Lead Opinion
Opinion
In this case we determine whether the abandonment theory of liability applies against a public agency, and whether plaintiff public works contractor, which sued for breach or abandonment of the public works contract, is entitled to compensation under a total cost method of measuring damages. The jury found the contract was breached and abandoned, and awarded total cost damages. The Court of Appeal affirmed. We conclude the
I. Factual and Procedural Background
In 1992, defendant City of Thousand Oaks (City) solicited bids for electrical work to be performed in the construction of the Civic Arts Plaza, a project including a civic center or office building, a dual-purpose 400-seat council chamber and forum theater, an 1,800-seat civic auditorium or performing arts theater, and an outside area (the project). Instead of a general contractor, the project was managed by Lehrer McGovern Bovis, Inc. (LMB), and the City solicited bids for the various prime contracts. City received five electrical work bids. Amelco Electric (Amelco), one of the largest electrical contractors in the United States, bid $6,158,378, and was awarded the contract. All five bids came within 10 percent of each other and the three lowest bids were within 3 percent of each other.
During the two-year construction process, City furnished 1,018 sequentially numbered sketches to the various contractors to clarify or change the original contract drawings, or to respond to requests for information. The vast majority of the changes were to one building, the civic center or office building, and to the outside lighting. Of the sketches issued, 248 affected the electrical cost. Amelco requested 221 change orders, and City and Amelco agreed upon 32 change orders encompassing these change order requests. As a result of these change orders, City paid Amelco $1,009,728 above the contract price, an increase of nearly 17 percent.
Amelco claimed at trial that the project involved an unusually high number of sketches that were difficult to work with. Amelco further claimed that scheduling the various contractors’ work became more difficult as a result of the changes. Amelco testified it was at times required to delay or accelerate particular tasks and to shift workers among tasks to accommodate work by other trades. While Amelco maintained daily records of its work activities, it was unable to produce documentation of instances in which its performance of a work directive or change order was delayed or interfered with by LMB’s actions, and for which it was not compensated. The general foreman, the person responsible for actually recording the information, was given a hypothetical regarding recordkeeping practices: “[I]f you came to this courtroom to work today, . . . and the wall was moved, that would be something you would put in your daily log?” “No.” “You wouldn’t note that?” “I wouldn’t put it down on my daily log.”
In May 1993, Amelco wrote to LMB concerning “Work Directive 48, addendum No. 1,” which Amelco asserted improperly shifted engineering documentation responsibilities to Amelco. Amelco also expressed concern that the electrical drawings being issued did not identify all revisions, or contain all prior revisions, and gave examples of how these omissions interfered with its performance. Amelco requested a change order and $203,759 in additional funds to hire a drafter to update the drawings, a foreperson, and a project engineer. LMB refused additional funds on the ground that these tasks were included in the original contract price. Amelco claimed at trial that it accepted this decision, did not hire any additional personnel to do the work, and signed a change order for zero dollars and zero additional time, because LMB verbally promised that “things are going to get better.”
On July 29, 1994, over a year later, and approximately two months before the project was completed, Amelco sent a letter requesting a second change order be issued for Work Directive No. 48. Amelco asserted the executed change order did “not include any field productive labor impact or related problems,” and that “[t]he price for this work will follow in the near future.”
In January 1995, Amelco submitted a $1.7 million total cost claim for costs allegedly resulting from the noncaptured costs of the change orders. The testimony was in conflict whether LMB had requested that Amelco submit such a claim; in any event, the claim was rejected. Amelco filed this action, ultimately alleging abandonment and breach of the construction contract. By the time of trial, Amelco’s claim had increased to $2,224,842 because of the discovery of additional costs.
The City asserted Amelco lost money on the project because it failed to start work promptly on the project, did not coordinate its work with other trades, such as by regularly attending mandatory coordination meetings, reduced its workforce so that it did not have enough workers to install the major electrical system components efficiently, did not have an organized manner of incorporating changes into the drawings (unlike other contractors on the project), performed work on the project under at least one subcontract for a different subcontractor during this period, and generally mismanaged its work.
