delivered the opinion of the court:
Plaintiff, AXIA, Inc., a Delaware corporation, formerly known as Bliss & Laughin Industries, Inc., filed a complaint seeking damages from defendants, I. C. Harbour Construction Company (Harbour) and Shaw and Associates, Inc. (Shaw), alleging that Harbour, as the contractor, and Shaw, as the architect, breached a written contract to construct an office building for plaintiff. Each defendant filed a motion to dismiss pursuant to section 2 — 619(a)(5) of the Code of Civil Procedure (Ill. Rev. Stat. 1983, ch. 110, par. 2 — 619(a)(5)) asserting that the action was not brought within the two-year time limitation as then set forth in section 13 — 214(a) of the Code of Civil Procedure (Ill. Rev. Stat. 1983, ch. 110, par. 13 — 214(a)), now amended to a four-year term limitation not applicable hereto (Ill. Rev. Stat. 1985, ch. 110, par. 13 — 214(a)). The trial court dismissed the complaint as being time barred. This court originally reversed the trial court’s decision in an
The issue raised by plaintiff is whether the trial court erred in dismissing plaintiff’s complaint as being barred by the statute of limitations.
According to the complaint, plaintiff entered into a written contract with Harbour on June 10, 1977, for the construction of a new three-story office building. The written agreement contained a provision stating that the contractor warranted that all work would be of good quality, free from faults and defects, and in conformance with the contract documents. It also contained a provision requiring the contractor to correct any defect in the building appearing within one year upon written notification by the owner. Plaintiff also entered into a written contract on June 24, 1977, with Shaw to design the office building. Under the terms of this contract, Shaw was required to prepare the drawings and specifications for the building and to periodically examine the construction to determine if the quality of work was in accordance with the contracts. The building was completed in the fall of 1978, and plaintiff and its tenants took possession of the building.
Shortly after completion, the building began to leak extensively after rain. Additionally, a white powdery deposit, described in the complaint as efflorescence, began covering the outside of the building as well as appearing on some inside walls. Within one year of completion of the building, plaintiff notified both Harbour and Shaw of the water-leakage problems and requested that they correct these conditions. Plaintiff alleged in the complaint that Harbour attempted to correct the water-leakage problems by caulking mortar joints and applying water-resistant sealer. The remedial measures were unsuccessful.
Plaintiff employed a consulting firm in July 1983 to investigate and determine the cause of the water-leakage problem. The consulting firm issued its report in September 1983 concerning the apparent causes of the conditions and its recommendations for correcting the conditions. Plaintiff sent copies of the report to Harbour and Shaw.
Harbour and Shaw each moved to dismiss the complaint alleging that the action was barred by the applicable two-year statute of limitations set forth in section 13 — 214(a) (Ill. Rev. Stat. 1983, ch. 110, par. 13 — 214(a)). In particular, each defendant asserted that the water-leakage problem manifested itself shortly after the completion of the building in 1978, yet the complaint was not filed in this action until September 17, 1984.
Plaintiff filed an “Amended Answer to Motion to Dismiss” to each motion arguing that Harbour and Shaw are estopped from asserting the statute of limitations because their conduct led plaintiff to believe that the situation would be remedied. In support of its opposition to the motions to dismiss, plaintiff also submitted the affidavit of Donald R. Pacey, one of plaintiff’s managers. Pacey generally reaffirmed the allegations contained in the complaint. Specifically, he stated that in 1979, 1980, and 1981, as well as on January 27 and 31, May 2, and September 13, 1983, he sent letters to Harbour either requesting it to perform corrective work or inquiring about the status of the corrective work. Only the 1983 letters, however, were attached to the affidavit. Pacey also stated that he sent similar letters to Shaw in 1979, 1980, 1981, and on January 31, 1983. Only the 1983 letter was attached. In addition, Pacey stated that from time to time from 1979 to 1983, Harbour inspected the building and performed tests to determine the cause of the problems. Harbour also performed work on the structure which included a sealant to some of the bricks in 1979, washing down the exterior of the building and coating it with sealant in 1980, caulking a structural crack in 1982, and applying a sealant to the penthouse wall in 1983.
Pacey further stated that in February 1983, plaintiff met with both Harbour and Shaw concerning additional corrective work. He states that Harbour proposed to further investigate the use of a particular sealant, and that Shaw indicated that it would explore the problems and have a waterproof expert submit an estimate. The parties
Plaintiff initially contends that the court improperly dismissed the complaint as time barred by the statute of limitations because the actionable breach of the contracts underlying the complaint asserted against both Harbour and Shaw was Harbour’s refusal to perform the recommended repair work which occurred in November 1983, and its subsequent refusal to pay for the costs of having the repair work completed. Our review of the record reveals that this issue was never presented to the trial court. The complaint asserted a breach of contract action based upon the improper design and construction of the office building and was not predicated on the failure to comply with a specific provision of the contract concerning a responsibility to pay for repair costs. In addition, plaintiff’s response to the motions to dismiss failed to assert this claim in opposition to the statute of limitations defense. As it is axiomatic that questions not raised in the trial cannot be raised for the first time on appeal and are deemed waived (George W. Kennedy Construction Co. v. City of Chicago (1986),
Plaintiff also argues in its reply brief that because it had no knowledge of the real cause of the problem until the September 1983 report was issued, the action did not accrue until September 1983. It also argues that Shaw’s obligation was to supervise Harbour and that Shaw’s breach flowed from Harbour’s breach. Arguments not raised in the initial brief, however, are also deemed waived for purposes of review. (Murdy v. Edgar (1984),
Plaintiff next contends that even if the cause of action for breach of contract accrued when it discovered the water-leakage problem, the trial court still improperly dismissed the complaint as barred by the statute of limitations because any delay in the filing of the lawsuit was caused by the defendants’ conduct. Plaintiff presents three separate arguments in support of this contention.
