NRG POWER MARKETING, LLC, ET AL. v. MAINE PUBLIC UTILITIES COMMISSION ET AL.
No. 08-674
Supreme Court of the United States
January 13, 2010
558 U.S. 165
Argued November 3, 2009
Jеffrey A. Lamken argued the cause for petitioners. With him on the briefs were John N. Estes III, Robert K. Kry, Michael R. Bramnick, and Christopher C. O‘Hara.
Eric D. Miller argued the cause for the Federal Energy Regulatory Commission urging reversal. With him on the briefs were Solicitor General Kagan, Deputy Solicitor General Kneedler, Cynthia A. Marlette, Robert H. Solomon, and Lona T. Perry.
Richard Blumenthal, Attorney General of Connecticut, argued the cause for respondents. With him on the brief were John S. Wright and Michael C. Wertheimer, Assistant Attorneys General, Jesse S. Reyes, Assistаnt Attorney General of Massachusetts, Mary E. Grover, Lisa Fink, and Stephen L. Teichler.*
JUSTICE GINSBURG delivered the opinion of the Court.
The Federal Power Act (FPA or Act), 41 Stat. 1063, as amended,
This case stems from New England‘s difficulties in
We reverse the D. C. Circuit‘s judgmеnt to the extent that it rejects the application of Mobile-Sierra to noncontracting parties. Our decision in Morgan Stanley, announced three months after the D. C. Circuit‘s disposition, made clear that the Mobile-Sierra public interest standard is not an exception to the statutory just-and-reasonable standard; it is an application of that standard in the context of rates set by contract. The “venerable Mobile-Sierra doctrine” rests on “the stabilizing force of contracts.” Morgan Stanley, 554 U. S., at 548; see id., at 551 (describing contract rates as “a key source of stability“). To retain vitality, the doctrine must control FERC
I
In a capacity market, in contrast to a wholesale-energy market, an electricity provider purchases from a generator an option to buy a quantity of energy, rather than purchasing the energy itself. To maintain the reliability of the grid, electricity providers generally purchase more capacity, i. e., rights to acquire energy, than necessary to meet their customers’ anticipated demand. For many years in New England, the supply of capacity was barely sufficient to meеt the region‘s demand. FERC and New England‘s generators, electricity providers, and power customers made several attempts to address this problem. This case stems from the latest effort to design a solution.
In 2003, a group of generators sought to enter into “reliability must-run” agreements with the New England Independent System Operator (ISO), which operates the region‘s transmission system.1 In its orders addressing those agreements, FERC directed the ISO to develop a new market mechanism that would set prices separately for various geographical subregions. Devon Power LLC, 103 FERC ¶ 61,082, pp. 61,266, 61,271 (2003).
In March 2004, the ISO proposed a market structure responsive to FERC‘s directions. See Devon Power LLC, 107 FERC ¶ 61,240, p. 62,020 (2004). FERC set the matter for hearing before an Administrative Law Judge (ALJ), who issued a 177-page order largely accepting the ISO‘s proposal. Devon Power LLC, 111 FERC ¶ 63,063, p. 65,205 (2005). Several parties filed exceptions to the ALJ‘s order; on September 20, 2005, the full Commission heard arguments on the proposed market structure, and thereafter established settlement procedures. Devon Power LLC, 113 FERC ¶ 61,075, p. 61,271 (2005).
After four months of negotiations, on March 6, 2006, a settlement was reached. Of the 115 negotiating parties, only 8 opposed the settlement.
The Settlement Agreement installed a “forward capacity market” under which annual auctions would set capacity prices; auctions would be conducted three years in advance of the time when the capacity would be needed. Devon Power LLC, 115 FERC ¶ 61,340, pp. 62,304, 62,306-62,308 (2006). Each energy provider would be required to purchase enough capacity to meet its share of the “installed capacity requirement,” i. e., the minimum level of capacity needed to maintain reliability on the grid, as determined by the ISO. Id., at 62,307. For the three-year gap between the first auction and the time when the capacity procured in that auction would be provided,2 the Agreement prescribed a series of fixed, transition-period payments to capacity-supplying generators. Id., at 62,308-62,309.
The issue before us centers on § 4.C of the Agreement (hereinafter Mobile-Sierra provision). Under that provision, challenges to both transition-period payments and auction-clearing prices would be adjudicated under “the ‘public interest’ standard
FERC approved the Settlement Agreement, “finding that as a package, it presents a just and reasonable outcome for this proceeding consistent with the public interest.” 115 FERC, at 62,304. The Mobile-Sierra provision, FERC explicitly determined, “appropriately balances the need for rate stability and the interests of the diverse entities who will be subject to the [forward capacity market‘s auction system].” Id., at 62,335.