The Court of Appeal affirmed. As relevant here, it concluded that as a matter of law a public works contract can be abandoned, and the jury was properly instructed on the measure of damages.
We granted the City’s petition for review.
II. Discussion
A. Does the Abandonment Theory of Liability Apply Against a Public Entity?
1. Background
In general, under long-standing California law, if a public contract is declared void, a contractor may not be paid for work performed under that contract. (Miller v. McKinnon (1942)
Similarly, this court has not generally allowed quantum meruit recovery for extra work performed beyond the contract requirements. (Zottman v. San Francisco (1862)
We affirmed on the ground the city charter authorized only a contract given to the lowest bidder. (Zottman, supra, 20 Cal. at pp. 103, 108.) “A contract made in disregard of these stringent but wise provisions cannot be the ground of any claim against the city. . . . The mode in which [the Common Council] could bind the [municipal] corporation by a contract for the improvement of city property was prescribed by the charter, and no validity could be given by them to a contract made in any other manner.” (Id. at pp. 101-102.) We observed, “ ‘It may sometimes seem a hardship upon a contractor that all compensation for work done, etc., should be denied him; but it should be remembered that he, no less than the officers of the corporation, when he deals in a matter expressly provided for in the charter, is bound to see to it that the charter is complied with. If he neglect[s] this, or choose[s] to take the hazard, he is a mere volunteer, and suffers only what he ought to have anticipated. If the statute forbids the contract which he has made, he knows it, or ought to know it, before he places his money or services at hazard.’ ” (Id. at pp. 104-105; Los Angeles Dredging Co. v. Long Beach (1930)
The question in this case is whether a public entity is liable under an abandonment theory to a contractor when it makes numerous changes to the contract work, and these changes allegedly make it difficult and more costly to perform the contract because of delay, interference with the work of other trades, and other problems not captured in the price of the executed change orders. In California, the Courts of Appeal have concluded that private parties may impliedly abandon a contract when they fail to follow change order procedures and when the final product differs substantially from the original. (Opdyke & Butler v. Silver (1952)
In C. Norman Peterson Co. v. Container Corp. of America (1985)
On appeal, the court affirmed the judgment entered in CNP’s favor. It noted, a construction contract is abandoned “when an owner imposes upon the contractor an excessive number of changes such that it can fairly be said that the scope of the work under the original contract has been altered.” (Peterson, supra,
In Peterson, there were “hundreds of changes, many of them significant, resulting in extra work having to be performed by CNP. As in Opdyke, the requirement for written change orders was ignored during most of the project period, and it was completely abandoned during the critical shutdown stage.” (Peterson, supra,
The Court of Appeal also upheld the trial court’s further finding that CCA had breached the contract. (Peterson, supra, 172 Cal.App.3d at pp. 642-644.) “[R]ather than being inconsistent with abandonment, . . . breaches by CCA
Dodge v. Harbor Boat Bldg. Co. (1950)
The Court of Appeal affirmed, noting there was an implicit “determination by the trial court that the value of the work done by National Ship provided a proper basis for a judgment in its favor and that it was unnecessary to sue on the original contract.” (Dodge, supra,
Hence, in Dodge, it appears the contractor carefully delineated its $79,592.65 in costs (Dodge, supra, 99 Cal.App.2d at p. 789) from the extra work requested by Harbor Boat that was “ ‘different from the original specifications or not specified at all.’ ” (Id. at p. 787.) Harbor Boat was paid for that and its own extra work, but failed to pass on any portion of the Navy’s payment to National Ship. This obvious inequity does not suggest the Court of Appeal concluded the contract was abandoned, but rather that National Ship was found to be entitled to payment for at least a portion of the authorized extra work. Indeed, the Court of Appeal noted that “a
The United States Federal Court of Claims has historically recognized government breach of contract liability under the doctrine of cardinal change. Here, Amelco asserts the abandonment doctrine is coextensive with the cardinal change doctrine. In fact, the theories are fundamentally different. Under Opdyke and Peterson, once the parties cease to follow the contract’s change order process, and the final project is materially different from the project contracted for, the contract is deemed inapplicable or abandoned and is set aside. The plaintiff may then recover the reasonable costs for all of its work. (Peterson, supra,
Under the cardinal change doctrine, the cardinal change “constitutes a material breach of the contract.” (Alliant Techsystems, Inc. v. U.S. (Fed.Cir. 1999)
2. Analysis
We now consider whether the abandonment theory of liability applies against a public entity. We conclude it does not, since such a theory
Under the abandonment doctrine, once the parties cease to follow the contract’s change order process, and the final project has become materially different from the project contracted for, the entire contract—including its notice, documentation, changes, and cost provisions—is deemed inapplicable or abandoned, and the plaintiff may recover the reasonable value for all of its work. Were we to conclude such a theory applied in the public works context, the notion of competitive bidding would become meaningless.
