History
  • No items yet
midpage
J.S. Riemer, Inc. v. The Village of Orland Hills
990 N.E.2d 831
Ill. App. Ct.
2013
Read the full case

Background

  • Village hired Barclay to provide architectural/design services for a new community center; substantial completion occurred July 1, 2001.
  • Building floor sank because site soil was peat and not fully excavated as planned; excavation by Riemer occurred August 10–11, 2000.
  • Village sued Barclay on December 8, 2006 for breach of contract and fraud; Barclay moved for summary judgment asserting the action was time-barred.
  • Contract Article 9.3 fixes accrual date to substantial completion or final certificate of payment, effectively creating a statute of repose and precluding discovery-based accrual.
  • Village alleged Barclay misrepresented fault to conceal the true cause and argued equitable estoppel and fraudulent concealment tolling.
  • Trial court granted summary judgment for Barclay; on appeal, court affirmed, focusing on equitable estoppel and application of the statute of limitations/noting Article 9.3 governs accrual.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether Barclay is equitably estopped from raising the statute of limitations Village argues Barclay misrepresented the cause and lulled forbearance Barclay contends no discovery rule; information available within period; no equitable estoppel Estoppel not applicable; information available within period; no fiduciary duty established
Whether fraudulent concealment tolls the limitations period Village asserts fraudulent concealment tolls under 13-215 No concealment; Village knew or could have discovered the cause; 13-215 not applicable Not tolled; concealment not proven to delay discovery within tolling rule
Whether Article 9.3 precludes discovery-based accrual but allows estoppel as tolling Discovery rule inapplicable; estoppel independent Article 9.3 controls accrual; discovery rule barred Article 9.3 precludes discovery rule but does not automatically bar equitable estoppel; estoppel rejected on facts

Key Cases Cited

  • Federal Insurance Co. v. Konstant Architecture Planning, Inc., 388 Ill. App. 3d 122 (Ill. App. 2009) (Article 9.3 controls accrual; precludes discovery rule)
  • Hester v. Diaz, 346 Ill. App. 3d 550 (Ill. App. 2004) (fraudulent concealment can toll statute of repose)
  • Carey Electric Contracting, Inc. v. First National Bank of Elgin, 74 Ill. App. 3d 233 (Ill. App. 1979) (confidential relationship not established by mere trust in contractual context)
  • Axia Inc. v. I.C. Harbour Construction Co., 150 Ill. App. 3d 645 (Ill. App. 1986) (equitable estoppel based on remedial actions akin to acknowledgment of responsibility)
  • Senior Housing, Inc. v. Nakawatase, Rutkowski, Wyns & Yi, Inc., 192 Ill. App. 3d 766 (Ill. App. 1989) (remedial measures can support estoppel when defendant takes responsibility)
Read the full case

Case Details

Case Name: J.S. Riemer, Inc. v. The Village of Orland Hills
Court Name: Appellate Court of Illinois
Date Published: May 10, 2013
Citation: 990 N.E.2d 831
Docket Number: 1-12-0106
Court Abbreviation: Ill. App. Ct.