Lead Opinion
delivered the opinion of the Court,
These two causes were submitted together because both involve the Public Utility Commission’s (Commission) treatment of various costs associated with the operation of a newly constructed nuclear power plant.
In 1972, Central Power and Light Company (CP & L), Houston Lighting and Power Company (HL & P), the City of Austin, and the City of San Antonio began construction of a two-unit nuclear powered electricity generating station in Matagorda County, Texas, known as the South Texas Project. Unit One of the project (STP-1) was completed and began commercial operation on August 25, 1988. Under standard accounting procedures, CP & L and HL & P would have stopped accruing carrying costs on their invested funds and would have begun charging operations and maintenance, depreciation, insurance and taxes (collectively “operating costs”) as expenses against income at this time. During the interval between the time STP-1 was placed in service and the time the investment in the plant would be included in rate base (i.e., the “regulatory-lag” period), HL & P and CP & L would have incurred carrying costs and operating costs on their invested funds that they would never recover. As a result, both CP & L and HL & P applied to the Commission for deferred-accounting treatment of such costs during the regulatory lag period.
In Docket No. 7560 the Commission granted CP & L’s request for deferred accounting treatment for a period from August 25, 1988, to no later than February 15,1990. In Docket No. 8230 the Commission granted HL & P’s request for deferred accounting treatment from August 25, 1988, through the earlier of either the date rates which reflect those costs became effective or November 23, 1989. The order also provided that if by November 23, 1989, rates were not in effect to reflect the prudently incurred costs of the plant, HL & P could file a petition to request an extension of the deferral period beyond that date. Later, in Docket No. 9010, the Commission extended HL & P’s deferral period beyond November 23, 1989, until such time as the cost of STP-1 was reflected in rates approved by the Commission. By granting deferred accounting treatment during such time periods, the Commission allowed CP & L and HL & P to capitalize their costs associated with STP-1 during those periods and carry them as separate assets on their balance sheets. The reasonableness of the amount of the costs was to be determined by the Commission in a separate ratemaking proceeding in which the balance-sheet asset consisting оf the deferred costs would be reviewed using the same criteria as any other asset.
The State of Texas on behalf of certain State agencies, and the Office of Public Utility Counsel (OPUC) sought judicial review of the Commission’s orders granting deferred accounting treatment to CP & L and HL & P. The trial court upheld all three orders. The court of appeals affirmed the portion of the trial court’s judgment which affirmed the Commission’s order allowing the deferral of post-in-service operating costs.
I.
A.
The Public Utility Regulatory Act
As a general rule, an administrative agency is a creation of the legislature and, as such, has only those powers expressly conferred and those necessary to accomplish its duties. State v. Jackson,
PURA section 27 grants to the Commission broad authority in setting and defining a utility’s system of accounts. Specifically, under PURA section 27(a), the Commission has the power to prescribe forms of books and accounts “which in the judgment of the Commission may be necessary to carry out any of the provisions of’ PURA.
The State and the OPUC contend that because the deferral of post-in-service costs is not explicitly included in PURA section 43 as a rеmedy for regulatory lag, the Commission exceeded its authority by pro-
B.
Regulatory Lag and the Financial Integrity Standard
Because deferred accounting alleviated the effects of regulatory lag, the State and the OPUC argue that the Commission violated the principle that regulatory lag is ordinarily an element of the risk associated with investment in a utility. While we agree that regulatory lag is ordinarily an element of risk for utilities, Railroad Comm’n of Texas v. Lone Star Gas Co.,
In Dockets Nos. 7560, 8230 and 9010, the Commission granted deferred accounting treatment in order to protect the financial integrity of CP & L and HL & P. The financial integrity of the utilities was at risk due to the effect of extraordinary regulatory lag.
When an administrative agеncy is created to centralize expertise in a certain regulatory area, it is to be given a large degree of latitude in the methods it uses to accomplish its regulatory function. City of El Paso v. Public Util. Comm’n of Texas,
Like any decision by the Commission, an order authorizing a utility to defer post-in-service costs is subject to review for an abuse of discretion. Tex.Gov’t Code Ann. § 2001.174 (Vernon Pamphlet 1994); Railroad Comm’n of Texas v. Lone Star Gas Co.,
II.
Accounting Proceeding v. Rate Proceeding
Section 43(a) of PURA provides that no utility may make a change in its rates except by first filing a statement of intent with the regulatory authority having original jurisdiction. Tex.Rev.Civ.Stat.Ann. art. 1446c, § 43(a). Section 3(d) defines the term “rate” as follows:
The term “rate,” when used in this Act, means and includes every compensation, tariff, charge, fare, toll, rental, and classification, or any of them demanded, observed, charged, or collected whether directly or indirectly by any public utility for any service, product, or commodity ... and any rules, regulations, practices, or contracts affecting any such compensation, tariff, charge, fare, toll, rental, or classification.