Even assuming there is substantial evidence of abandonment in this case, the entire notion of the parties abandoning a public works contract, with its strict statutory requirements, is anomalous. General law cities, such as the City of Thousand Oaks, are statutorily required to award public contracts in excess of $5,000 to the lowest responsible bidder. (Pub. Contract Code, § 20162.) We have generally not allowed recovery on a quantum meruit basis where there is a defect in the bidding rendering the contract void. (Miller, supra,
“[I]t is clear ‘that neither the doctrine of estoppel nor any other equitable principle may be invoked against a governmental body where it would operate to defeat the effective operation of a policy adopted to protect the public.’ ” (Kajima/Ray Wilson v. Los Angeles County Metropolitan Transportation Authority (2000)
Moreover, allowing a contractor to claim, following completion of the work, that the parties implicitly set aside a public works contract implicates significant public policy concerns. Under the abandonment doctrine, the plaintiff need not demonstrate—and even now Amelco cannot state—at what point the contract was abandoned. As one of Amelco’s experts testified, “So there’s no one point in time where Amelco could have sat back and said, gee, they’ve abandoned the contract, except maybe at the end when they got all their costs together and they looked back and said, wow, what just happened to us. And I guess that’s when they knew it was abandoned.” Amelco’s project manager did not even determine Amelco had a claim on the project until November 1994, after the work was completed. Under Amelco’s approach, a certain number of changes may be permissible, but at some indeterminate point, the next requested change makes the number “excessive,” the competitively bid contract is set aside, and the contractor recovers on a quantum meruit basis from the beginning of the project onward. Such a vague definition fails to provide any meaningful guidance as to when that line has been crossed. Public entities would not receive timely notice of claims that would allow them to make project management, budget, or procedural adjustments during the course of construction. Rather, contractors would be permitted to wait until a project was completed before giving notice of “too many” changes, thus creating intolerable uncertainty in the budgeting and financing of construction projects.
In addition, allowing contractors to recover in quantum meruit for the actual as opposed to the bid cost of a project would encourage contractors to bid unrealistically low, with the hope of prevailing on an abandonment claim, based on the numerous changes inherent in any large public works project. One of the purposes of the public contracting laws is to prevent collusion and favoritism in selecting contractors. (Pub. Contract Code, § 100, subd. (d) [Legislature’s intent in enacting Public Contract Code includes “eliminat[ing] favoritism, fraud, and corruption in the awarding of public contracts”].) One can imagine a situation where a friend of a public official bids extremely low, with tire understanding that numerous changes in the contract, many perhaps not even affecting the contractor, will be forthcoming. Such scenarios would simply provide an end run around the public works bidding requirements. Moreover, if abandonment is recognized as a theory of recovery for public works, “the possibility of significant monetary
Public Contract Code section 7105 provides in part that a public works contract required to be awarded by competitive bid, “may be terminated, amended, or modified only if the termination, amendment, or modification is so provided in the contract or is authorized under provision of law other than this subdivision. The compensation payable, if any, for amendments and modifications shall be determined as provided in the contract. The compensation payable, if any, in the event the contract is so terminated shall be determined as provided in the contract or applicable statutory provision providing for the termination.” (Pub. Contract Code, § 7105, subd. (d)(2).)
