620 S.W.3d 418
Tex.2021Background
- SWEPCO built the John W. Turk, Jr. coal plant after the Public Utility Commission (PUC) approved a certificate of convenience and necessity but capped Texas-ratepayer exposure to $1.522 billion of total plant cost.
- During construction (completed 2012), SWEPCO did not maintain contemporaneous records showing periodic reassessment of the project’s economic viability.
- Administrative Law Judges (SOAH) found SWEPCO should have stopped construction by June 2010 and proposed disallowing $171 million of costs based on falling natural-gas prices and alternative options.
- On rehearing the PUC independently reviewed the record, applied a prudence standard (whether a reasonably prudent utility manager could have chosen to complete the plant), and concluded completion was within the range of reasonable options; it allowed the Texas share of construction costs into rate base.
- The trial court affirmed the PUC; the court of appeals reversed, holding the PUC had effectively required independent retrospective (outside expert) analyses and that SWEPCO’s employee testimony was insufficient.
- The Texas Supreme Court reversed the court of appeals, holding the PUC applied its prudence standard correctly, that substantial evidence supports the PUC’s decision, and remanded for consideration of a separate AFUDC (financing-cost) issue.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Prudence of continuing construction after June 2010 | PUC decision arbitrary and unsupported because SWEPCO failed to present independent retrospective (outside expert) analyses; employee testimony insufficient | PUC properly applied prudence standard: whether a reasonably prudent utility manager could have chosen completion; outside expert testimony not required | Reversed court of appeals: PUC’s standard valid; employee and historical evidence can suffice; substantial evidence supports PUC finding that completion was within a reasonable range of options |
| Inclusion of AFUDC (capital financing costs) in rate base | AFUDC was part of capped capital costs and should be excluded from rate base | PUC concluded AFUDC was separately calculated and not part of capped cost; allowed AFUDC to be included | Texas Supreme Court remanded for the court of appeals to consider AFUDC issue in the first instance (did not decide on merits) |
Key Cases Cited
- Gulf States Utils. Co. v. Pub. Util. Comm’n of Tex., 841 S.W.2d 459 (Tex. App.—Austin 1992) (discusses utility’s burden when contemporaneous documentation is lacking)
- State v. Pub. Util. Comm’n of Tex., 883 S.W.2d 190 (Tex. 1994) (certificate to construct does not guarantee prudence recovery in rates)
- R.R. Comm’n of Tex. v. Torch Operating Co., 912 S.W.2d 790 (Tex. 1995) (explains substantial-evidence review and deference to agency expertise)
- City of El Paso v. Pub. Util. Comm’n of Tex., 883 S.W.2d 179 (Tex. 1994) (defines when agency action is arbitrary or capricious)
- Cities for Fair Util. Rates v. Pub. Util. Comm’n of Tex., 924 S.W.2d 933 (Tex. 1996) (explains rate base and AFUDC concepts)
- Duquesne Light Co. v. Barasch, 488 U.S. 299 (U.S. 1989) (notes complexity of economic judgments in rate proceedings)