Id. § 3(d). The State argues that deferred accounting treatment is a “practice” that “affects compensation” and is therefore a “rate” as that term is defined by section 3(d). As a result, the State contends that the Commission erred in failing to follow the ratemaking procedures set forth in PURA section 43. We disagree.
By allowing deferred accounting treatment, the Commission authorized the utilities to recognize a deferred cost asset on its books until a subsequent rate hearing. At that subsequent hearing, the deferred cost asset will be evaluated just as any other asset before inclusion in rate base.
We do not agree with the State’s contentions thаt the orders, in fact, changed the rates because deferred accounting will necessarily result in increased rates in the future. Although we recognize that accounting practice and ratemaking procedure are inherently intertwined, they are two distinct and separate concepts.
For example, if a certificate of convenience and necessity (CCN) to construct a new plant is granted, the costs of the new plant will eventually be considered in setting future rates. However, the approval of construction does not constitute a ratemaking proceeding subjeet to PURA section 43. See City of El Paso v. Public Util. Comm’n of Texas,
III.
A.
Retroactive Ratemaking
Fundamental in the utility rate-making process is the principle that utility
The rule against retroactive ratemaking is often misunderstood and misapplied. Stefan Krieger, The Ghost of Regulation Past: Current Applications of the Rule Against Retroactive Ratemaking in Public Utility Proceedings, 1991 U.Ill.L.Rev. 983, 988 (1991). The rule prohibits a public utility commission from setting future rates to allow a utility to recoup past losses or to refund to consumers excess utility profits. Id. at 984. Restated, the rule prohibits a utility commission from making a retrospective inquiry to determine whether a prior rate was reasonable and imposing a surcharge when rates were too low or a refund when rates were too high.
The State and OPUC argue that because the old rate is effective through the regulatory lag period, allowing expenses incurred during this period to be deferred and included in the rate base is tantamount to retroactive ratemaking. While we recognize that regulatory lag is ordinarily an element of the risk associated with investment in a utility, Railroad Comm’n of Texas v. Lone Star Gas Co.,
B.
Inclusion of Capitalized Post-in-Service Expenses in Rate Base
The State and OPUC next contend that the inclusion of post-in-service costs in a utility’s rate base violates PURA Section 41(a), which sets out the components of a utility’s rate base. A utility’s rate base is its authorized level of invested capital. Ron Moss, Ratemaking in the Public Utility Commission of Texas, 44 Baylor L.Rev. 825, 844 (1992). By statute, the utility is allowed to recover its reasonable and necessary oper ating expenses and both a return on, and a return of, its rate base. Tex.Rev.Civ.Stat.Ann. art. 1446c, § 39(a). Texas follows the “original-cost” method of valuing a utility’s rate base. Section 41(a).of PURA provides in pertinent part:
Sec. 41. The components of invested capital ... shall be determined according to the following rales:
(a) Invested Capital. Utility rates shall be based upon the original cost of property used by and useful to the public utility in providing service including construction work in progress at cost as recorded on the books of the utility_ Original cost shall' be the actual money cost, or the actual money value of any considerаtion paid other than money, of the property at the time it shall have been dedicated to public use, whether by the utility which is the present owner or by a predecessor, less depreciation.
Tex.Rev.Civ.Stat.Ann. art. 1446c, § 41(a) (emphasis added).
The State and OPUC contend that “property” as used in Section 41(a) refers only to the physical plant and the phrase “at the time it shall have been dedicated to public use” establishes a cutoff point — the original commercial operation date of the plant — for the calculation of the cost of the plant. As a result, they conclude that operating and maintenance costs and carrying costs incurred after the plant begins commercial operations cannot be included in the cost of the plant and thus cannot be included in the utility’s rate base. We disagree.
This interpretation is further supported by the fact that intangibles are ordinarily included in a utility’s rate base. See Ron Moss, Ratemaking in the Public Utility Commission of Texas, 44 Baylor L.Rev. 825, 844 (1992). On the other hand, if the term “property” is interpreted to include only tangible property, then the inclusion in invested capital of any intangibles would be incongruous with the language of section 41 which sets out the components of invested capital.
Having concluded that the term “property” as used in section 41(a) includes intangibles, we next address the meaning of the phrase “dedicated to public use.” The State and the OPUC argue that this language provides a cutoff date — when a plant begins commercial operation — after which no costs or expenditures can be included in a utility’s rate base. Because “property” includes intangibles, the State’s and OPUC’s interpretation of “dedicated to public use” lacks a logical foundation. When read to include intangibles, section 41(a) values original cost at the time any property is first dedicated to public use — not when the physical plant is first dedicated. Thus, the contention that “dedicated to public use” refers only to the plant facilities is not persuasive. “Dedicated to public use” means the time that capital is invested for utility purposes; i.e. when the expenditure is originally incurred.
This interpretation is consistent with the language of Section 41(a). The phrase “dedicated to public use” is immediately followed and qualified by the phrase “whether by the utility which is the present ownеr or by a predecessor.” This language defines original cost as the cost of investment to the utility that first dedicates property to public use, ignoring subsequent transfers. Virtually identical language was interpreted in the same manner by the U.S. Supreme Court in American Tel. & Teleg. Co. v. United States,
“Original cost” or “cost” ... means the actual money cost of (or the current money value of any consideration other than money exchanged for) property at the time when it was first dedicated to the public use, whether by the accounting company or by a predecessor public utility.
