The United States appeals a judgment of the United States Court of Federal Claims awarding FloorPro, Inc. (“FloorPro”) damages for breach of a government contract.
See FloorPro, Inc. v. United
BACKGROUND
On February 6, 2002, the United States Navy awarded Contract No. N62467-02-M-2013 to G.M. & W. Construction Corporation (“GM & W”) for the installation of floor coating in several warehouse bays at a military base. GM & W subsequently entered into a subcontracting agreement with FloorPro, pursuant to which FloorPro agreed to perform the floor-coating work for a sum of $37,500.00. FloorPro completed the work on February 27, 2002, and promptly submitted an invoice to GM & W.
On March 8, 2002, the Navy informed GM & W that the floor-coating work had been completed satisfactorily. On April 17, 2002, FloorPro contacted the Navy’s contracting officer, stating that it had not been paid by GM & W. The contracting officer then contacted GM & W to inquire why FloorPro had not been paid for the floor-coating work. GM & W informed the contracting officer that there were several claims pending against it, and that it was not sure whether any funds that the Navy directly deposited into its bank account would be available to pay FloorPro. Accordingly, on April 22, 2002, the Navy and GM & W entered into a contract modification (“Modification P00001”), which provided that the Defense Finance and Accounting Service (“DFAS”) would not pay GM & W directly, as required by the original contract, but would instead pay for the floor-coating work by issuing a hard-copy, two-party check payable to GM & W and FloorPro. Modification P00001 further provided that the Navy would mail the check directly to FloorPro.
Notwithstanding Modification P00001, on July 17, 2002, the DFAS paid GM & W directly by an electronic fund transfer to its bank account. On July 18, 2002, the contracting officer informed FloorPro that DFAS had “ignored” Modification P00001 and “did not issue the two-party check as [Modification P00001] had directed.” FloorPro responded by sending a letter, dated July 23, 2002, asking the contracting officer “[w]hat exactly is being done by [the Navy] to process a payment to us for our work?” On August 9, 2002, Captain B.M. Scott, a Navy acting commander, sent FloorPro a letter confirming that the government had paid GM & W in full on the contract. Scott asserted that “[a]s the Government does not possess privity of contract with FloorPro, Inc., or any other subcontractor,” payment to GM & W had “fulfilled] the extent of the Government’s obligations” under the contract. Scott informed FloorPro that its only recourse was to seek payment “from GM & W through the civil court system.” Scott stated, moreover, that GM & W’s failure to pay FloorPro “ha[d] been referred to the Naval Criminal Investigative Service for investigation.”
On December 5, 2002, FloorPro submitted a claim to the Navy’s contracting officer, asserting that the Navy had failed to pay it for the floor-coating work it had performed. Two weeks later, the contracting officer wrote FloorPro a letter stating that she could not issue a final decision on its claim because the government did “not have a contract with Floor-Pro.”
On March 27, 2003, FloorPro filed an action against the Navy at the Armed Services Board of Contract Appeals (“ASBCA”). Relying upon this court’s decision in
D & H Distributing Co. v. United
On appeal, this court reversed.
See Winter v. FloorPro, Inc.,
On October 2, 2009, FloorPro filed suit against the government in the Court of Federal Claims. The government moved for summary judgment, arguing that FloorPro’s claim was time-barred because it was filed more than six years after it first accrued. In response, FloorPro argued that its claim did not accrue until October 5, 2004, “at which time the Navy filed a brief at the [ASBCA] contending that FloorPro had no enforceable rights under [Modification P00001].”
Federal Claims Decision I,
The Court of Federal Claims agreed with FloorPro that “the facts and the law” supported an October 5, 2004 accrual date for its claim.
Id.
The court determined, however, that it should not resolve the timeliness question “solely base[d] ... on which date [was] proper to start the running of the statute of limitations.”
Id.
Because FloorPro “did not sleep on its rights,” but instead had diligently pursued its claim by filing suit at the ASBCA, the court concluded that barring FloorPro’s claim as untimely would “lead to an unjust result.”
Id.
at 779. The court determined, moreover, that FloorPro was an intended third-party beneficiary of Modification P00001 and that it was entitled to damages of $37,500 for the government’s breach of that provision.
See Federal Claims Decision II,
Discussion
“Whether the Court of Federal Claims possesses jurisdiction over a claim is a question of law subject to
de novo
review.”
Navajo Nation v. United States,
Because FloorPro’s claim was filed more than six years after it accrued, the Court of Federal Claims was without jurisdiction to consider it. In general, a cause of action against the government accrues “when all the events have occurred which fix the liability of the Government and entitle the claimant to institute an action.”
Goodrich v. United States,
FloorPro’s cause of action accrued when the government breached Modification P00001 by making payment directly to GM & W, rather than sending a two-party check to FloorPro as the modification required.
See Franconia Assocs. v. United States,
FloorPro argues that its cause of action did not accrue until October 5, 2004, when the government filed its brief in the ASBCA proceedings. It asserts that while it “knew that the Government had paid GM & W directly in violation of Modification P00001, the Government did not repudiate the terms of the modification” until the government filed its brief with the ASBCA. We do not find this reasoning persuasive. FloorPro knew long before the government filed its brief in the
We likewise reject FloorPro’s contention that equitable tolling can be applied to defer the running of the limitations period. FloorPro argues that its claim should be deemed timely because it diligently pursued its claim and acted reasonably in initially filing suit at the ASBCA, rather than in the Court of Federal Claims. It asserts, moreover, that nothing in the Supreme Court’s decision in
Sand & Gravel
“specifically bars the application of equitable tolling.” We disagree.
Sand & Gravel
makes clear that section 2501 sets forth an “absolute” time limit for filing suit in the Court of Federal Claims.
Conclusion
Accordingly, the judgment of the United States Court of Federal Claims is vacated and the case is remanded with instructions to dismiss for lack of jurisdiction.
Costs
No costs.
VACATED AND REMANDED
