FCM Group, Inc. v. Miller
17 A.3d 40
| Conn. | 2011Background
- The FCM Group, Inc. contracted with Jeffrey Miller to construct a 5000 square foot Greenwich home; Cheryl Miller was not a party or signatory to the contract but lived on the property.
- The contract allowed owner-initiated changes and provided for time and cost adjustments via written change orders; several changes increased the price to $803,090.98 and extended the schedule by 86 days.
- Disputes arose over final payment, punch list completion, and a contention that Cheryl Miller as equitable owner could be liable for breach of contract.
- Plaintiff recorded two mechanic's liens: $30,761.98 (contract balance) and $343,351.47 (delay damages); the latter was later attacked as invalid.
- After delays, the trial court awarded damages to the plaintiff for delay and lost profits but foreclosed the contract balance lien and denied some requested attorney’s fees; the defendants appealed and plaintiff Mercede cross-appealed.
- The Supreme Court reversed in part, holding Cheryl Miller cannot be held liable as a nonparty, vacated the contract-balance award, and remanded for attorney’s fees under § 49-8(c) related to the invalid lien.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Can Cheryl Miller be held liable on the contract? | Cheryl Miller was an equitable owner who participated in project control and thus bound by the contract. | Only signatories bound by the contract can be liable; Cheryl Miller was not a party or titleholder. | Cheryl Miller cannot be held liable; not a party to the contract. |
| Whether the contract balance award was proper when breached? | Plaintiff proved a remaining balance due despite substantial completion; delay and deviation arguments support recovery. | Plaintiff failed to prove it furnished materials/services for the balance; damages limited to actual loss. | The contract balance award was improper; plaintiff did not prove entitlement to that balance. |
| Whether delay damages for changes and wetlands delays were recoverable under the contract? | Article 12 allowed delay costs for owner-caused delays, including change orders and wetlands delays. | Delays outside owner-initiated work are governed by time extensions, not monetary damages. | Delay damages for change orders and wetlands delays were not recoverable; exclusive remedy is extended time under the contract. |
| Validity of the $343,351.47 lien and related damages/fees? | Lien is valid to secure delay damages; foreclosure should stand as to that lien. | Lien exceeds balance due; lien invalid under § 49-36 and § 49-33; defendants entitled to damages. | Lien invalid; damages awarded under § 49-8(c) related to that lien must be addressed; foreclosure of the lien was improper. |
| Attorney's fees under § 49-8(c) for invalidating the lien? | FCM is entitled to attorney's fees as prevailing party on § 49-8(c) issues. | Fees were not properly awarded because the lien was invalid and no foreclosure occurred. | Remand to determine reasonable attorney's fees under § 49-8(c) for the invalidation of the lien. |
Key Cases Cited
- Centerbrook Architects & Planners v. Laurel Nursing Services, Inc., 224 Conn. 580 (1993) (limits on equitable ownership for mechanic's lien to pre-title-transfer improvements)
- Sekeret v. Zdanis, 2001 WL 477433 (Superior Court, 2001) (beneficial ownership not binding contract when not a party)
- Hees v. Burke Construction, Inc., 290 Conn. 1 (2009) (damages for breach limited to actual loss; burden on plaintiff to prove damages with certainty)
- Burgess Construction Co. v. M. Morrin & Son Co., 526 F.2d 108 (10th Cir. 1975) (exclusive remedy of time extension for contractor delays when contract provides for it)
- United States ex rel. Straus Systems, Inc. v. Associated Indemnity Co., 969 F.2d 83 (5th Cir. 1992) (extension-of-time clause as exclusive remedy for delays)
- Hope v. Cavallo, 163 Conn. 576 (1972) (equitable ownership and related concepts discussed in context of property interests)
- Mozeleski v. Thomas, 76 Conn.App. 287 (2003) (ownership status and liability considerations for nonparty interests)