First, plaintiff argues that both Harbour and Shaw undertook remedial actions to correct the problems constituting acknowledgements of liability which tolled the running of the applicable two-year statute of limitations. The defendants both respond that this issue is also waived as plaintiff did not raise this issue below. Plaintiff, however, did present this argument to the trial court in its answers to the defendants’ motions to dismiss. Although plaintiff preserved this issue for our review, it has failed to cite in its brief any authority to support its contention that the acts of the defendants operated to “toll” the running of the statute of limitations period. The statute itself does not provide for any exception which would toll, or delay, the running of the statute, as it is an established rule regarding the statute of limitations that no exceptions which toll the statute or enlarge the scope will be implied (Hamil v. Vidal (1985),
Second, plaintiff argues that the circumstances here are analogous to situations involving a second, or new, promise to pay a past-due debt. (See Hurtt v. Steven (1947),
Finally, plaintiff contends that the defendants are estopped from raising the statute of limitations as a bar to this action as the actions and representations of both Harbour and Shaw indicate an intent by the defendants to remedy the defects in the building thereby inducing plaintiff to refrain from commencing a lawsuit until the defendants’ refusal to repair after the time period under the statute had run. The general rule is that where a party by his statements or conduct leads another to do something he would not have done but for the statements or conduct of the other, the one guilty of the expressions or conduct will not be allowed to deny his utterances or acts to the damage of the other party. (Dill v. Widman (1952),
Both Harbour and Shaw argue that their actions were not sufficient to induce plaintiff to delay bringing suit. Shaw contends that it never admitted liability and that it never represented that Harbour’s work would rectify the problems. Harbour likewise contends that it never represented that it was liable for the defects or that it would work out a settlement with plaintiff, or even that it would continue to attempt to repair the problems. The trial court determined that because the parties were relatively commercially sophisticated, the doctrine of estoppel did not apply to them under these circumstances for to do so would only chill any settlement efforts. As it is incumbent upon the plaintiff to show sufficient facts to avoid the statute of limitations when a defendant raises a statute of limitations defense in a motion to dismiss (Burnett v. West Madison State Bank (1940),
Initially, as to Shaw, the record is devoid of any allegations that it had any contact with plaintiff after the completion of the building until the meeting in 1983, more than three years after the water-leakage problem was discovered. There are only the allegations that plaintiff sent some letters to Shaw; however, there are no allegations that Shaw responded to these letters. Pacey’s affidavit asserts conduct by Shaw which occurred after the expiration of the two-year period as inducing its reliance. Post-expiration conduct could be considered as additional evidence in determining whether there has been estoppel. Where, however, as in this case, there is no preexpiration conduct sufficient to induce any reasonable reliance, the post-expiration conduct illustrates nothing. (See Hurtt v. Davidson (1980),
While plaintiff failed to show conduct by the defendant Shaw sufficient to apply equitable estoppel, Pacey’s affidavit sets forth four instances, in 1979, 1980, and 1982, where the additional defendant,
The issue of whether efforts to repair estop a party from asserting the statute of limitations as a bar to a cause of action has been treated in a number of other jurisdictions with varying results. See, e.g., Torcon, Inc. v. Alexian Brothers Hospital (1985),
In the only remotely relevant Illinois authority, it was held that “efforts to repair do not toll the statute [of limitations].” (Tomes v. Chrysler Corp. (1978),
Additionally, Harbour analogizes this case with the cases involving settlement negotiations by insurance carriers with a claimant. (See Myers v. Centralia Cartage Co. (1981),
In the context of the facts presented here, we conclude that Harbour’s conduct was sufficient to establish an estoppel to prevent Harbour from shielding itself with the limitations bar. Within one year of the completion of the building, plaintiff notified Harbour of water leakage and efflorescence on the outside brick. Numerous telephone conversations between the parties about these conditions were exchanged, and Harbour not only inspected the premises and conducted tests but also performed corrective work on the building for over a four-year period. In 1979, Harbour applied a sealant to the bricks in some areas; in 1980, Harbour washed down the exterior of the building and coated the building with a sealant; in 1982, Harbour caulked a structural crack around the crown of the building; and in 1983, Harbour applied sealant to the penthouse wall. When these measures did not solve the problems, both parties employed experts to examine the premises and submit bids for corrective work. Following the submission of the proposals by these firms, Harbour wrote plaintiff on October 27, 1983, and requested its review and suggested action. After this exchange, the parties apparently could not agree on a further course of action, and a lawsuit was later filed by plaintiff.
Harbour also contends on appeal that the doctrine of laches should apply to bar plaintiff from obtaining relief. This affirmative matter, however, was not raised in Harbour’s motion to dismiss (see Ill. Rev. Stat. 1985, ch. 110, par. 2 — 619(a)(9)) and was only alluded to in Harbour’s reply to plaintiff’s amended answer to the motion to dismiss where Harbour asserted that plaintiff “cannot rely on the estoppel doctrine since ten (10) months passed before the present suit was filed.” Although the trial judge stated in his findings that even if estoppel against Harbour was applicable, the doctrine of laches would prevent plaintiff’s action because of the 10-month delay in filing suit, this defense simply was not properly raised, nor was plaintiff given an opportunity below to dispute it. In any event, on the record before us, Harbour has not established any prejudice to invoke the doctrine of laches.
For the foregoing reasons, the part of the judgment dismissing Shaw is affirmed and the judgment dismissing Harbour is reversed and the cause is remanded.
Affirmed in part, reversed and remanded in part.
HOPF and LINDBERG, JJ., concur.
