Utah Code Ann. § 38-1a-804
(1) The owner of any interest in a project property that is subject to a recorded preconstruction or construction lien, or any original contractor or subcontractor affected by the lien, who disputes the correctness or validity of the lien may submit for recording a notice of release of lien and substitution of alternate security:
(2) A notice of release of lien and substitution of alternate security recorded under Subsection (1) shall:
(c) have as an attachment a surety bond or evidence of a cash deposit that:
(i)
(ii) is in an amount equal to:
(iv) is conditioned for the payment of:
(v) has as principal:
(3)
(4)
(5) The alternate security attached to a notice of release of lien shall be discharged and released upon:
(d) the entry of judgment against the claimant in:
(7)
(b) A petition under this Subsection (7) shall:
(c) A petitioner under Subsection (7)(a) shall, as provided in Utah Rules of Civil Procedure, Rule 4, serve on the claimant:
(f) A claimant may:
(g) A determination under this section is limited to a determination of the amount claimed under a preconstruction or construction lien for the sole purpose of providing alternate security and does not conclusively establish: