GERALD HEES ET AL. v. BURKE CONSTRUCTION, INC.
(SC 18075)
Supreme Court of Connecticut
Argued September 4, 2008-officially released January 6, 2009
Rogers, C. J., and Norcott, Palmer, Zarella and Schaller, Js.
Scott M. Harrington, for the appellant (defendant).
Richard H. Raphael, for the appellees (plaintiffs).
Opinion
NORCOTT, J. The principal issue in this appeal is whether a violation of the Home Improvement Act (act),
The record reveals the following relevant facts and procedural history. The parties entered into a written home improvement contract on June 1, 2002, the terms of which provided that the defendant would provide various home improvement services and materials for $349,500. The original terms of the contract were changed periodically through the execution of thirty different change orders, which increased the price for the project by $42,354, to a total of $391,854. The terms of the contract required the plaintiffs to make monthly requisition payments for work already completed, the first nine of which the plaintiffs made in a timely fashion. The plaintiffs failed, however, to make the tenth requisition payment within thirty days, as required by the contract. By letter dated May 19, 2003, the defendant advised the plaintiffs that it intended to terminate the contract, in accordance with its terms, if payment was not received within one week. Thereafter, the plaintiffs did not pay the defendant, which then terminated the contract on May 29, 2003. At the time of termination, the defendant had completed and billed the plaintiffs for $346,378 worth of work,4 in addition to $625 for which the plaintiffs were not billed. The plaintiffs, however, had only paid the defendant $330,531, which left an unpaid balance on the contract for work already performed of $16,472.5
The plaintiffs thereafter brought this action, alleging that the defendant had breached the contract by failing
The court referred the case to the referee, who, after conducting a hearing, filed a report finding in favor of the plaintiffs with regard to both the breach of contract claim6 and the defendant‘s three counterclaims. The referee concluded that, because the contract did not contain a right of rescission clause, it was unenforceable against the plaintiffs under
On appeal, the defendant contends that the plaintiffs’ damages award should have been reduced by an amount equal to the unpaid balance remaining on the contract, because, under traditional contract damages law, the appropriate measure of damages in a construction contract case is the plaintiffs’ reasonable cost to complete or repair the work, less the unpaid balance on the contract. The defendant further contends that the trial court improperly accepted the referee‘s conclusion that a violation of
We begin by determining the appropriate standard of review. “While the reports of [attorney trial referees] are essentially of an advisory nature, it has not been the practice to disturb their findings when they are properly based upon evidence, in the absence of errors of law, and the parties have no right to demand that the court shall redetermine the fact[s] thus found. . . .
“A reviewing authority may not substitute its findings for those of the trier of the facts. This principle applies no matter whether the reviewing authority is the Supreme Court . . . the Appellate Court . . . or the
“Although it is true that when the trial court reviews the attorney trial referee‘s report the trial court may not retry the case and pass on the credibility of the witnesses, the trial court must review the referee‘s entire report to determine whether the recommendations contained in it are supported by findings of fact in the report. . . .
“Finally, we note that, because the attorney trial referee does not have the powers of a court and is simply a fact finder, [a]ny legal conclusions reached by an attorney trial referee have no conclusive effect. . . . The reviewing court is the effective arbiter of the law and the legal opinions of [an attorney trial referee], like those of the parties, though they may be helpful, carry no weight not justified by their soundness as viewed by the court that renders judgment. . . . Where legal conclusions are challenged, we must determine whether they are legally and logically correct and whether they find support in the facts found by the . . . referee.” (Citations omitted; internal quotation marks omitted.) Alliance Partners, Inc. v. Oxford Health Plans, Inc., 263 Conn. 191, 201-202, 819 A.2d 227 (2003).
