History
  • No items yet
midpage
Orangeburg, South Carolina v. Federal Energy Regulatory Commission
862 F.3d 1071
D.C. Cir.
2017
Read the full case

Background

  • Orangeburg, SC (a municipal wholesale power buyer) sought in 2008 to switch its long-standing supplier to Duke Energy Carolinas under an agreement treating Orangeburg as a "native-load" customer, which would yield lower wholesale rates (~$10M/year savings projected).
  • The North Carolina Utilities Commission (NCUC) issued a 2009 declaratory ruling that it would not recognize Orangeburg as native-load for North Carolina retail ratemaking and would "impute" higher revenue from Orangeburg, creating "trapped costs" that made the deal infeasible; Duke invoked a regulatory-out and the contract was terminated.
  • Duke and Progress (sister utilities) later filed a Joint Dispatch Agreement (JDA) as part of a corporate merger; the JDA reserved lowest-cost, most reliable power for native-load customers and initially incorporated NCUC regulatory conditions (including deference to NCUC imputation and notice requirements).
  • FERC approved the JDA in 2012 (directing deletion of some explicit state-incorporation provisions) and rejected Orangeburg’s protest that the JDA (and NCUC’s role) unlawfully permitted discrimination against out-of-state wholesale customers and intruded on FERC’s wholesale jurisdiction.
  • Orangeburg challenged FERC’s approval and rehearing denial, arguing (1) FERC’s approval authorized discriminatory treatment of wholesale customers reserved to native-loads, and (2) NCUC’s imputation regime functioned as a protectionist gatekeeping measure violating the Federal Power Act and the Commerce Clause.
  • The D.C. Circuit held Orangeburg has Article III standing (imminent loss of opportunity to obtain desired product; injury traceable to FERC’s approval/acquiescence) and vacated in part the portions of FERC’s JDA Approval and Rehearing Orders that accepted disparate wholesale rates for native-load vs. non-native-load customers, remanding for further explanation.

Issues

Issue Plaintiff's Argument (Orangeburg) Defendant's Argument (FERC) Held
Standing: Article III injury and imminence Orangeburg lost (and faces imminent loss of) the opportunity to purchase lowest-cost, most reliable wholesale power from Duke as a native-load customer (quantified savings; prior deal failed due to NCUC imputation) FERC argued Orangeburg lacks a concrete, imminent injury (current contract runs years) and causation is attributable to NCUC, not FERC Court: Orangeburg has standing — injury is imminent (contracting cycle and FERC delay make harm likely), causation is fairly traceable to FERC approval/acquiescence, and relief would likely redress injury
Causation: Did FERC’s approval "authorize" the conduct causing harm? FERC’s approval of the JDA (preferring native-loads) and its refusal to preempt NCUC effectively authorized discrimination and NCUC’s gatekeeping FERC claimed the injury stems from NCUC and state action, not FERC Court: FERC’s approval of disparate treatment plus its pattern of sidestepping/preemption refusals suffices to show authorization and traceability for standing purposes
Merits: Was FERC’s approval of disparate wholesale treatment arbitrary and capricious? The JDA’s allocation of lowest-cost power to native-load wholesale customers is unjustified here given NCUC’s role; FERC failed to offer a valid reason for the disparity FERC relied on a passage in Order No. 2000 to justify allowing states to require lowest-cost power to native load Court: FERC’s reliance solely on Order No. 2000 (a brief passage) was inadequate/unexplained and potentially inconsistent with Order No. 888 and FERC’s exclusive wholesale jurisdiction; vacatur in part and remand for explanation
Preemption / Commerce Clause concern NCUC’s imputation regime functions as protectionist gatekeeping, potentially violating the Commerce Clause and subject to preemption by federal wholesale authority FERC treated the NCUC-related provisions as retail ratemaking matters and declined to rule on NCUC’s authority Court: The panel did not resolve preemption/Commerce Clause merits but found FERC failed adequately to justify accepting disparate wholesale treatment tied to state actions; remand required for fuller analysis

Key Cases Cited

  • FERC v. Elec. Power Supply Ass’n, 136 S. Ct. 760 (2016) (describing FERC’s jurisdiction over interstate wholesale power and the link between wholesale and retail markets)
  • New England Power Co. v. New Hampshire, 455 U.S. 331 (1982) (Commerce Clause bars state protectionist restrictions on interstate energy exports)
  • Pub. Util. Dist. No. 1 of Snohomish Cnty. v. FERC, 272 F.3d 607 (D.C. Cir. 2001) (addressing Order No. 2000 context and RTO formation)
  • Black Oak Energy, LLC v. FERC, 725 F.3d 230 (D.C. Cir. 2013) (agency must offer a valid reason for disparate treatment between ratepayers)
  • Lujan v. Defenders of Wildlife, 504 U.S. 555 (1992) (standing requirements: injury-in-fact, traceability, redressability)
  • Animal Legal Def. Fund, Inc. v. Glickman, 154 F.3d 426 (D.C. Cir. 1998) (agency action that authorizes otherwise-illegal conduct can satisfy causation for standing)
  • Motor Vehicle Mfrs. Ass’n v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29 (1983) (arbitrary-and-capricious review requires reasoned explanation)
Read the full case

Case Details

Case Name: Orangeburg, South Carolina v. Federal Energy Regulatory Commission
Court Name: Court of Appeals for the D.C. Circuit
Date Published: Jul 14, 2017
Citation: 862 F.3d 1071
Docket Number: 15-1274
Court Abbreviation: D.C. Cir.