delivered the opinion of the court:
Plaintiff, Federal Insurance Company (Federal), brought suit against defendant Konstant Architects,
Plaintiff filed a complaint on September 9, 2005. The complaint alleged that Thomas and Anita Croghan entered into a contract with defendant to design a home in Winnetka, Illinois. The contract consisted of a standard form agreement between owner and architect, which was a document issued by the American Institute of Architects (ALA). Article 9.3 of the contract provides:
“Causes of action between the parties to this Agreement pertaining to acts or failures to act shall be deemed to have accrued and the applicable statutes of limitations shall commence to run not later than either the date of Substantial Completion, or the date of issuance of the final Certificate for Payment for acts or failures to act occurring after Substantial Completion.”
The parties agree that the home was built and substantially completed in 1997. The Croghans discovered water and mold damage in their home on November 7, 2002. The damages and remediation caused by water intrusion and mold infestation resulted in costs to repair in excess of $300,000. Plaintiff paid the Croghans for these losses pursuant to an insurance policy that it had previously issued to the Croghans. As a result, plaintiff became subrogated to the rights of its insureds, the Croghans.
In the complaint, plaintiff alleged that defendant breached the AIA contract by: (1) failing to properly design the Croghans’ home, including the failure to provide proper ventilation and a roof design to prevent ice damming, leaking, and water intrusion; (2) failing to properly supervise the installation of the roof to prevent ice damming, water intrusion, and mold infestation; and (3) failing to warn the Croghans that their home, as designed and built, was at risk of having ice damming, water infiltration, and possible mold infestation.
Defendant filed a motion to dismiss the case under section 2 — 619(a)(5) of the Code. Defendant argued that the cause of action was time-barred because plaintiff had failed to file suit within the four-year limitations period governing the construction of improvements to real property (735 ILCS 5/13 — 214(a) (West 2006)). Defendant maintains that pursuant to the AIA contract, specifically Article 9.3, the statute of limitations began to run at the time the house was completed in 1997, and, therefore, plaintiff did not file its complaint within the requisite four-year period.
On September 8, 2006, the circuit court entered an order granting defendant’s motion to dismiss plaintiffs complaint. In doing so, the circuit court found that the four-year limitations period applied to this case (735 ILCS 5/13 — 214(a) (West 2006)) and that Article 9.3 of the AIA contract provided that the applicable four-year period began to run on the date of substantial completion. Because four years had elapsed since the date of substantial completion, the circuit court concluded that plaintiffs complaint was time-barred. Plaintiff now appeals.
The circuit court dismissed this case under section 2 — 619(a)(5) of the Code, which allows for the involuntary dismissal of an action that “was not commenced within the time limited by law.” 735 ILCS 5/2— 619(a)(5) (West 2006). Such a dismissal is subject to de novo review. Alvarez v. Pappas,
On appeal plaintiff contends, as it did below, that the statute of limitations applicable to this case is section 13 — 206, which provides for a 10-year limitations period. Defendant contends that the four-year limitations period under section 13 — 214(a) is applicable to this case. We agree with defendant.
Section 13 — 206 provides a 10-year limitations period for “actions on bonds, promissory notes, bills of exchange, written leases, written contracts, or other evidences of indebtedness in writing.” 735 ILCS 5/13 — 206 (West 2006). Section 13 — 214(a) provides:
“Actions based upon tort, contract or otherwise against any person for an act or omission of such person in the design, planning, supervision, observation or management of construction, or construction of an improvement to real property shall be commenced within 4 years from the time the person bringing an action, or his or her privity, knew or should reasonably have known of such act or omission.” 735 ILCS 5/13 — 214(a) (West 2006).
Section 13 — 214(a) protects a party who is being sued because it either engaged in an activity enumerated in section 13 — 214(a) (People ex rel. Skinner v. Hellmuth, Obata & Kassabaum, Inc.,
Again, section 13 — 214(a) applies only if the defendant is being sued for its act or omission of one of the enumerated construction-related activities. Paschen Contractors,
Plaintiff argues that the Illinois statutory limitations scheme is an “organic whole” that should be read together. Nevertheless, when two limitations periods apply to an action, the more specific statute is generally effective. DeMarco,
Plaintiff also asserts that even if the four-year limitations period under section 13 — 214(a) applied, section 13 — 214(b) allows for a 10-year statute of limitations, so long as the action is brought within four years of the date that the party making the claim discovers such act or omission. Section 13 — 214(b) provides:
“No action based upon tort, contract or otherwise may be brought against any person for an act or omission of such person in the design, planning, supervision, observation or management of construction, or construction of an improvement to real property after 10 years have elapsed from the time of such act or omission. However, any person who discovers such act or omission prior to expiration of 10 years from the time of such act or omission shall in no event have less than 4 years to bring an action as provided in subsection (a) of this Section.” 735 ILCS 5/13 — 214(b) (West 2006).
Contrary to plaintiff’s assertion, subsection (a) of section 13 — 214 is the limitations portion of the statute; whereas, subsection (b) of section 13 — 214 is commonly known as the repose portion of the statute. See Ryan v. Commonwealth Edison Co.,
As previously stated, section 13 — 214(a) provides that the statute of limitations begins to run “from the time the person bringing an action, or his or her privity, knew or should reasonably have known of such act or omission.” 735 ILCS 5/13 — 214(a) (West 2006). Plaintiff asserts that Article 9.3 of the contract has no impact on this language, which makes the discovery rule applicable to actions brought under section 13 — 214(a). Defendant asserts that Article 9.3 precludes application of the discovery rule. While neither party cites Illinois case law regarding the application of a contractual provision that controls the accrual date of an action, “it is well established that parties to a contract may agree upon a shortened contractual limitations period to replace a statute of limitations, as long as it is reasonable.” Medrano v. Production Engineering Co.,
Defendant cites to other jurisdictions that have addressed the impact that Article 9.3 has on the accrual date of the applicable statute of limitations. In Gustine Uniontown Associates, Ltd. v. Anthony Crane Rental, Inc.,
In Schultz v. Cooper, 134 S.W3d 618 (Ky. App. 2003), the Kentucky court held that the discovery rule was inapplicable because of the provision of the AIA contract (entitled Article 8.3 in that case) requiring that the limitations period of all claims arising out of the contract between the homeowner and architect commence upon substantial completion of the work or issuance of the final certificate for payment. Schultz,
Similarly, we find that Article 9.3 of the AIA contract in this case controlled the accrual date of the applicable statute of limitations and precluded application of the discovery rule. When construing the language of a contract, this court’s primary objective is to give effect to the intent possessed by the parties at the time they entered the agreement. Regency Commercial Associates, LLC v. Lopax, Inc.,
While plaintiff argues that Article 9.3 is ambiguous, we find that it is “unambiguous and susceptible of only one meaning” in that it “specifies a clear date for [the] accrual of a cause of action.” College of Notre Dame of Maryland,
Defendant argues for the first time on appeal that the circuit court’s dismissal should be affirmed where plaintiffs claims are not supported by the contract. However, this court need not consider this alternative argument.
For the above reasons, we affirm the circuit court’s dismissal of plaintiffs complaint pursuant to section 2 — 619(a)(5) of the Code.
Affirmed.
THEIS and COLEMAN, JJ., concur.
Notes
Plaintiff entered into a settlement agreement with defendant Hanson Roofing, Inc., and third-party defendant ET. Construction, Inc. Pursuant to that settlement agreement, the circuit court dismissed the portion of this case with respect to these parties on March 27, 2008.