Amelco contends Public Contract Code section 7105 applies only to compensation for termination, amendment, or modification of a contract, not to damages for its abandonment. Under the abandonment theory, however, the original contract is set aside and the contractor paid for the reasonable value of its work. It is difficult to understand how such a radical change is not a modification or termination of the public contract subject to section 7105. Indeed, given a public works project must generally be governed by a valid contract, abandonment cannot be one of the changes “authorized under provision of law” contemplated by section 7105.
Amelco observes Civil Code section 3262, pertaining to mechanic’s liens, was amended in 1993 to include “abandonment” in subdivision (d)(1) and (2). Subdivision (d)(1) and (2) specifies that waiver and release forms required from a contractor to receive progress payments must contain substantially the following language: “This release of any mechanic’s lien, stop notice, or bond right shall not otherwise affect the contract rights, including rights between parties to the contract based upon a rescission, abandonment, or breach of the contract, or the right of the undersigned to recover compensation for furnished labor, services, equipment, or material covered by this release if that furnished labor, services, equipment, or material was not compensated by the progress payment.” (Italics added.) Amelco argues that by this amendment, “the Legislature has clearly recognized the doctrine of abandonment in the construction contract context.” Asserting Civil Code section 3262 is applicable to both private and public contracts, Amelco argues it evidences a legislative intent “that abandonment claims are valid against public agencies and not inconsistent with the statutory competitive bidding scheme it created.”
It is not clear what the Legislature meant in amending the sample forms in Civil Code section 3262. The amended language does not, however, ineluctably mean the Legislature is endorsing the abandonment theory for public
While Amelco relies on California abandonment cases, such as Opdyke, supra,
Amelco also asserts the City is liable for a breach of its agreement in the same manner as a private party. That is correct, and in this case the jury found the City had breached the contract. Recovery for a specific breach, however, with its requirements of causation and damages, is far different from abandonment, in which the entire competitively bid contract is set aside, and the contractor recovers on a quantum meruit basis from the beginning of the project onward.
The dissenting opinion broadly refers to “the rule usually applied in this country.” (Dis. opn. of Werdegar, J., post, at p. 251.) It cites, however, no out-of-state or federal authority upholding the abandonment doctrine in the public works context. Rather, it relies solely on the cardinal change doctrine, which, as we have already described, is materially different from abandonment. (See ante, p. 238.)
B. Measure of Damages
We next consider whether Amelco adduced sufficient evidence to warrant instructing the jury on the total cost method of measuring damages. The City does not argue total cost recovery is never appropriate against a public agency, only that such a damages theory is inappropriate here. For this reason, we do not determine whether total cost damages are ever appropriate in a breach of public contract case, but rather whether the theory for such damages was in this case properly submitted to the jury.