I
We begin our analysis by briefly addressing the defendant‘s first claim, namely, that the trial court improperly accepted the referee‘s report because the referee failed to use an appropriate method to calculate the plaintiffs’ damages. “It is axiomatic that the sum of damages awarded as compensation in a breach of contract action
Thus, we agree with the defendant that the referee used an improper method to calculate the plaintiffs’ damages. The parties do not dispute the fact that, at the time of the breach, there remained an unpaid balance on the contract of $16,472. They also do not dispute the fact that, as a result of the breach, the plaintiffs incurred expenses to complete and repair the work in the amount of $16,085.17. Accordingly, in the absence of some legal justification for not doing so, the referee should have subtracted any unpaid amount remaining on the contract from the extra costs incurred by the plaintiffs, so as to avoid placing the plaintiffs in a better position than they would have been in had the contract been
II
We turn, then, to the principal issue in this appeal, namely, whether the trial court improperly accepted the referee‘s legal conclusion that the defendant‘s violation of
Whether
“When construing a statute, [o]ur fundamental objective is to ascertain and give effect to the apparent intent of the legislature. . . . In other words, we seek to determine, in a reasoned manner, the meaning of the statutory language as applied to the facts of [the] case, including the question of whether the language actually does apply. . . . In seeking to determine that meaning,
We begin our statutory analysis, then, with the language of
Accordingly, we now turn to an analysis of the relevant extratextual sources in order to determine the scope of
Moreover, the only cases disclosed by our research in which
Furthermore, were we to agree with the plaintiffs’ position in this case, we would, in effect, award them an unwarranted windfall that the legislature could not have intended. The plaintiffs essentially claim that, not only does
The judgment is reversed and the case is remanded with direction to render judgment in favor of the defendant.
In this opinion ROGERS, C. J., and PALMER and ZARELLA, Js., concurred.
SCHALLER, J., concurring. I agree that the plaintiff homeowners, Gerald Hees and Beatrice Hees, are not entitled to recover damages for their costs to complete and repair the work performed by the defendant, Burke Construction, Inc. I disagree, however, with the decision to reverse the judgment on the basis of an interpretation of the Home Improvement Act (act),
Central to my approach is a precise recognition of the parties’ claims and the application of
The defendant, in addition to contesting the plaintiffs’ breach of contract claim, also filed various counterclaims. In response, the plaintiffs filed a motion for summary judgment, claiming that
The plaintiffs, in other words, simultaneously claimed that the contract was enforceable to support their breach of contract claim but unenforceable, pursuant to
The problem in this case arose when, in calculating the plaintiffs’ damages, the referee conflated the application of
I agree with the majority that ”
Simply put, the road to calculating the plaintiffs’ damages never detours with a stop at
Under the facts of the present case, the appropriate calculation of compensatory damages, with reference to the contract, would be as follows: The contract price of $349,500, after various change orders, totaled $391,854. The defendant charged the plaintiffs $347,0033 for work that it had performed, and the plaintiffs paid the defendant $330,531 of that amount, leaving an unpaid balance of $16,472. The reasonable cost of completion was $16,085.17. Accordingly, because the $16,085.17 for the reasonable cost of completion and the payments of $330,531 were less than the contract price; see footnote 8 of the majority opinion; the plaintiffs were not entitled to damages. See Levesque v. D & M Builders, Inc., supra, 170 Conn. 180-81 (“[a]s a general rule, in awarding damages upon a breach of contract, the prevailing party is entitled to compensation which will place him in the same position he would have been in had the contract been properly performed“).
In short, this case presents nothing more than an ordinary breach of contract claim that requires the
The majority opinion, at the outset, seems to agree with the proposition that
Significantly, in order to reach the conclusion that
Moreover,
The majority‘s analysis with respect to the CUTPA cases, and the insignificance of a defendant‘s legal authority to collect an unpaid sum, makes the majority‘s foray into statutory interpretation all the more unnecessary. In my view, the majority‘s analysis goes astray when it asks whether “the legislature intended
The question actually presented by the facts of this case is far narrower. The more appropriate question to be asked is whether
Accordingly, because I conclude that the referee properly considered the contract to be valid for purposes of the plaintiffs’ complaint, I see no obstacle to relying on the contract to assess damages, as the case law requires. Doing so does not run afoul of the act in any respect. This approach would avoid interpreting the act in a way that, to my mind, relies on concepts, such as affirmative uses of the statute as opposed, presumably, to nonaffirmative uses of the statute, that do not appear in the statute and are likely to prove troublesome in the future. It is also unnecessary to
For the foregoing reasons, I respectfully concur in the judgment reached by the majority.
