History
  • No items yet
midpage
Purcell v. Schweitzer CA4/1
224 Cal. App. 4th 969
| Cal. Ct. App. | 2014
Read the full case

Background

  • Purcell sued Schweitzer on an $85,000 promissory note; they settled for a $38,000 balance plus 8.5% interest, paid in installments over 24 months.
  • Settlement required payments due the 1st, timely if received by the 5th; a late payment would be treated as breach making the original $85,000 liability immediately due.
  • The stipulation expressly stated the $85,000 was not a penalty or forfeiture and Schweitzer waived appeals and challenges to the judgment.
  • Schweitzer paid late in October (paid on Oct. 11); Purcell accepted the payment but nevertheless obtained a default judgment on Oct. 17 for $58,829.35 (much of which was labeled as "punitive damages").
  • Schweitzer moved to set aside the default judgment, arguing the stipulated judgment was an unenforceable penalty; the trial court granted the motion, finding no reasonable relationship between the stipulated amount and actual anticipated damages and that the waiver was unenforceable as against public policy.
  • On appeal the Court of Appeal reviewed the issue de novo and affirmed the order setting aside the default judgment.

Issues

Issue Purcell's Argument Schweitzer's Argument Held
Whether the stipulated judgment/ liquidated damages provision (triggering $85,000) was an enforceable liquidated damages clause or an unenforceable penalty The parties expressly agreed the $85,000 reflected actual damages and economics of proceeding; clause is not a penalty and is enforceable The stipulated judgment is an unlawful penalty because it bears no reasonable relationship to actual damages from a late installment Held unenforceable as a penalty; it bore no reasonable relationship to anticipated damages for breach of the settlement stipulation
Whether Schweitzer's waiver of the right to challenge the judgment bars relief The waiver expressly precludes any challenge or appeal of the judgment Waiver is unenforceable as contrary to public policy where clause attempts to circumvent statutory limits on liquidated damages Held waiver unenforceable as to enforcement of an unlawful penalty; public policy precludes circumventing Civil Code limits
Whether entry of judgment as "punitive damages" was permissible in a contract case The judgment amount was justified by the parties' agreement Punitive damages are not recoverable for breach of contract Held improper: punitive damages are not recoverable in breach of contract actions
Whether acceptance of a late payment (Oct. 11) precluded relief Purcell argues acceptance did not waive right to enter judgment under the agreement Schweitzer notes acceptance shows no actual damages and undermines claim of large damages Court relied on lack of relationship between breach and damages; acceptance underscores minimal or no actual damage

Key Cases Cited

  • Ridgley v. Topa Thrift & Loan Assn., 17 Cal.4th 970 (discusses when liquidated damages become unenforceable penalties)
  • Greentree Financial Group, Inc. v. Execute Sports, Inc., 163 Cal.App.4th 495 (liquidated/stipulated judgment that equals full underlying claim can be an unenforceable penalty when disproportionate to breach of settlement)
  • Cook v. King Manor and Convalescent Hospital, 40 Cal.App.3d 782 (public policy prevents circumventing Civil Code limits by contractual labeling)
  • Morris v. Redwood Empire Bancorp, 128 Cal.App.4th 1305 (reinforces requirement that liquidated damages reasonably relate to anticipated actual damages)
  • Myers Building Indus., Ltd. v. Interface Tech., Inc., 13 Cal.App.4th 949 (punitive damages not recoverable for breach of contract)
  • Harbor Island Holdings v. Kim, 107 Cal.App.4th 790 (standard of review: legal question on undisputed facts reviewed de novo)
Read the full case

Case Details

Case Name: Purcell v. Schweitzer CA4/1
Court Name: California Court of Appeal
Date Published: Feb 24, 2014
Citation: 224 Cal. App. 4th 969
Docket Number: D063435
Court Abbreviation: Cal. Ct. App.