57 Cal.App.5th 480
Cal. Ct. App.2020Background
- California law authorized job order contracting (JOC): competitively bid master contracts with incorporated General Conditions and a construction task catalog; individual job orders (or proposals) set scope/price using fixed unit prices and bidder adjustment factors.
- Torres won multiple LAUSD JOCs and received 19 Phase I, 18 Phase II and 18 Phase III job orders for the Café LA school cafeteria modernization; Western Surety bonded Torres’ performance.
- LAUSD audited Torres’ job orders (final audit Oct. 24, 2011) and found improper pricing methods and overbilling across phases (incorrect use of NPP pricing, wrong markups, and billing for unperformed/oversized electrical work).
- LAUSD sued Torres and Western for breach of contract and on the payment/performance bonds; the trial court granted summary adjudication on all Phase I and many Phase II orders, directed verdicts on many Phase III orders, and a jury decided the remainder.
- Judgment awarded LAUSD roughly $3.94 million in damages (net recovery ~$4.56M after offsets, interest, costs) and $2.1 million in attorney fees against Western; appellants appealed raising contract-formation, evidentiary, offset, statutory-condition, waiver, surety-defense, prejudgment-interest, and fee-adequacy claims.
Issues
| Issue | Plaintiff's Argument (LAUSD) | Defendant's Argument (Torres/Western) | Held |
|---|---|---|---|
| Whether a JOC is an enforceable contract or merely an agreement to negotiate | JOCs (with detailed General Conditions and catalog) set all material terms except project-specific Scope of Work; proposals/JOs fix price so JOCs support expectation damages | JOCs are preliminary agreements to negotiate; only signed Job Orders (final agreements) can support breach/damages | JOCs are binding contracts incorporating detailed terms and pricing formulas; denial of summary judgment affirmed |
| Admissibility of LAUSD’s “gap‑filler” reply evidence (proposal submission printouts) on summary adjudication | Reply evidence filled gaps about proposal submission dates and revised damages; court may consider such evidence if opposing party had opportunity to respond | Admission deprived defendants of due process and shifted theories | Trial court did not abuse discretion; reply gap‑filler evidence properly considered |
| Whether Torres’ setoff/offset claims create triable issue defeating summary adjudication | Offsets concern distinct withheld payments on other jobs and should reduce LAUSD’s recovery | Offsets create uncertainty in LAUSD’s damages and require adjudication before summary relief | Offsets are equitable/end‑of‑case matters and do not defeat summary adjudication of LAUSD’s claims; trial court acted properly |
| Whether LAUSD’s failure to prepare independent district estimates was a condition precedent excusing Torres’ performance | Statutory §20919.11 requires independent estimates before job orders; LAUSD’s failure excuses Torres or prevents recovery | The contractor’s duty to price proposals correctly is independent (statute not phrased as condition precedent); LAUSD performed/issued job orders | Independent estimate is not a condition precedent to contractor pricing duty; appellants forfeited new arguments; summary adjudication proper |
| Waiver: did LAUSD’s conduct (issuing/approving job orders) waive pricing/formula rights | LAUSD accepted job orders and thus waived enforcement of General Conditions pricing rules | Job Orders preempt inconsistent terms only in writing; LAUSD’s anti‑waiver clause and audit rights preserve enforcement | No triable waiver issue: public‑works rules and anti‑waiver clause bar broad waiver of statutorily central pricing formulas |
| Surety defenses — statute of limitations, notice to surety, recoverability of damages under bond | Western: bonds contain limitations periods; no pre‑suit notice to surety; claimed damages are overpayments not recoverable under bond | LAUSD: surety liable on contractor default immediately under Civil Code absent specific bond notice term; audit provisions and bond language incorporate contract guarantees | Western forfeited many record citations; Civil Code makes surety liable upon principal default absent contractual notice; overpayment/premature‑payment theory not shown to bar recovery; directed‑verdict denials affirmed |
| Prejudgment interest: whether damages were sufficiently certain and timing appropriate | Appellants: damages were uncertain (required expert or judicial re‑writing) and offsets make amounts uncertain; interest should start no earlier than complaint | LAUSD: damages were calculable by arithmetic from audit adjustments; offsets don’t defeat certainty for Civil Code §3287(a) | Prejudgment interest award affirmed; damages were capable of calculation and offsets don’t negate certainty for interest purposes |
| Attorney fees award sufficiency and process (redacted billing) | LAUSD: fee request supported by lead counsel declaration and billing records; trial judge familiar with case and reduced fees modestly | Western: redactions and lack of detail prevented meaningful challenge and denied due process; court rubber‑stamped fee | Trial court did not abuse discretion; judge’s familiarity, hearing, and a 13% reduction of miscellaneous entries supported reasonableness |
Key Cases Cited
- Wiener v. Southcoast Childcare Ctrs., 32 Cal.4th 1138 (review of summary judgment standards)
- Buss v. Superior Court, 16 Cal.4th 35 (summary judgment/judgment on pleadings standards)
- Copeland v. Baskin‑Robbins U.S.A., 96 Cal.App.4th 1251 (damages for agreements to negotiate are limited to reliance)
- Amelco Elec. v. City of Thousand Oaks, 27 Cal.4th 228 (limits on modifying public‑works contracts)
- Ghilotti Constr. Co. v. City of Richmond, 45 Cal.App.4th 897 (public entity waiver limited to inconsequential deviations)
- Cates Constr. v. Talbot Partners, 21 Cal.4th 28 (context on owner payments/premature payment issues)
- R.P. Richards, Inc. v. Chartered Constr. Corp., 83 Cal.App.4th 146 (settlement/release can exonerate surety)
- Syers Props. III, Inc. v. Rankin, 226 Cal.App.4th 691 (abuse‑of‑discretion standard for fee awards)
- Yanowitz v. L’Oreal USA, 36 Cal.4th 1028 (exclude evidence not before trial court on summary judgment)