Nor does the City challenge the jury’s finding of breach of contract; rather, it challenges only the manner in which damages were calculated. In particular, it asserts that in order to proceed on a total cost theory Amelco
1. Background
Under a breach of contract theory, the plaintiff must demonstrate a contract, the plaintiff’s performance or excuse for nonperformance, the defendant’s breach, and damage to the plaintiff. (4 Witkin, Cal. Procedure (4th ed. 1997) Pleading, § 476, p. 570.) “ ‘Contract damages are generally limited to those within the contemplation of the parties when the contract was entered into or at least reasonably foreseeable by them at that time; consequential damages beyond the expectation of the parties are not recoverable. [Citations.] This limitation on available damages serves to encourage contractual relations and commercial activity by enabling parties to estimate in advance the financial risks of their enterprise.’ ” (Erlich v. Menezes (1999)
The total cost method of determining damages is generally disfavored. (Servidone, supra,
In Boyajian v. United States (Ct.Cl. 1970)
Likewise in Huber, Hunt & Nichols, Inc. v. Moore (1977)
2. Analysis
We conclude Amelco failed to adduce substantial evidence to warrant instructing the jury on the four-part total cost theory of damages. In particular, Amelco failed to adduce evidence to satisfy at least the fourth element of the four-part test, i.e., that it was not responsible for the added expenses. A corollary of this element of the test is that the contractor must demonstrate the defendant, and not anyone else, is responsible for the additional cost. (S. W. Electronics & Mfg. Corp. v. United States (Ct.Cl. 1981)
Here, as in Boyajian, supra,
Nor did Amelco demonstrate when any particular breach occurred. Rather, it sought to recover all of its costs over the life of the contract if the jury found at any undetermined point the contract had been breached.
Amelco asserts we have applied the total cost method in cases involving breach of the implied warranty of correctness, citing Warner Constr. Corp. v. City of Los Angeles (1970)
Amelco asserts that even if the jury should have been instructed on the four-part total cost test, that error was harmless because these factors were adequately covered by other instructions. As we view the City’s contention, however, the issue is whether the jury should have been instructed on the theory of total cost damages at all.
In any event, we disagree the jury was sufficiently guided by the totality of the instructions that damages had to be linked to a particular breach by the City. The jury was instructed, “If you find that the City breached or abandoned the contract, then Amelco is entitled to recover the reasonable value of the work performed by it less the payments made by the City, and less any costs incurred by Amelco which are not fairly attributable to the City.” Under such global instruction, caused in part by the misinstruction on
Amelco also asserts that if we fail to uphold the total cost method here, “[pjublic entities [will] be motivated to change, mismanage and disrupt problem projects as much as possible to make it impossible for a contractor to determine the separate cost of each distinct change.” Here, Amelco has simply failed to demonstrate the existence of such impossibility.
Under these circumstances, the jury should not have been instructed to calculate Amelco’s loss from any breach of contract under a total cost measure of damages.
Disposition
The judgment of the Court of Appeal is reversed, and the part regarding breach of contract is remanded to the Court of Appeal with instructions to remand to the trial court for a retrial on the issue of damages.
George, C. J., Baxter, J., Chin, J., and Moreno, J., concurred.
Notes
The jury was instructed regarding the breach of contract claim, “By furnishing plans and specifications to bidders on a construction project, the owner thereby warrants that the plans and specifications are reasonably accurate and suitable for their intended purpose.” “The City breached the contract if the City provided important facts about the project to Amelco, at bid time, such as in the plans or specifications, which Amelco relied upon, but the City: 1. Failed to disclose other material facts which materially qualified the facts which were disclosed; or 2. Failed to disclose other material facts, the absence of which made the facts disclosed likely to mislead Amelco; or 3. Failed to disclose other material facts which were known or accessible only to the City, and which the City knew were not known by Amelco, [and] not reasonably discoverable by Amelco.” The City “breached the contract if [it] prevented or hindered plaintiff[’s] . . . performance of the contract.” In addition, the jury was instructed, “Amelco claims the City breached and/or abandoned the contract by doing the following: 1. Providing an inadequate design; 2. Making excessive changes to the project; 3. Making changes in a disorganized manner; 4. Failing to properly coordinate the work of the multiple prime contractors; 5. Accelerating Amelco’s work; and 6. Failing to make payments to Amelco in a timely manner.”