Id. at 238,
Violation of the “Test Year”
The OPUC argues that the Commission’s action also violated the test year requirement because it reached outside the test year to allow recovery of selective charges. Because we hold that the authorization to defer post-in-service costs is not the equivalent of a ratemaking function, this argument is misplaced. There is no requirement in PURA or the Commission’s procedures that the Commission must follow a test year when determining accounting policy. See 16 Tex.Admin.Code § 23.21(a) (West 1994).
D.
Single Issue Ratemaking
Further, the OPUC’s contention that deferred accounting violates a general prohibition against “single issue” ratemaking is also without merit. The OPUC argues that the Commission cannot authorize the deferral of post-in-service costs without considering all relevant factors affecting the financial condition of the utility. The OPUC cites no section of PURA and no Texas authority to support its position. We reject this argument.
IV.
The State’s Challenges
The State independently makes several arguments contending that the Commission’s authorization of deferred accounting treatment was arbitrary, capricious, in excess of its authority, and violated the State’s statutory due process rights. We will address each argument in the context of the applicable Docket.
A.
Dockets 7560 & 8230
In determining whether the post-in-service costs would impact the financial integrity of the utilities, the Commission did not inquire as to whether a portion of the post-in-service costs could be expensed without negatively impacting the financial integrity of each utility. Rather, the Commission considered the post-in-service costs of each nuclear plant in their entirety. Although the State recognizes that it will have an opportunity to dispute the reasonableness of the deferred expenses in a subsequent rate case, the State independently argues that the Commission acted arbitrarily and capriciously by precluding it from contesting whether the deferrals of 100 percent of the post-in-service costs were necessary to protect the financial integrity of the utilities.
An exercise of discretion by the Commission may only be reversed as being arbitrary and capricious if it constitutes a clear abuse of discretion. See City of Carrollton v. Keeling,
However, we do agree that the language of the Commission’s orders improperly forecloses any opportunity at the subsequent rate hearings to make these inquiries.
The State also contends that the Commission erred and abused its discretion by failing to balance the interests of consumers in deciding that the utilities should be granted deferred accounting. The PURA balances the important objective of protecting consumers from monopoly power with the need for financial stability which is required to attract the large amounts of investment capital essential to dependable utility service. Tex.Rev.Civ.Stat.Ann. art. 1446c, § 2. See Texas-New Mexico Power Co. v. Texas Indus. Energy Consumers,
Finally, the State argues that the Commission acted arbitrarily and capriciously by approving a deferral period of one year from the filing of the request. The State provides no supporting argument explaining why the length of the deferral period was improper. We refuse to speculate as to the State’s
B.
Docket No. 9010
In Docket No. 8230, the Commission approved HL & P’s request to allow the deferral of post-in-service costs from the date of commercial operation (August 25, 1988) and ending the earlier of either the date rates which reflect those costs became effective or November 23,1989. The order also provided that “[i]f by November 23,1989, rates are not in effect that reflect the prudently incurred costs of the plant, HL & P may file a petition with the Commission alleging what extraordinary circumstances, if any, exist which would warrant an extension of the deferral period beyond November 23, 1989.” Docket No. 8230, supra note 1, at 2821-22. On August 11, 1989, HL & P filed a petition requesting continued deferred accounting treatment. Based upon a stipulated statement of facts and briefs of the parties, the Examiner’s Report was issued denying HL & P’s request on January 19, 1990. On February 24, 1990, the Commission overturned the Examiner’s recommendations and approved HL & P’s request to extend deferred accounting treatment.
The State contends that on June 9, 1989, HL & P implemented bonded rates and thus Docket No. 9010 was mooted because rates reflecting the costs of STP-1 were included in the bonded rates prior to November 23, 1989. The State notes that HL & P bonded its rates at an annualized $227 million increase on June 9, 1989. Contrary to the State’s contention, however, the evidence in Docket No. 9010 assumed that bonded rates were in effect. See Docket 9010, supra note 1, at 1942-53 (Examiner’s report, attachment B). Thus, the Commission concluded that the financial integrity of the HL & P was at risk even with the bonded rates. The State’s argument fails.
The State also argues that the Commission erred in authorizing the extended deferred accounting treatment because although HL & P bonded its rates at $227 million, it could have bonded its rates in excess of $430 million. As a result, the State claims that if HL & P was not recovering all its costs, it was because of its own failure to use a legislatively granted remedy for regulatory lag. As noted, see supra note 10, HL & P was not required to utilize bonded rates authorized by PURA section 43 in order to request and receive deferred accounting treatment. Thus, the fact that HL & P did not bond in rates at the highest possible level does not preclude it from requesting and receiving deferred accounting treatment so long as its financial integrity is at risk.
