History
  • No items yet
midpage
Maine Public Utilities Commission v. Federal Energy Regulatory Commission
625 F.3d 754
D.C. Cir.
2010
Read the full case

Background

  • Maine PUC and Connecticut/Massachusetts Attorneys General challenged FERC's approval of a settlement that redesigned New England's capacity market.
  • Settlement created a Forward Capacity Market with annual auctions held three years in advance to set capacity rates.
  • Settlement included a Mobile-Sierra clause requiring challenges to auction-derived rates to be adjudicated under the public-interest standard rather than just-and-reasonable.
  • Supreme Court Morgan Stanley v. Snohomish County held Mobile-Sierra applies to contract-rate challenges; NRG Power Mktg. LLC v. Maine PUC then addressed whether auction rates are contract rates.
  • This court on remand examines (1) whether the auction rates are contract rates or analogizable, and (2) whether FERC had discretion to apply Mobile-Sierra to non-contract rates; remands for further proceedings.
  • Jurisdiction issue: petitioners argued, and the court acknowledged, that the remand required addressing arguments not precisely raised before FERC, but the court found petitioners did raise a related rights-based challenge to the Mobile-Sierra clause.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether the Mobile-Sierra clause applies to auction rates Maine and allies contend it deprives non-settling parties of FPA rights FERC had discretion to apply Mobile-Sierra to these rates Remanded for further proceedings
Whether the auction rates are contract rates or non-contract rates Rates are not contract rates and thus may not be Mobile-Sierra-protected Rates resemble cost-based tariffs; Mobile-Sierra may apply if justified Remanded for determination
Whether FERC could apply Mobile-Sierra outside the contract-rate context No, unless justified by statute and orderly explanation Discretion exists to extend Mobile-Sierra to analogous circumstances Remanded for explanation
Whether the court has jurisdiction to review arguments not precisely raised before FERC Only petitioners' arguments before FERC are reviewable Intervenors' precise framing is not required; related rights challenge suffices Court retains jurisdiction and proceeds on remand

Key Cases Cited

  • NRG Power Marketing LLC v. Maine Pub. Utils. Comm'n, 130 S. Ct. 693 (2010) (Mobile-Sierra applies to third-party challenges)
  • Me. Pub. Utils. Comm'n v. FERC, 520 F.3d 464 (D.C. Cir. 2008) (Mobile-Sierra clause challenged as applied to non-settling parties)
  • Morgan Stanley Capital Group Inc. v. Pub. Utility Dist. No. 1 of Snohomish County, 554 U.S. 527 (2008) (Mobile-Sierra as application of just-and-reasonable standard to contract rates)
  • United Gas Pipe Line Co. v. Mobile Gas Serv. Corp., 350 U.S. 332 (1956) (Mobile-Sierra foundational decision on contract rates)
  • Federal Power Comm'n v. Sierra Pac. Power Co., 350 U.S. 348 (1956) (Contract-rate defenses and public-interest considerations)
  • Potomac Electric Power Co. v. FERC, 210 F.3d 403 (D.C. Cir. 2000) (extension of Mobile-Sierra protections to purchasers)
Read the full case

Case Details

Case Name: Maine Public Utilities Commission v. Federal Energy Regulatory Commission
Court Name: Court of Appeals for the D.C. Circuit
Date Published: Nov 5, 2010
Citation: 625 F.3d 754
Docket Number: 06-1403, 06-1427, 07-1193
Court Abbreviation: D.C. Cir.