History
  • No items yet
midpage
57 Cal.App.5th 480
Cal. Ct. App.
2020
Read the full case

Background

  • California law authorized job order contracting (JOC): competitively bid master contracts with incorporated General Conditions and a construction task catalog; individual job orders (or proposals) set scope/price using fixed unit prices and bidder adjustment factors.
  • Torres won multiple LAUSD JOCs and received 19 Phase I, 18 Phase II and 18 Phase III job orders for the Café LA school cafeteria modernization; Western Surety bonded Torres’ performance.
  • LAUSD audited Torres’ job orders (final audit Oct. 24, 2011) and found improper pricing methods and overbilling across phases (incorrect use of NPP pricing, wrong markups, and billing for unperformed/oversized electrical work).
  • LAUSD sued Torres and Western for breach of contract and on the payment/performance bonds; the trial court granted summary adjudication on all Phase I and many Phase II orders, directed verdicts on many Phase III orders, and a jury decided the remainder.
  • Judgment awarded LAUSD roughly $3.94 million in damages (net recovery ~$4.56M after offsets, interest, costs) and $2.1 million in attorney fees against Western; appellants appealed raising contract-formation, evidentiary, offset, statutory-condition, waiver, surety-defense, prejudgment-interest, and fee-adequacy claims.

Issues

Issue Plaintiff's Argument (LAUSD) Defendant's Argument (Torres/Western) Held
Whether a JOC is an enforceable contract or merely an agreement to negotiate JOCs (with detailed General Conditions and catalog) set all material terms except project-specific Scope of Work; proposals/JOs fix price so JOCs support expectation damages JOCs are preliminary agreements to negotiate; only signed Job Orders (final agreements) can support breach/damages JOCs are binding contracts incorporating detailed terms and pricing formulas; denial of summary judgment affirmed
Admissibility of LAUSD’s “gap‑filler” reply evidence (proposal submission printouts) on summary adjudication Reply evidence filled gaps about proposal submission dates and revised damages; court may consider such evidence if opposing party had opportunity to respond Admission deprived defendants of due process and shifted theories Trial court did not abuse discretion; reply gap‑filler evidence properly considered
Whether Torres’ setoff/offset claims create triable issue defeating summary adjudication Offsets concern distinct withheld payments on other jobs and should reduce LAUSD’s recovery Offsets create uncertainty in LAUSD’s damages and require adjudication before summary relief Offsets are equitable/end‑of‑case matters and do not defeat summary adjudication of LAUSD’s claims; trial court acted properly
Whether LAUSD’s failure to prepare independent district estimates was a condition precedent excusing Torres’ performance Statutory §20919.11 requires independent estimates before job orders; LAUSD’s failure excuses Torres or prevents recovery The contractor’s duty to price proposals correctly is independent (statute not phrased as condition precedent); LAUSD performed/issued job orders Independent estimate is not a condition precedent to contractor pricing duty; appellants forfeited new arguments; summary adjudication proper
Waiver: did LAUSD’s conduct (issuing/approving job orders) waive pricing/formula rights LAUSD accepted job orders and thus waived enforcement of General Conditions pricing rules Job Orders preempt inconsistent terms only in writing; LAUSD’s anti‑waiver clause and audit rights preserve enforcement No triable waiver issue: public‑works rules and anti‑waiver clause bar broad waiver of statutorily central pricing formulas
Surety defenses — statute of limitations, notice to surety, recoverability of damages under bond Western: bonds contain limitations periods; no pre‑suit notice to surety; claimed damages are overpayments not recoverable under bond LAUSD: surety liable on contractor default immediately under Civil Code absent specific bond notice term; audit provisions and bond language incorporate contract guarantees Western forfeited many record citations; Civil Code makes surety liable upon principal default absent contractual notice; overpayment/premature‑payment theory not shown to bar recovery; directed‑verdict denials affirmed
Prejudgment interest: whether damages were sufficiently certain and timing appropriate Appellants: damages were uncertain (required expert or judicial re‑writing) and offsets make amounts uncertain; interest should start no earlier than complaint LAUSD: damages were calculable by arithmetic from audit adjustments; offsets don’t defeat certainty for Civil Code §3287(a) Prejudgment interest award affirmed; damages were capable of calculation and offsets don’t negate certainty for interest purposes
Attorney fees award sufficiency and process (redacted billing) LAUSD: fee request supported by lead counsel declaration and billing records; trial judge familiar with case and reduced fees modestly Western: redactions and lack of detail prevented meaningful challenge and denied due process; court rubber‑stamped fee Trial court did not abuse discretion; judge’s familiarity, hearing, and a 13% reduction of miscellaneous entries supported reasonableness

Key Cases Cited

  • Wiener v. Southcoast Childcare Ctrs., 32 Cal.4th 1138 (review of summary judgment standards)
  • Buss v. Superior Court, 16 Cal.4th 35 (summary judgment/judgment on pleadings standards)
  • Copeland v. Baskin‑Robbins U.S.A., 96 Cal.App.4th 1251 (damages for agreements to negotiate are limited to reliance)
  • Amelco Elec. v. City of Thousand Oaks, 27 Cal.4th 228 (limits on modifying public‑works contracts)
  • Ghilotti Constr. Co. v. City of Richmond, 45 Cal.App.4th 897 (public entity waiver limited to inconsequential deviations)
  • Cates Constr. v. Talbot Partners, 21 Cal.4th 28 (context on owner payments/premature payment issues)
  • R.P. Richards, Inc. v. Chartered Constr. Corp., 83 Cal.App.4th 146 (settlement/release can exonerate surety)
  • Syers Props. III, Inc. v. Rankin, 226 Cal.App.4th 691 (abuse‑of‑discretion standard for fee awards)
  • Yanowitz v. L’Oreal USA, 36 Cal.4th 1028 (exclude evidence not before trial court on summary judgment)
Read the full case

Case Details

Case Name: Los Angeles Unified etc. v. Torres Construction CA2/8
Court Name: California Court of Appeal
Date Published: Oct 26, 2020
Citations: 57 Cal.App.5th 480; 271 Cal.Rptr.3d 523; B291940
Docket Number: B291940
Court Abbreviation: Cal. Ct. App.
Log In
    Los Angeles Unified etc. v. Torres Construction CA2/8, 57 Cal.App.5th 480