“If you find that the City breached or abandoned the contract, then Amelco is entitled to recover the reasonable value of the work performed by it less the payments made by the City, and less any costs incurred by Amelco which are not fairly attributable to the City.” “The measure of damages for the breach of contract is that amount which will compensate the injured party for all the detriment or loss caused by the breach, or which in the ordinary course of things, would [be] likely to result therefrom. The injured party should receive those damages naturally arising from the breach, or those damages which might have been reasonably contemplated or foreseen by both parties, at the time they made the contract, as the probable result of the breach. As nearly as possible, the injured party should receive the equivalent of the benefits of performance. HD Damages must be reasonable. A party cannot receive a greater amount as damages than he could have gained by full performance of the contract.” “[0]nce a Plaintiff . . . proves that it is reasonably certain that it has suffered a particular loss or type of harm as a result of the breach by the Defendant. . . , the law does not require Plaintiff ... to prove the exact amount of that loss or harm.” “[Y]ou may not award any damages for a loss or harm resulting from a breach of contract if Defendant proves that Plaintiff could have avoided that loss or harm by making reasonable efforts or expenditures once it became aware of the breach.”
Dissenting Opinion
It has long been the rule in this state,
Until today, no court, state or federal, has limited this doctrine only to contractors and builders that contract with a private owner. Nor, indeed, is this defendant City of Thousand Oaks’ (the City) main argument, as the City primarily urges us to abolish the doctrine in its entirety.
I begin by setting forth the general rules applicable to public contracts. Public Contract Code section 20162, which is applicable to cities such as the City, provides that “[w]hen the expenditure required for a public project exceeds five thousand dollars ($5,000), it shall be contracted for and let to the lowest responsible bidder after notice.” It is undisputed that plaintiff Amelco Electric (Amelco) participated in the bidding and was the lowest responsible bidder for the project at issue in this case.
Civil Code section 1635 is also relevant. It provides: “All contracts, whether public or private, are to be interpreted by the same rules, except as
The general rule applicable to construction contracts with public entities thus requires that we treat a public entity such as the City the same as any other contracting party once the public bidding process has terminated and a valid contract has been awarded. The majority’s reliance on Miller v. McKinnon (1942)
As the majority recognizes, the general rule in California is that “[i]n the specific context of construction contracts, . . . when an owner imposes upon the contractor an excessive number of changes such that it can fairly be said that the scope of the work under the original contract has been altered, an abandonment of contract properly may be found. [Citations.] In these cases, the contractor, with the full approval and expectation of the owner, may complete the project. [Citation.] Although the contract may be abandoned, the work is not.” (Peterson, supra,
Setting aside the majority opinion’s complete absence of supporting legal precedent, I am also unpersuaded by the majority’s sole supporting rationale that permitting Amelco to recover against a public entity will render competitive bidding laws “meaningless.” (Maj. opn., ante, at p. 239.) Although circumvention of competitive bidding laws is a concern, no facts in this case suggest Amelco somehow evaded the applicable competitive bidding laws. Instead, viewing the facts in a light favorable to Amelco, the prevailing party below (Bickel v. City of Piedmont (1997)
Moreover, the majority’s argument that applying the abandonment doctrine against a public entity like the City “would encourage contractors to bid unrealistically low, with the hope of prevailing on an abandonment claim,” (maj. opn., ante, at p. 240) is fallacious. To believe a contractor would deliberately submit an abnormally low bid in hopes of obtaining a job and, once obtaining it, would expend the time and expense of completing'it, with the intention of thereafter incurring the high cost—in dollars, delay and inconvenience—of modem litigation to recoup several years later its additional expenses, defies common sense. Such a hypothetical contractor, moreover, would also have to hope the public entity would make so many substantial changes to the original project that a plausible claim of abandonment could be made. Were insufficient changes imposed, the contractor would simply be left to bear the losses of its below-market bid. The dearth of cases asserting abandonment (see fn. 5, ante) bespeaks the difficulty of establishing it. The majority’s argument ignores practicality.