The State next claims the Commission did not apply a financial integrity standard to Docket No. 9010, but instead applied a lower standard which considered financial ratios that did not establish that HL & P’s financial integrity was at risk. We disagree. In two separate findings of fact, the Commission concluded that the evidence established that deferred accounting treatment was necessary to protect HL & P’s financial integrity during the pendency of the rate proceeding. Docket 9010, supra note 1, at 1963 (Findings of Fact 22 & 23). Thus, the State’s claim that thе Commission applied an incorrect standard is without merit.
The State further contends that there was not substantial evidence to support the Commission’s finding in Docket No. 9010. We disagree.
At its core, the substantial evidence rule is a reasonableness test or a rational basis test. Railroad Comm’n of Texas v. Pend Oreille Oil & Gas Co.,
Although substantial evidence is more than a mere scintilla, the evidence in the record actually may preponderate against the decision of the agency and nonetheless amount to substantial evidence. Texas Health Facilities Comm’n v. Charter Medical-Dallas, Inc.,
The State makes two arguments supporting its claim that there was not substantial evidence to support the Commission’s finding, neither of which overcomes the presumption that the Commission’s order was supported by substantial evidence. First, the State argues that HL & P’s mortgage indicators were almost identical with or without deferred accounting treatment. Thus, the State claims that the Commission’s Finding of Fact number 22, that HL & P’s mortgage indicators were inadequate to preserve HL & P’s' financial integrity, was not supported by substantial evidence. However, the Commission’s Finding of Fact number 22 concluded that “the financial indicators in evidence in this case are inadequate to preserve HL & P’s financial integrity during the pendency of its rate case.” Docket 9010, supra note 1, at 1963. Thus, contrary to the State’s implications, the Commission’s finding was not based solely on the mortgage indicators. And, deferred accounting improved other financial indicators considered by the Commission. See Docket 9010, supra note 1, at 1942-53. Even if we agree that the mortgage indicators taken alone do not support the Commission’s holding, our inquiry is whether the Commission’s decision is reasonably supported by substantial evidence in view of the reliable and probative evidence in the record as a whole. Public Util. Comm’n of Texas v. Gulf States Utils. Co.,
Finally, the State argues that because the Commission did not adopt the Examiner’s Report, it could not rely on the record evidence summarized in the Examiner’s Report. As a result, the State claims that there was insufficient record evidence supporting the Commission’s decision. This argument is entirely unfounded. In its final order, the Commission states:
[T]he Examiner’s Report is NOT ADOPTED. Instead, based on the record evidence as summarized in the Examiner’s Report, the Commission issues the following Order: ....
The Commission is free to accept or reject the Examiner’s recommendations. See Ross v. Texas Catastrophe Prop. Ins.,
V.
Conclusion
We hold that the Commission has the authority under PURA to authorize utilities to defer costs incurred during the regulatory lag period. We reverse the court of appeals to the extent that it disallowed the deferral of post-in-service carrying costs. Because of its erroneous conclusion that the deferral of post-in-service carrying costs violated PURA section 41, the court of appeals did not consider several arguments advanced by the State contesting the deferral of carrying costs, including that there was not substantial evidence to support the Commission’s finding. Consequently, causes D-3154 and D-3155 are remanded to the court of appeals for consideration of the State’s unresolved arguments. In all other respects, the judgments of the court of aрpeals are affirmed.
Notes
. The present disputes arise from the following three Commission orders: Tex. Public Utils. Comm’n, Application of Central Power and Light Co. for Approval of Deferred Accounting Treatment of Certain Costs Related to the South Texas Nuclear Project No. 1, Docket No. 7560, 14 Tex P.U.C.Bull. 2669 (April 19, 1989) (Docket No. 7560); Tex. Public Utils. Comm’n, Petition of
. Tex.Rev.Civ.Stat.Ann. art. 1446c (Vernon Supp. 1994).
. Generally, regulatory lag is the delay between the time when a utility’s profits are above or below standard and the time when an offsetting rate decrease or rate increase may be put into effect by commission order or otherwise. This delay is due to the inherent inability in the regulatory process to allow for immediate rate decreases or increases. For purposes of this opinion, “regulatory lag” is the period between the date a new plant begins commercial operation (the "in-service” date) and the effective date of the new rates that result from including the new plant’s costs in the rate base. See James C. Bonbright et al., Principles of Public Utility Rates 96 (2d ed. 1988).
. Thе court of appeals separated the costs into two categories: (1) depreciation, operation and maintenance, insurance, and tax costs; and (2) carrying costs. Our holding makes no distinction between these costs.
. PURA’s only limit to this authority prohibits the Commission from creating a system of accounts that conflicts with that established by a federal agency for that utility. Tex.Rev.Civ.Stat. Ann. art. 1446c § 27(a). Accordingly, the Commission has directed that utilities generally must follow the Federal Energy Regulatory Commission (FERC) Uniform System of Accounts. See 16 Tex.Admin.Code § 23.12(a)(2)(B) (West 1994). The FERC Uniform System of Accounts specifically provides for the recognition of deferred cost assets. See 18 C.F.R. Part 101 (1993). Further, generally accepted accounting procedures recognize and allow for the deferral and capitalization of expenses. See Accounting for the Effects of Certain Types of Regulation, Statement of Financial Accounting Standards No. 71 (Fin. Accounting Standards Bd.1982).