Six of the eight objectors to the settlement sought reviеw in the D. C. Circuit. For the most part, the Court of Appeals rejected the objectors’ efforts to overturn FERC‘s order approving the settlement. 520 F. 3d, at 467. But the objectors prevailed on the Mobile-Sierra issue: The D. C. Circuit held that Mobile-Sierra applies only to contracting parties. Id., at 478. In this Court, the parties have switched places. Defenders of the settlement, including the Mobile-Sierra provision, are petitioners; objectors to the settlement, victorious in the Court of Appeals only on the Mobile-Sierra issue, are respondents.
Because of the importance of the issue, and in light of our recent decision in Morgan Stanley, we granted certiorari, 556 U. S. 1207 (2009), to resolve this question: “[Does] Mobile-Sierra‘s public-interest standard appl[y] when a contract rate is challenged by an entity that was nоt a party to the contract[?]” Brief for Petitioners i. Satisfied that the answer to that question is yes, we reverse the D. C. Circuit‘s judgment insofar as it rejected application of Mobile-Sierra to noncontracting parties.
II
The FPA gives FERC authority to regulate the “sale of electric energy at wholesale in interstate commerce.” See
The Mobile-Sierra doctrine originated in twin decisions announced on the same day in 1956: United Gas Pipe Line Co. v. Mobile Gas Service Corp., 350 U. S. 332, and FPC v. Sierra Pacific Power Co., 350 U. S. 348. Both concerned rates set by contract rather than by tariff. Mobile involved the Natural Gas Act, which, like the FPA, requires utilities to file all new ratеs with the regulatory commission.
The Sierra case involved a further issue. Not only had the Commission erroneously concluded that a newly filed tariff superseded a contract rate. In addition, the Commission had suggested that, in any event, the contract rate, which the utility sought to escape, was itself unjust and unreasonable. The Commission thought that was so “solely because [the contract rate] yield[ed] less than a fair return on the [utility‘s] net invested capital.” 350 U. S., at 355.
The Commission‘s suggestion prompted this Court to home in on “the question of how the Commission may evaluate whether a contract rate is just and reasonable.” Morgan Stanley, 554 U. S., at 533. The Sierra Court answered the question this way:
“[T]he Commission‘s conclusion appears on its face to be based on an erroneous standard. . . . [W]hile it may be that the Commission may not normally impose upon a public utility a rate which would produce less thаn a fair return, it does not follow that the public utility may not itself agree by contract to a rate affording less than a fair return or that, if it does so, it is entitled to be relieved of its improvident bargain. . . . In such circumstances the sole concern of the Commission would seem to be whether the rate is so low as to adversely affect the public interest—as where it might impair the financial ability of the public utility to continue its service, cast upon other consumers an excessive burden, or be unduly discriminatory.” 350 U. S., at 354-355 (some emphasis added).
In a later case, we similarly explained: “The regulatory system created by the [FPA] is premised on contractual agreements voluntarily devised by the regulated companies; it contemplates abrogation of these agreements only in circumstances of unequivocal public necessity.” Permian Basin Area Rate Cases, 390 U. S. 747, 822 (1968).3
Two Terms ago, in Morgan Stanley, 554 U. S. 527, the Court reaffirmed and clarified the Mobile-Sierra doctrine. That case presented two questions: First, does the Mobile-Sierra presumption (that contract rates freely negotiated between sophisticated parties meet the just-and-reasonable standard imposed by
Answering no to the first question and yes to the second, the Court emphasized the essential
Morgan Stanley did not reach the question presented here: Does Mobile-Sierra‘s public interest standard apply to challenges to contract rates brought by noncontracting parties? But Morgan Stanley‘s reasoning strongly suggests that the D. C. Circuit‘s negative answer misperceives the aim, and diminishes the force, of the Mobile-Sierra doctrine.