Contrary to the majority’s view that recognition of the abandonment doctrine in the context of public contracts would compromise the public welfare, the doctrine may be seen actually to benefit the public. First, its recognition would deter public entities from prematurely putting a project out to bid, motivating them instead, as the Court of Appeal reasoned, first to determine what they want built, with adequate plans and specifications so that intelligent competitive bidding can take place. By this, the public as well as the contracting agency and contractors would benefit. Second, its availability would allow a contractor faced with a project whose very character has been altered by excessive changes to finish the project (clearly in the public interest) and recoup its actual cost, rather than the alternative, which would be to stop building, thereby requiring the public agency to draw
The majority also purports to find “significant public policy concerns” (maj. opn., ante, at p. 240) in the fact that Amelco cannot pinpoint the exact time and date the contract was abandoned. This argument has two answers. First, the majority’s concern betrays a misunderstanding of the abandonment doctrine itself, for unlike the traditional doctrine of abandonment in which both sides to a contract expressly announce their intention to abandon it, releasing both sides from their respective duties under the contract (also called mutual rescission; see Pennel v. Pond Union School Dist. (1973)
The difference was explained in Peterson, supra,
Second, the majority’s concern over the absence of a specific time and date of abandonment goes to the viability of the doctrine itself, and not just to its application to public entities. Thus, it is not only public entities that “would not receive timely notice of claims that would allow them to make project management, budget, or procedural adjustments during the course of construction.” (Maj. opn., ante, at p. 240.) Private parties also would lack such notice. The majority’s concern in this regard thus does not advance its proposition that the abandonment doctrine should be limited to private contractees.
The only plausible support for the majority’s conclusion is Public Contract Code section 7105, subdivision (d) (hereafter section 7105(d)). That
The provision in section 7105(d) limiting “terminations” of public contracts that are subject to competitive bidding laws would apply here if, by “termination,” the statute means to include “abandonment.” But that the Legislature meant to include abandonment of a construction contract is not evident. Certainly the plain meaning of the word “terminations,” as used in section 7105(d), does not clearly embrace “abandonment,” which is more akin to a mutual rescission. All three California cases relying on the abandonment doctrine in the construction context (Peterson, supra,
There being no authority or persuasive reason to prohibit application of the abandonment doctrine to construction contracts with public entities, I dissent.
Kennard, J., concurred.
Respondent’s petition for a rehearing was denied March 13, 2002. Kennard, J., and Werdegar, J., were of the opinion that the petition should be granted.
C. Norman Peterson Co. v. Container Corp. of America (1985)
See, e.g., Greenlee County v. Webster (1923)
See, e.g., Edward R. Marden Corporation v. United States (Ct.Cl. 1971)
See generally 11 part 1 California Jurisprudence Third (1996) Building and Construction Contracts, section 21, pages 30-31 (abandonment); 13 American Jurisprudence Second (2000) Building and Construction Contracts, section 102, page 87 (same); Stein, Cohstruction Law (1992) Modification of Construction Contracts, paragraph 4.02[3], page 4-7 (cardinal change); Keyes, Government Contracts Under the Federal Acquisition Regulation (2d ed. 1996) Contract Modifications, section 43.15, page 925 (cardinal change).
Only three reported cases in California deal with the doctrine.
The City in its briefing adopts a fallback position, arguing in the alternative that limiting the abandonment doctrine to private entities would also be satisfactory.
The majority misreads applicable precedent when it opines that “the Courts of Appeal have concluded that private parties may impliedly abandon a contract when they fail to follow change order procedures and when the final product differs substantially from the original.” (Maj. opn., ante, at p. 235, italics added.) Although the failure to follow prescribed change order procedure is mentioned in the three California cases addressing the abandonment doctrine (Peterson, supra,
In any event, whether or not Amelco reserved the right to seek additional compensation despite partial attempts to utilize the contractual change order procedure, and whether or not the City acceded to those attempts, was a hotly contested issue at trial. Viewing the facts in a light favorable to the prevailing party below, as we must, the evidence showed, as the Court of Appeal stated, that the parties deviated from the contract’s change order procedure by performing many changes on a “price and proceed” basis, with Amelco reserving the right to seek additional compensation later, rather than following the procedure described in the contract.