. A constant theme running throughout both the State’s and OPUC's briefs is the argument that there is a fundamental distinction between invested capital and expenses. However, there is no inherent or fundamental characteristic that determines whether a particular expenditure is an expense or a capital investment. Indeed, one of the primary objectives of accounting regulation is to distinguish between expenditures that should be expensed currently or capitalized and recovered over a future period of time. Charles F. Phillips, Jr., The Regulation of Public Utilities 206 (2d ed. 1988) ("accounting regulation is needed so as to distinguish between expenditures that should be charged to capital and those that should be charged to income”); James C. Bonbright et al., Principles of Public Utility Rates 256 (2d ed. 1988). See Accounting for the Effects of Certain Types of Regulation, Statement of Financial Accounting Standards No. 71, para. 9 (Fin. Accounting Standards Bd.1982). PURA grants to the Commission broad authority concerning accounting policy. Tex.Rev.Civ.Stat.Ann. art. 1446c, § 27. We recognize that uniformity is necessary in determining expenditures that should be charged to capital and those that should be charged against income. At the same time, the appropriate classification of a particular expenditure as capital or expense is dependent on the circumstances associated with the outlay. See Bonbright, at 256; see also Norfolk & Western Railway Co. v. United States,
. Section 39(a) provides in part:
... the regulatory authority shall fix its overall revenues at a level which will permit such utility a reasonable opportunity to earn a reasonable return on its invested capital used and useful in rendering service to the public over and above its reasonable and necessary operating expenses.
Tex.Rev.Civ.Stat.Ann. art. 1446c, § 39(a).
. At oral argument the State recognized that deferred accounting may be appropriate in certain circumstances. We note that deferred accounting treatment has been authorized by the vast majority of utility commissions that have addressed this issue. E.g., Re Arizona Public Service Co.,
. The State and the OPUC claim that the four methods for reducing the effect of regulatory lag provided by PURA section 43 are exclusive. They include: (1) a time schedule within which the Commission must reach a decision in a rate case; (2) the authority to implement temporary rates during the pendency of a case; (3) the utility’s ability to bond in proposed rates, without agency approval, by filing a bond adequate to protect customers if the agency ultimately approves a lower rate; and (4) the utility’s ability to include construction work in progress (CWIP) in invested capital if necessary for its financial integrity. Tex.Rev.Civ.Stat.Ann. art. 1446c, § 43.
. The State argues that the Commission erred in its findings of fact that the alternatives provided in PURA section 43, see supra note 9, were not sufficient to protect the utilities from regulatory lag. As noted, PURA authorizes the Commission to order deferred accounting treatment of post-in-service costs. There is no requirement that the Commission first determine that no other method is adequate before invoking its authority to order deferred accounting. Thus, contrary to the State's position, the Commission is not required to first find that the methods provided in section 43 would not sufficiently protеct the utilities. See Railroad Comm’n of Texas v. Lone Star Gas Co.,
.We note that both HL & P and CP & L were faced with atypically long regulatoiy lag periods. Part of the extended periods were due to the existence at the time the dockets were pending of the "Big Cajun” rule. The “Big Cajun" rule required a utility to wait until after the end of a calendar quarter during which a new plant was in service before filing a rate case seeking inclusion of the plant in rate base. See Tex. Public Utils. Comm’n, Application of Gulf States Utilities Co. for a Rate Increase, Docket No. 5560, 10 Tex.P.U.C.Bull. 405, 420-23 (July 13, 1984). The rule exacerbated the effect of regulatory lag on a
. The Commission’s orders explicitly provide
Capitalized costs will be subjеct to review by the Commission in CPL’s subsequent ratemak-ing dockets. Those costs will be included in cost of service, and a return allowed on the unamortized balance, to the extent and only to the extent that the Commission determines that they are prudent, reasonable and neces-saiy expenses related to property that is used and useful in providing service.
Docket No. 7560, supra note 1, at 2740. See also Docket No. 8230, supra note 1, at 2822; Docket No. 9010, supra note 1, at 1960-65.
. The Commission itself has differentiated between ratemaking proceedings and other utilily regulation matters. City of El Paso,
. The State and OPUC also contend that inclusion of deferred costs in a utility's rate base violates section 41(a) because the deferred costs are not “used by and useful to the public utility in providing service....” Tex.Rev.Civ.Stat.Ann. art. 1446c, § 41(a). We disagree. By deferring costs that would otherwise not be recovered by the utility, the utility is able to avoid heightened costs of capital and the possibility of missed dividend payments which would adversely impact the ability to raise equity capital. Further, the deferred costs, when incurred, were necessary to the continued operations of the utility plant in the first instance.