In unmistakably plain language, Morgan Stanley restated Mobile-Sierra‘s instruction to the Commission: FERC “must presume that the rate set out in a freely negotiated wholesale-energy contract meets the ‘just and reasonable’ requirement imposed by law. The presumption may be overcome only if FERC concludes that the contract seriously harms the public interest.” 554 U. S., at 530. As our instruction to FERC in Morgan Stanley conveys, the public interest standard is not, as the D. C. Circuit presented it, a standard independent of, and sometimes at odds with, the “just and reasonable” standard, see 520 F. 3d, at 478; rather, the public interest standard defines “what it means for a rate to satisfy the just-and-reasonable standard in the contract context,” Morgan Stanley, 554 U. S., at 546. And if FERC itself must presume just and reasonable a contract rate resulting from fair, arm‘s-length negotiations, how can it be maintained that noncontracting parties nevertheless may escape that presumption?4
Moreover, the Mobile-Sierra doctrine does not overlook third-party interests; it is framed with a view to their protection. The doctrine directs the Commission to reject a contract rate that “seriously harms the consuming public.” Morgan Stanley, 554 U. S., at 545-546; see Verizon Communications Inc. v. FCC, 535 U. S. 467, 479 (2002) (When a buyer and a seller agree upon a rate, “the principal regulatory responsibility [i]s not to relieve a contracting party of an unreasonable rate, . . . but to protect against potential discrimination by favorable contract rates between allied businesses to the detriment of other wholesale customers.” (emphasis added)).
Finally, as earlier indicated, see supra, at 173-174, the D. C. Circuit‘s confinement of Mobile-Sierra to rate challenges by
larly those . . . critical to maintaining reliability.” 115 FERC, at 62,335. A presumption applicable to contracting parties only, and inoperative as to everyone else—consumers, advocacy groups, state utility commissions, elected officials acting parens patriae—could scarcely provide the stability Mobile-Sierra aimed to secure.5
We therefore hold that the Mobile-Sierra presumption does not depend on the identity of the complainant who seeks FERC investigation. The presumption is not limited tо challenges to contract rates brought by contracting parties. It applies, as well, to challenges initiated by third parties.
III
The objectors to the settlement appearing before us maintain that the rates at issue in this case—the auction rates and the transition payments—are prescriptions of general applicability rather than “contractually negotiated rates,” hence Mobile-Sierra is inapplicable. See Brief for Respondents 15-17, and n. 1 (internal quotation marks omitted). FERC agrees that the rates cоvered by the settlement “are not themselves contract rates to which the Commission was required to apply Mobile-Sierra.” Brief for FERC 15. But, FERC urges, “the Commission had discretion to do so,” id., at 28; furthermore, “[t]he court of appeals’ error in creating a third-party exception to the Mobile-Sierra presumption is a sufficient basis for reversing its judgment,” id., at 22. Whether the rates at issue qualify as “contract rates,” and, if not, whether FERC had discretion to treat them analogously are questions raised before, but not ruled upon by, the Court of Appeals. They remain open fоr that court‘s consideration on remand. See Tr. of Oral Arg. 16.
For the reasons stated, the judgment of the Court of Appeals for the D. C. Circuit is reversed to the extent that it rejects the application of Mobile-Sierra to noncontracting parties, and the case is remanded for further proceedings consistent with this opinion.
It is so ordered.
JUSTICE STEVENS, dissenting.
The opinion that the Court announces today is the third chapter in a story about how a reasonable principle, extended beyond its foundation, becomes bad law.
In the first chapter the Court wisely and cоrrectly held that a seller who is a party to a long-term contract to provide energy to a wholesaler could not unilaterally repudiate its contract obligations in response to changes in market conditions by simply filing a new rate schedule with the regulatory commission. Only if the rate was so low that the seller might be unable to stay in business, thereby impairing the public interest, could the seller be excused from
In the second chapter the Court unwisely and incorrectly held that the same rule should apply to a buyer who hаd been forced by unprecedented market conditions to enter into a long-term contract to buy energy at abnormally high prices. The Court held the Federal Energy Regulatory Commission (FERC) could not set aside such a contract as unjust and unreasonable, even though it saddled consumers with a duty to pay prices that would be considered unjust and unreasonable under normal market conditions, unless the purchaser could also prove that “the contract seriously harms the public interest.” Morgan Stanley Capital Group Inc. v. Public Util. Dist. No. 1 of Snohomish Cty., 554 U. S. 527, 530 (2008).
The Court held in Morgan Stanley that Mobile-Sierra established a presumption: FERC “must presume that the rate set out in a freely negotiated wholesale-energy contract meets the ‘just and reasonable’ requirement imposed by law.” 554 U. S., at 530. And that presumption, according to the Court, is a simple application of the just-and-reasonable standard to contract rates, not a different standard of review. Id., at 535 (rejecting the “obviously indefensible proposition that a standard different from the statutory just-and-reasonable standard applies to contract rates“). But applying the presumption nonetheless sets a higher bar for a rate challenge.1 FERC may abrogate the rate only if the public interest is seriously harmed. Id., at 550-551 (“[U]nder the Mobile-Sierra presumption, setting aside a contract rate requires a finding of ‘unequivocal public necessity,‘” Permian Basin Area Rate Cases, 390 U. S. 747, 822 (1968), “or ‘extraordinary circumstances,’ Arkansas Louisiana Gas Co. v. Hall, 453 U. S. 571, 582 (1981)“).
