- (1) In the selection of a construction manager/general contractor, a standard procurement process as defined in Section 63G-6a-103 may be used or an exception allowed under Part 8 of the Utah Procurement Code.
- (2) When the construction manager/general contractor enters into any subcontract that was not specifically included in the construction manager/general contractor's cost proposal, the construction manager/general contractor shall procure the subcontractors by using a standard procurement process as defined in Section 63G-6a-103 or an exception to the requirement to use a standard procurement process, described in Part 8 of the Utah Procurement Code.
KEY: contracts, procurement, public buildings
Date of Last Change: August 8, 2024
Notice of Continuation: January 10, 2022
Authorizing, and Implemented or Interpreted Law: 63A-5b-305; 63G-2-101 et seq.; 63G-6a-101 et seq.