. The State specifically asserts that the Commission’s orders did not preserve the ability to review whether "any or all” of the deferred costs were actually reasonable and necessary to protect the utilities' integrity. We interpret the State’s argument to mean that the State did not have an opportunity to argue that only a portion of the costs associated with the nuclear generation plants were actually necessary to preserve the utilities’ financial integrity. To the extent the State is arguing that the Commission foreclosed an opportunity to review whether the deferred costs, taken as a whole, were necessary to protect the utilities’ financial integrity, that argument is without merit. The very purpose of the hearings in question was to determine that issue.
. In Docket No. 8230, the State claims that its due process rights were violated because the Administrative Law Judge (AU) refused to consider a cosi/benefit analysis that established that through deferred accounting treatment, HL & P would earn more money than if it followed legal ratemaking methodologies. Because the focus of the inquiry was on whether HL & P's financial integrity was at risk, evidence relevant to the eventual rates was not within the scope of the hearing. Further, to the extent that the State claims that the analysis would establish that deferred accounting would earn HL & P more than "legal” ratemaking methodologies, the basis for its argument is flawed as deferred accounting treatment is an authorized and “lеgal” action by the Commission. We note that deferred accounting is not a ratemaking action. See supra II.
. The Commission's orders provide that the deferred costs will be subject to review at a subsequent rate hearing and will be included in the rate base only to the extent that they are prudent, reasonable and necessary and are related to property that is used and useful in providing service. However, the orders clearly foreclose the Commission from an opportunity to review the extent to which the deferred costs must actually be included in rate base in order to protect the utilities’ financial integrity. For example, the Commission provided in its order in Docket No. 7560 that:
Capitalized costs will be subject to review by the Commission in CPL’s subsequent ratemak-ing dockets. Those costs will be included in cost of service, and a return allowed on the unamortized balance, to the extent and only to the extent that the Commission determines that they are prudent, reasonable and necessary expenses related to property that is used and useful in providing service.
Docket No. 7560, supra note 1, at 2740. See also Docket No. 8230, supra note 1, at 2822; Docket No. 9010, supra note 1, at 1960-65.
. The State’s argument is, in actuality, a claim that there was not substantial evidence to support the Commission's decision. Although cloaked in terms of applying an incorrect standard, the State’s primary support for its argument is that the evidence relied on by the Commission does not support a conclusion that HL & P's financial integrity was in jeopardy.
Dissenting Opinion
dissenting.
Today the majority approves a creative accounting procedure that allows risk-free nuclear investment at the ratepayer’s expense. By statute, a utility is entitled to earn a reasonable return on its invested capital, over and above its reasonable and necessary operating expenses. During the periods at issue in this case, however, a utility is not entitled — statutorily or otherwise — to recover its operating expenses; and under no circumstances is the utility entitled to reap a profit on those expenses. By erasing the line between capital and expenses, the majority converts the utilities’ losses during the period before revised rates take effect into gains worth hundreds of millions of dollars. I dissent.
I.
The Public Utility Commission is required to set a utility’s revenues at a level that will allow the utility an opportunity to earn “a reasonable return on its invested capital used and useful in rendering service to the public over and above its reasonable and necessary operating expenses.” Public Utility Regulatory Act (“PURA”), Tex.Rev.Civ.Stat.Ann. art. 1446c, § 39(a) (Vernon Supp.1994). The valuation of its invested capital, or rate base, is thus critical in determining the amount that utilities are allowed to charge ratepayers.
PURA provides a simple mechanism for valuing a utility’s rate base: valuation is based on “the original cost of property used by and useful to the public utility in providing service.” § 41(a). “Original cost” is defined as the property’s actual money cost “at the time it shall have been dedicated to public use, whether by the utility which is the present owner or by a predecessor, less depreciation.” Id. This method could not be more straightforward; value is determined by looking to the property’s cost as of the time the plant is put into commercial operation.
This state’s adoption of original-cost valuation represented a rejection of the previous valuation system, which looked to the “fair value” of a company’s facilities. See Ron Moss, Ratemaking in the Public Utility Commission of Texas, 44 Baylor L.Rev. 825, 854-57 (1992). The fair value system was widely criticized because it involved the “laborious and baffling” task of finding an exchange value for property that is “not commonly bought and sold in the market.” Missouri ex rel. Southwestern Bell Tel. Co. v. Public Serv. Comm’n,
The thing devoted by the investor to the public use is not specific property, tangible and intangible, but capital embarked in the enterprise. Upon the capital so invested the Federal Constitution guarantees to the utility the opportunity to earn a fair return.
Id. at 290,
In Texas, the shift toward “capital invested” came in stages. Before PURA, this Court — quoting at length from Justice Brandéis — concluded that the governing statutes required a “physical property valuation rate base.” Railroad Comm’n v. Houston Natural Gas Corp.,
Apart from the simplicity of its administration, the original-cost system has the advantage that it is not subject to political manipulation. Under the fair-value system, the ratesetting authority could avoid a politically-sensitive rate increase by simply making an inflation adjustment to the rate base; the utility’s nominal rate of return would remain the same, but consumers’ electric bills would go up. See Moss, 44 Baylor L.Rev. at 857. Original-cost valuation brings accountability to the ratesetting process: with value fixed at original cost, the Public Utility Commission must make adjustments to the rate of return. The original-cost method thus “sheds light on the ratesetting process and allows the public to discern the true rate of return.” Id.
