Utah Code Ann. § 54-17-201
(1)
(2)
(b) To obtain the approval of the commission of a solicitation process, the affected electrical utility shall file with the commission a request for approval that includes:
(c) In ruling on the request for approval of a solicitation process, the commission shall determine whether the solicitation process:
(ii) is in the public interest taking into consideration:
(d) Before approving a solicitation process under this section the commission:
(f) Unless the commission determines that additional time to analyze a solicitation process is warranted and is in the public interest, within 60 days of the day on which the affected electrical utility files a request for approval of the solicitation process, the commission shall:
(4) In accordance with the commission's authority under Subsection 54-12-2(2), the commission shall determine: