion through short-term loans from financier Robert Shaw. Mr. Fail continued borrowing money from Mr. Shaw and allowing the loans to roll over until a total of $140 million in short-term loans from Mr. Shaw came due in 1992. Unable to secure long-term financing and facing default on the short-term loans, Mr. Fail entered into a more complex financing agreement with Mr. Shaw, which was referred to as the Economic Benefits Agreement (“EBA”). Under the EBA, Mr. Fad agreed to pay approximately $59 million to Mr. Shaw up front. Mr. Shaw agreed to provide long-term financing for the remaining $81 million due on the short-term loans in exchange for receiving a 49 percent equity interest in CFSB’s profits. The plaintiffs contended that if there had been no breach Mr. Fail would have been able to obtain all-debt financing through long-term loans at an interest rate of 13.5 percent. The plaintiffs thus sought two categories of damages: those damages related to the EBA, which flowed from the relinquishment of the 49 percent equity interest in CFSB; and those damages not related to the EBA, which resulted from the increased loan interest and lender fees that plaintiffs had to pay as a result of the breach. The value of the equity interest that Mr. Fail relinquished is reflected in a document called the Memo Account.
The Court of Federal Claims granted partial summary judgment for the plaintiffs on the issue of liability,
see Bluebonnet Sav. Bank, FSB v. United States,
On appeal, this court reversed in part.
See Bluebonnet Sav. Bank, FSB v. United States,
On remand, the Court of Federal Claims declined to reopen the record. Noting that “[t]he Federal Circuit held that Bluebonnet persuasively argued that it was entitled to the entire cost of the EBA as an award of damages,” the court stated that it “interprets the Federal Circuit’s mandate to require that the court add the $5,400,392 [paid to Mr. Shaw under the EBA] to the $126,997,808, which represents the value of the EBA debt as calculated in the Memo [Account], in order to arrive at the damage award in this case. The court is constrained by the mandate of the Federal Circuit.”
Bluebonnet Sav. Bank, FSB v. United States,
II
This appeal turns on the proper interpretation of our prior opinion in this case, and in particular the extent to which our mandate prohibited the trial court from conducting further proceedings on remand to determine the proper damages award. The plaintiffs contend that the trial court was correct in concluding that our prior opinion required the court to enter judgment in the amount of the full value of the EBA-related costs, as memorialized in the Memo Account, without further analysis or calculations. The government, on the other hand, argues that our opinion simply held that the Memo Account was an appropriate basis for determining the actual EBA-related costs and left it to the trial court to use that evidence, along with any other relevant evidence, to arrive at a fair and reasonable damages award. In formulating the damages award, the government contends, the trial court erred in awarding Mr. Fail the full value of the EBA-related costs, and not adjusting the award by subtracting the financing costs that the plaintiffs would have incurred had there been no breach.
One of the basic principles of contract damages is that “damages for breach of contract shall place the wronged party
*1345
in as good a position as it would have been in, had the breaching party fully performed its obligation.” Mass.
Bay Transp. Auth. v. United States,
Both sides thus continue to take an all- or-nothing approach on appeal. The government argues that the plaintiffs should receive no damages because they have not proved the costs they would have incurred absent a breach, while the plaintiffs contend that they are entitled to the full value of the equity interest relinquished as part of the EBA because they would not have relinquished equity absent a breach and thus the EBA-related costs they would have incurred absent a breach are zero.
We do not accept either of those extreme positions. In our prior opinion in this case, we rejected the trial court’s ruling that the Memo Account was not a sufficiently reliable basis for calculating the costs resulting from the plaintiffs’ surrender of equity as part of the EBA. For that reason, the trial court was justified in concluding, as it did, that the actual costs resulting from that portion of the EBA totaled $132,398,200. But that does not mean that damages should necessarily be awarded in that amount. To derive the proper amount for the damages award, the costs resulting from the breach must be reduced by the costs, if any, that the plaintiffs would have experienced absent a breach.
It has been determined that the plaintiffs would not have entered into the EBA but for the breach, that “dividend financing would have been available,” and that “it would have been unnecessary [for the plaintiffs] to give up a significant equity stake in CFSB to obtain financing.”
Bluebonnet,
Much of our prior opinion was directed to the question whether the Memo Account provided an adequate basis from which to calculate the loss attributable to the trans
*1346
fer of equity in the EBA. Ruling that it was “inappropriate to require CFSB to justify the basis for each term in the [Memo Account],” we concluded that the trial court should formulate its award of damages based on the total value of the EBA equity transfer as reflected in the Memo Account and the payments already made on Shaw’s equity interest.
Bluebonnet,
Accordingly, while it was proper for the trial court to begin its damages analysis on remand by treating the entire $132,398,200 in surrendered equity as a cost resulting from the breach, that does not end the matter. It is necessary for the court to make a further determination as to what costs, if any, the plaintiffs would have incurred in the absence of breach and thus to ascertain the net financial effect of the breach on the plaintiffs. While we believe a remand is required for the trial court to conduct the inquiry into the but-for financing costs, we again reject the government’s argument that it should pay no damages at all. We reiterate the point made in our prior opinion that, at a minimum, jury verdict damages would be appropriate in this case.
We recognize that, although the parties and the courts have separated the costs in this case into EBA-related costs and non-EBA-related costs, that distinction is somewhat artificial and may have resulted in some lack of certainty in the proper analysis to be applied to the damages issue in this case. We now ask the trial court to consider the alternatives to the equity arrangement in the EBA that the plaintiffs would have faced if there had been no breach. That determination should be made without regard to whether the “but-for” costs in question would be considered EBA-related costs or non-EBA-related costs.
Given the complexity of the case and the trial court’s intimate familiarity with the facts, we are confident that the trial court is in the best position to examine the question whether there are “but-for” costs that would have been incurred absent breach and should be used to offset the EBA-related cost of $132,398,200, and if so how much those costs should be. Because of our confidence that the trial court was in the best position to make the factual determinations necessary to establish an appropriate damages award, we did not mean for our prior mandate to prevent the trial court judge from conducting further factual analysis on remand. We continue to believe that the trial court is in the best position to make the necessary findings on this complex issue and to determine whether, and by how much, the EBA-related cost of $132,398,200 should be offset in order to obtain as accurate an assessment as possible of the true injury caused by the breach. We therefore vacate the judgment and remand the case to allow the trial court to use whatever means it deems appropriate, including reopening the record if necessary, to assess the net effect of the breach.
VACATED and REMANDED.