A pure original-cost method — with cost fixed as of the date of commerciаl operation — is also consistent with accounting rules regarding the treatment of carrying costs before and after the commercial operation date. Up until the plant begins operating, the utility may accrue carrying costs in its allowance for funds used during construction (AFUDC), which can later be included in rate base. After the commercial operation date, however, such costs must be expensed. As the court of appeals concluded in another of the three causes decided today, “simple logic” requires that valuation must occur at the time that AFUDC capitalization ceases— that is, at the date of commercial operation. City of El Paso v. Public Util. Comm’n,
The majority today abandons this approach, without even acknowledging the court of appeals’ reasoning. According to the majority, property is “dedicated to public use” within section 41(a) not at the date of commercial operation, but “when the expenditure is originally incurred,” supra at 200, whether that occurs before or after the commercial operation date.
The most obvious problem with the majority’s view is reconciling it with the language of the statute. If the Legislature had intended “original cost” to mean cost at the time of the expenditure, it could easily have said so, instead of referring to “the time [the property] shall have been dedicated to public use.” Other language in section 41(a) indicates that the Legislature did not intend a “time of expenditure” construction: property can hardly be “used by and useful to the public utility in providing service” before the utility has even begun providing service.
The majority dismisses the “dedicated to public use” language on the ground that it was intended to prevent the property’s value from being inflated by artificial transactions. Supra at 200 (citing American Tel. & Tel. Co. v. United States,
By ignoring clear statutory limitations on the definition of invested capital, the majority opens the door to other types of manipulation, including rate base manipulation by the Public Utility Commission to avoid rate increases. Rate base will now include, for
The mаjority has achieved, in short, exactly what original-cost valuation was designed to prevent: the inclusion in rate base of items that should in fact be classified as expenses. With deferred accounting, a utility’s value is greater than its original cost— guaranteeing the utility a return greater than that authorized by the Legislature. See Re Puget Sound Power and Light Co.,
The majority understandably downplays the distinction between capital and expenses, asserting that “there is no inherent or fundamental characteristic that determines whether a particular expenditure is an expense or a capital investment.” Supra at 194 n. 6. The authority the majority cites, however, states exactly the opposite. Professor Phillips describes the fundamental characteristics separating capital from expenses,
The result of this judicial alchemy is that consumers will now be paying higher electric rates to compensate thе utilities for expenses incurred in a period prior to the ratemaking proceeding. This result violates the most basic principle of ratemaking: rates are prospective only, so past losses are not recoverable under future rates. See Railroad Commission v. Lone Star Gas Co.,
The majority acknowledges that this rule “prohibits a public utility commission from setting future rates to allow a utility to recoup past losses,” supra at 199; but it insists that the orders in this ease do not allow recoupment of past losses. This reasoning is sharply at odds with the generally-accepted accounting procedures on which the majority relies. See supra at 194 n. 5 and 194 (citing Statement of Financial Accounting Standards No. 71 (Fin. Accounting Standards Bd.1982)). Those accounting rules provide that deferred accounting is permissible only if “future revenue will be provided to permit recovery of the previously incurred cost rather than to provide for expected levels of similar future costs.” FAS 71 ¶ 9.b. Thus, under the majority’s own standards, deferred accounting must entail future recoupment of past losses.
Though today’s ruling is cast in arcane terms, its bottom line is simple: the Public Utility Commission may now levy a surcharge on consumers to reward massive utility companies for expenditures the companies made during the regulatory lag period. If the utilities reap unexpected profits in the future, consumers — many of them facing fi
II.
Regulatory lag, in the context of public utilities, is not an evil to be eliminated. Because utility rates are based on historical data from a test year, “some lag is inherent in the process.” Lone Star Gas Co.,
In rare instances, the regulatory lag period may be so protracted as to pose a threat to the utility’s viability. The Texas Legislature has addressed that danger in section 43 of PURA, which “provides a detailed program in an attempt to compensate a utility for undue regulatory lag.” Lone Star Gas Co.,
The accounting maneuver approved today is not among the remedies chosen by the Legislature. In fact, had this maneuver been permissible in 1983, there would have been no need for any of the remedies in section 37. Deferred accounting treatment enables the Public Utility Commission to shift the entire burden of regulatory lag from shareholders to- ratepayers. All lag-period costs — 'from the time a new plant goes into service until the time new rates go into effect — may now be included in the utility’s rate base. Under such circumstances, the lag period will serve no efficiency role at all: a utility may not only recover all lag-period expenditures, but may actually earn a guaranteed return on those expenditures.
III.
