Herren Associates, Inc.
ASBCA No. 62706
| A.S.B.C.A. | Apr 22, 2022Background
- Contract N00178-04-D-4062: IDIQ awarded 2004; Task Order NS01 awarded to Herren on Feb. 12, 2009 for services through Apr. 11, 2014. Task order B-2 set fixed fees payable as hourly rates (with up to 85% paid during performance).
- On first day of performance (Feb. 12, 2009) the government provided a staffing matrix adding more senior personnel not in Herren’s proposal; Herren alleges it requested an equitable adjustment then but produced no record of any CO request or response.
- Herren submitted a certified claim on Sept. 19, 2019 seeking an upward adjustment to the fixed-fee hourly rates for labor performed years earlier (Herren admits all contested hours were performed before Sept. 19, 2013). CO denied that claim in a July 27, 2020 final decision.
- Herren later amended its claim (Apr. 27, 2020) seeking reimbursement for rented office space for March 16, 2009–July 23, 2010; Herren never invoiced the government for those lease costs despite submitting numerous invoices during performance and admits it paid the rent by Apr. 27, 2014.
- The contract referenced FAR 52.216-7 (Allowable Cost and Payment) and a contract clause requiring no more than a 30-day lapse between performance and submission of an interim payment invoice. The Board granted the government’s motion for summary judgment, holding Herren’s claims time-barred under the CDA six-year limitations period.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Accrual for increased fixed-fee claim (statute of limitations) | Herren: cost-reimbursement/final indirect-rate mechanics and B-2 permit waiting; claim could be brought later (effectively at closeout) | Government: liability fixed when the labor-mix changed/when higher-cost workers performed; accrual occurred in 2009 (or when the work was performed) | Time-barred: claim accrued well before Sept. 19, 2013; six-year CDA period elapsed |
| Accrual for leased-space cost claim (statute of limitations/invoicing) | Herren: contract did not require invoice timing for these direct costs; could bill at closeout | Government: contract required invoicing within 30 days of performance; Herren could and should have invoiced earlier but did not | Time-barred: accrual when Herren became obligated/paid rent (2009–2010); claim filed after six-year period |
| Do FAR 52.216-7, task-order B-2, or the Changes clause toll accrual? | Herren: FAR clauses and B-2 justify delaying claim until final payment/closeout or until final indirect cost determination | Government: those clauses do not toll the CDA limitations period; B-2 lists fixed hourly rates and contains no tolling language | Not tolled: clauses do not postpone accrual; they do not excuse a six‑year delay |
| Appropriateness of summary judgment | Herren: asserted disputes/contested facts (generally) | Government: submitted undisputed material facts showing accrual and non‑payment within six years | Summary judgment proper: no genuine issue of material fact; government entitled to judgment as a matter of law |
Key Cases Cited
- Anderson v. Liberty Lobby, 477 U.S. 242 (1986) (summary judgment standard; Board does not weigh evidence)
- Mingus Constructors, Inc. v. United States, 812 F.2d 1387 (Fed. Cir. 1987) (conclusory denials insufficient to avoid summary judgment)
- Sikorsky Aircraft Corp. v. United States, 773 F.3d 1315 (Fed. Cir. 2014) (burden on movant to establish statute-of-limitations defense)
- FloorPro, Inc. v. United States, 680 F.3d 1377 (Fed. Cir. 2012) (actual knowledge not required for accrual; accrual when facts reasonably knowable)
- United States v. Commodities Export Co., 972 F.2d 1266 (Fed. Cir. 1992) (only inherently unknowable facts postpone accrual)
- Duhame v. United States, 135 F. Supp. 742 (Ct. Cl. 1955) (contractor cannot toll limitations by refraining from acts within its power, e.g., invoicing)
- Triple Canopy, Inc. v. Sec’y of the Air Force, 14 F.4th 1332 (Fed. Cir. 2021) (accrual may depend on specific contract provisions; tolling is fact- and contract-specific)
