History
  • No items yet
midpage
Delaware Riverkeeper Network v. Secretary of the Pennsylvania Department of Environmental Protection
870 F.3d 171
| 3rd Cir. | 2017
Read the full case

Background

  • Tennessee Gas proposed the 12.9-mile Orion pipeline loop in Pennsylvania; nearly all routing parallels existing pipelines and would affect exceptional‑value wetlands in Pike and Wayne Counties.
  • FERC is the lead federal agency under the Natural Gas Act; PADEP issues state Chapter 105 permits and a §401 Water Quality Certification required as a condition of FERC approval.
  • PADEP issued a conditional Water Quality Certification (Sept. 2016) and two Chapter 105 permits (Feb. 23, 2017) finding the project is "water dependent" and the least environmentally damaging alternative for affected exceptional‑value wetlands.
  • Delaware Riverkeeper Network (Riverkeeper) petitioned for review in this Court challenging (1) jurisdiction/timeliness and finality of PADEP’s order, (2) PADEP’s water‑dependency determination, and (3) PADEP’s rejection of a compressor ("compression") alternative.
  • The District/Third Circuit companion case addressed the Army Corps’ related permitting; here the court focuses on PADEP administrative-finality and the substantive determinations under Pennsylvania regulations.

Issues

Issue Plaintiff's Argument (Riverkeeper) Defendant's Argument (PADEP/Tennessee Gas) Held
Jurisdiction / finality of PADEP order PADEP order not final until reviewed by Environmental Hearing Board; transfer or dismissal for lack of jurisdiction PADEP order became final because Riverkeeper did not timely appeal to the Board and permits have immediate legal effect Court exercised jurisdiction: PADEP action was final under PA law and had practical legal consequences
Timeliness of petition to federal court Petition untimely if measured by state appeal period to Board Rule 15 looks to the statute (Natural Gas Act) for timing; no state deadline governs petition to this Court here Petition timely; Court declines to apply Board appeal-period as controlling for federal filing
Water‑dependency finding Water‑dependency should be interpreted per federal regime: linear infrastructure (pipelines) are categorically not water dependent PADEP reasonably reads its regs to allow case‑by‑case water‑dependency determinations incorporating alternatives analysis PADEP’s interpretation is reasonable and entitled to deference; its water‑dependency finding upheld
Rejection of compression alternative PADEP arbitrarily rejected compression; compression would avoid wetland impacts PADEP considered system/compression alternatives and reasonably concluded compression would cause other significant permanent environmental harms Court upholds PADEP: record supports finding that compression would have significant adverse environmental effects and thus is not a practicable superior alternative

Key Cases Cited

  • Del. Riverkeeper Network v. Sec'y Pa. Dep’t of Envtl. Prot., 833 F.3d 360 (3d Cir. 2016) (PADEP §401/Chapter 105 permits are actions "pursuant to federal law" for NGA review)
  • Berkshire Envtl. Action Team, Inc. v. Tenn. Gas Pipeline Co., LLC, 851 F.3d 105 (1st Cir. 2017) (discusses finality requirement and Massachusetts adjudicatory process)
  • Bennett v. Spear, 520 U.S. 154 (1997) (familiar standard for agency action finality)
  • Auer v. Robbins, 519 U.S. 452 (1997) (deference to agencies’ interpretations of their own regulations)
  • Motor Vehicle Mfrs. Ass’n v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29 (1983) (review of administrative action under arbitrary and capricious standard)
  • NE Hub Partners, L.P. v. CNG Transmission Corp., 239 F.3d 333 (3d Cir. 2001) (PADEP permits effective pending EHB outcome)
Read the full case

Case Details

Case Name: Delaware Riverkeeper Network v. Secretary of the Pennsylvania Department of Environmental Protection
Court Name: Court of Appeals for the Third Circuit
Date Published: Aug 30, 2017
Citation: 870 F.3d 171
Docket Number: 17-1533
Court Abbreviation: 3rd Cir.