Among the fundamental problems with deferred accounting is a lack of meaningful standards for implementing it. The majority holds that deferred accounting is permissible “to protect the financial integrity” of a utility. Supra at 196. Unfortunately, the proceedings in the present cases confirm what past experience has shown: that the “financial integrity” standard is, in effect, no standard at all.
Docket 9010 demonstrates the approach typically taken by the Public Utility Commission in applying the financial integrity standard. The Administrative Law Judge in that ease, after hearing all the evidence, submitted an Examiner’s Report concluding that deferred accounting should be denied:
Clearly, HL & P would be better off financially if the extension of deferred accounting were granted. That is not the issue, however. To balance the interests of utilities and their ratepayers, the Commission has decided to approve deferred accounting only if necessary to protect the utility’s financial integrity. In this case, an extension of deferred accounting is not necessary to ensure HL & P’s continued access to the capital markets on reasonable terms while its rate case is pending.
Texas Public Utils. Comm’n, Petition of Houston Lighting and Power Company to Continue Deferred Accounting Treatment for STP Unit One Beyond November 23, 1989, Docket No. 9010, 15 Tex.P.U.C.Bull. 1905, 1920 (Feb. 28, 1990). The Commission, however, overruled the Administrative Law Judge, and approved deferred accounting for the duration of the lag period — that is, until such time as the cost of South Texas Nuclear Project Unit 1 was included in rates. Id. at 1960. Commissioner Campbell dissented,
The indeterminate standard approved today is similar to one previously adopted by the Legislature in a related context. As enacted in 1975, PURA allowed the Commission to include in rate base expenditures on construction work in progress (CWIP) “where necessary to the financial integrity of the utility.” Act of June 2, 1975, 64th Leg., R.S., ch. 721, § 41(a), 1975 Tex.Gen.Laws 2327, 2341. From the outset, this provision met with criticism, as in the following passage:
The first question a consumer might pose is when will such an inclusion be “necessary to the financial integrity of the utility?” It is likely that the consumer will not be benefitted on this point, since it will be very easy for the Commission to always find it necessary to include utility construction work in the rate base, in order to strengthen the utility’s “financial integrity,” that is, to increase its profits.
H. Louis Nichols and Randall Hagan Fields, Rate Base Under PURA: How Firm is the Foundation?, 28 Baylor L.Rev. 861, 878-79 (1976). The Legislature reconsidered the CWIP provision in 1983, recognizing the “widespread dissatisfaction” with the 1975 standard. Ron Moss, Ratemaking in the Public Utility Commission of Texas, 44 Baylor L.Rev. 825, 848 (1992). It then adopted language that (1) provided that “construction work in progress is an exceptional form of rate relief’; and (2) shifted to the utility the burden of showing that inclusion of CWIP in the rate base was necessary to maintain the utility’s financial integrity. Act of May 26, 1983, 68th Leg., R.S., ch. 274, § 1, 1983 Tex.Gen.Laws 1258, 1297 (amending PURA § 41(a)); see also Moss, 44 Baylor L.Rev. at 849. The Public Utility Commission has recognized that the 1983 amendment requires a more stringent treatment of CWIP. Tex. Public Util. Comm’n, Application of Gulf States Utilities Company for a Rate Increase, Docket No. 5560, 10 Tex.P.U.C.Bull. 405, 435 (July 13, 1984); Moss, 44 Baylor L.Rev. at 850 & n. 114.
Fortunаtely, today’s decision, like the 1975 CWIP provision, may eventually be subject to legislative correction. Unfortunately, however, any such action will come too late to ease the burden today’s decision places on millions of consumers.
[[Image here]]
I would affirm the judgments of the court of appeals with regard to the disallowance of deferrals of post-in-service carrying costs. In all other respects, I would reverse the judgments of the court of appeals and hold that expenses incurred after the beginning of commercial operation cannot be capitalized and included in rate base.
. PURA defines "facilities” to include "all tangible and intangible real and personal property without limitation.” § 3(n). This broad definition, however, was not incorporated into PURA’s definition of rate base. See Nichols and Fields, 28 Baylor L.Rev. at 874 ("Fortunately, this broad definition [of facilities] is not used in defining rate base under PURA. Valuations of 'intangible
. The majority also cites Office of Consumers' Counsel v. Public Util. Comm'n of Ohio,
. "[A]ccrual of AFUDC after the in-service date of a utility plant would result in a utility plant with a value exceeding its ‘original’ cost. The original cost concept requires that the value of utility plant be determined at the time it is first placed in service to the public. To grant this petition would establish a dangerous and unwarranted precedent leading to further requests to disregard the original cost concept.”
. "Expenditures that represent investment in capital assets (plant and equipment) should be charged to fixed asset accounts rather than to operating expense accounts. Similarly, expenditures that represent costs of doing business should be charged to operating expense accounts rather than to capital.” Phillips, supra, at 206.
.In Lone Star Gas Co., we recognized that a regulatory authority may set new rates to be effective as early as the time the authority assumed jurisdiction over the ratemaking proceeding.