As I explained in my dissent in Morgan Stanley, the imposition of this additional burden on purchasers challenging rates was not authorized by the governing statute. Under the Federal Power Act (FPA), all wholesale electricity rates must be “just and reasonable.”
(STEVENS, J., dissenting). Instead, “the statement in Permian Basin about ‘unequivocal public necessity,’ 390 U. S., at 822, speaks to the difficulty of establishing injury to the public interest in the context of a low-rate challenge,” i. e., one brought by sellers of electricity. Id., at 562. It does not establish a new standard that applies as well to a “high-rate challenge” brought by purchasers. Ibid.
As the D. C. Circuit noted,2 “[c]ourts have rarely mentioned the Mobile-Sierra doctrine without reiterating that it is premised on the existence of a voluntary contract between the parties.” Ibid. But, the Court asks, “if FERC itself must presume just and reasonable a contract rate resulting from fair, arm‘s-length negotiations, how can it be maintained that noncontracting parties nevertheless may escape that presumption?” Ante, at 174-175. This Court‘s under-
standing of Sierra provides an answer. ”Sierra was grounded in the commonsense notion that ‘[i]n wholesale markets, the party charging the rate and the party charged [are] often sophisticatеd businesses enjoying presumptively equal bargaining power, who could be expected to negotiate a “just and reasonable” rate as between the two of them.‘” Morgan Stanley, 554 U. S., at 545 (quoting Verizon Communications Inc. v. FCC, 535 U. S. 467, 479 (2002); emphasis added). This “commonsense notion” supports the rule requiring FERC to apply a presumption against letting a party out of its own contract, as the D. C. Circuit recognized. 520 F. 3d, at 478 (“The Mobile-Sierra doctrine applies a more deferential standard of review to preserve the terms of the bargain as between the contracting parties“). It does not, however, support a rule requiring FERC to aрply a presumption against abrogating any rate set by contract, even when, as in this case, a noncontracting party may be required in practice to pay a rate it did not agree to.
The Court further reasons that “confinement of Mobile-Sierra to rate challenges by contracting parties diminishes the animating purpose of the doctrine,” which is ensuring the stability of contract-based supply arrangements. Ante, at 175. Maybe so, but applying Mobile-Sierra to rate challenges by noncontracting parties loses sight of the animating purpose of the FPA, which is “the protection of the public interest.” Sierra, 350 U. S., at 355. That interest is “thе interest of consumers in paying ‘the “lowest possible reasonable rate consistent with the maintenance of adequate service in the public interest.“‘” Morgan Stanley, 554 U. S., at 561 (STEVENS, J., dissenting) (quoting Permian Basin, 390 U. S., at 793). I do not doubt that stable energy markets are important to the public interest, but “under the FPA, Congress has charged FERC, not the courts, with balancing the short-term
today imposes additional limits upon FERC‘s ability to protect that interest. If a third-party wholesale buyer can show a rate harms the public interest (perhaps because it is too high to be just and reasonable under normal review), but cannot show it seriously harms the public, FERC may do nothing about it.3
The Court assures respondents that the “public interest standard” does not “overlook third-party interests” and is “framed with a view to their protection.” Ante, at 174, 175. Perhaps in practice the Mobile-Sierra doctrine will protect third parties’ interests, and the public interest, just as well as the so-called “ordinary” just-and-reasonable standard. But respondents are rightly skeptical. The Mobile-Sierra doctrine, as interpreted by the Court in Morgan Stanley, must pose a higher bar to respondents’ rate challenge—that is, it requires them to show greater harm tо the public.4
Otherwise, it would hardly serve to protect contract stability better than the plain vanilla just-and-reasonable standard and the Court‘s decision in Morgan Stanley would have little effect. Furthermore, the Court today reiterates that the doctrine poses a high bar. See ante, at 173-174.
It was sensible to require a contracting party to show something more than its own desire to get out of what proved to be a bad bargain before FERC could abrogate the parties’ bargain. It is not sensible, nor authorized by the statute, for the Court to change the de facto standard of review whenever a rate is set by private
For these reasons, I respectfully dissent.
Notes
Briefs of amici curiae urging affirmance were filed for the American Public Power Associatiоn et al. by Scott H. Strauss, Susan N. Kelly, Wallace F. Tillman, and Richard Meyer; for Public Citizen, Inc., et al. by Scott L. Nelson, Lynn Hargis, and Barbara Jones; and for the California Public Utilities Commission by Kevin K. Russell, Frank R. Lindh, Elizabeth M. McQuillan, and Karen P. Paull.
