16 U.S.C. § 824a–3
(a) Cogeneration and small power production rules Not later than 1 year after , the Commission shall prescribe, and from time to time thereafter revise, such rules as it determines necessary to encourage cogeneration and small power production, and to encourage geothermal small power production facilities of not more than 80 megawatts capacity, which rules require electric utilities to offer to—
Such rules shall be prescribed, after consultation with representatives of Federal and State regulatory agencies having ratemaking authority for electric utilities, and after public notice and a reasonable opportunity for interested persons (including State and Federal agencies) to submit oral as well as written data, views, and arguments. Such rules shall include provisions respecting minimum reliability of qualifying cogeneration facilities and qualifying small power production facilities (including reliability of such facilities during emergencies) and rules respecting reliability of electric energy service to be available to such facilities from electric utilities during emergencies. Such rules may not authorize a qualifying cogeneration facility or qualifying small power production facility to make any sale for purposes other than resale.
(b) Rates for purchases by electric utilities The rules prescribed under subsection (a) shall insure that, in requiring any electric utility to offer to purchase electric energy from any qualifying cogeneration facility or qualifying small power production facility, the rates for such purchase—
No such rule prescribed under subsection (a) shall provide for a rate which exceeds the incremental cost to the electric utility of alternative electric energy.
(c) Rates for sales by utilities The rules prescribed under subsection (a) shall insure that, in requiring any electric utility to offer to sell electric energy to any qualifying cogeneration facility or qualifying small power production facility, the rates for such sale—
(e) Exemptions
(3) No qualifying small power production facility or qualifying cogeneration facility may be exempted under this subsection from—
(f) Implementation of rules for qualifying cogeneration and qualifying small power production facilities
(g) Judicial review and enforcement
(h) Commission enforcement
(2)
(A) The Commission may enforce the requirements of subsection (f) against any State regulatory authority or nonregulated electric utility. For purposes of any such enforcement, the requirements of subsection (f)(1) shall be treated as a rule enforceable under the Federal Power Act [16 U.S.C. 791a et seq.]. For purposes of any such action, a State regulatory authority or nonregulated electric utility shall be treated as a person within the meaning of the Federal Power Act. No enforcement action may be brought by the Commission under this section other than—
(j) New dams and diversions Except for a hydroelectric project located at a Government dam (as defined in section 3(10) of the Federal Power Act [16 U.S.C. 796(10)]) at which non-Federal hydroelectric development is permissible, this section shall not apply to any hydroelectric project which impounds or diverts the water of a natural watercourse by means of a new dam or diversion unless the project meets each of the following requirements:
(2) Protected rivers At the time the application for a license or exemption for the project is accepted by the Commission (in accordance with the Commission’s regulations and procedures in effect on , including those relating to environmental consultation), such project is not located on either of the following:
(m) Termination of mandatory purchase and sale requirements
(1) Obligation to purchase After , no electric utility shall be required to enter into a new contract or obligation to purchase electric energy from a qualifying cogeneration facility or a qualifying small power production facility under this section if the Commission finds that the qualifying cogeneration facility or qualifying small power production facility has nondiscriminatory access to—
(A)
(B)
(2) Revised purchase and sale obligation for new facilities
(B) For the purposes of this paragraph, the term “existing qualifying cogeneration facility” means a facility that—
(5) Obligation to sell After , no electric utility shall be required to enter into a new contract or obligation to sell electric energy to a qualifying cogeneration facility or a qualifying small power production facility under this section if the Commission finds that—
(7) Recovery of costs
(n) Rulemaking for new qualifying facilities
(1)
(A) Not later than 180 days after , the Commission shall issue a rule revising the criteria in 18 CFR 292.205 for new qualifying cogeneration facilities seeking to sell electric energy pursuant to this section to ensure—
(2) Notwithstanding rule revisions under paragraph (1), the Commission’s criteria for qualifying cogeneration facilities in effect prior to the date on which the Commission issues the final rule required by paragraph (1) shall continue to apply to any cogeneration facility that—
(Pub. L. 95–617, title II, § 210, , 92 Stat. 3144; Pub. L. 96–294, title VI, § 643(b), , 94 Stat. 770; Pub. L. 99–495, § 8(a), , 100 Stat. 1249; Pub. L. 101–575, § 2, , 104 Stat. 2834; Pub. L. 109–58, title XII, § 1253(a), , 119 Stat. 967.)
The Federal Power Act, referred to in subsecs. (e), (h), (j)(1), and (m)(7)(B), is act June 10, 1920, ch. 285, 41 Stat. 1063, which is classified generally to this chapter (§ 791a et seq.). Part I of the Federal Power Act is classified generally to subchapter I (§ 791a et seq.) of this chapter. Part II of the Federal Power Act is classified generally to this subchapter (§ 824 et seq.). For complete classification of this Act to the Code, see section 791a of this title and Tables.
The Public Utility Holding Company Act, referred to in subsec. (e), probably means the Public Utility Holding Company Act of 1935, title I of act Aug. 26, 1935, ch. 687, 49 Stat. 803, which was classified generally to chapter 2C (§ 79 et seq.) of Title 15, Commerce and Trade, prior to repeal by Pub. L. 109–58, title XII, § 1263, , 119 Stat. 974. For complete classification of this Act to the Code, see Tables.
The Electric Consumers Protection Act of 1986, referred to in subsec. (j)(1), is Pub. L. 99–495, , 100 Stat. 1243. For complete classification of this Act to the Code, see Short Title of 1986 Amendment note set out under section 791a of this title and Tables.
This Act, referred to in subsecs. (m)(6) and (n)(1)(B), is Pub. L. 95–617, , 92 Stat. 3117, known as the Public Utility Regulatory Policies Act of 1978. For complete classification of this Act to the Code, see Short Title note set out under section 2601 of this title and Tables.
Section was enacted as part of the Public Utility Regulatory Policies Act of 1978, and not as part of the Federal Power Act which generally comprises this chapter.
, referred to in subsec. (n)(1)(A), was in the original “the date of enactment of this section”, which was translated as meaning the date of enactment of Pub. L. 109–58, which enacted subsecs. (m) and (n) of this section, to reflect the probable intent of Congress.
2005—Subsecs. (m), (n). Pub. L. 109–58 added subsecs. (m) and (n).
1990—Subsec. (e)(2). Pub. L. 101–575 inserted “(other than a qualifying small power production facility which is an eligible solar, wind, waste, or geothermal facility as defined in section 3(17)(E) of the Federal Power Act)” after first reference to “facility”.
1986—Subsecs. (j) to (l). Pub. L. 99–495 added subsecs. (j) and (k) and redesignated former subsec. (j) as (l).
1980—Subsec. (a). Pub. L. 96–294, § 643(b)(1), inserted provisions relating to encouragement of geothermal small power production facilities.
Subsec. (e)(1). Pub. L. 96–294, § 643(b)(2), inserted provisions relating to applicability to geothermal small power production facilities.
Subsec. (e)(2). Pub. L. 96–294, § 643(b)(3), inserted provisions respecting a qualifying small power production facility using geothermal energy as the primary energy source.
Pub. L. 99–495, § 8(b), , 100 Stat. 1250, provided that:
- “(1) Subsection (j) of section 210 of the Public Utility Regulatory Policies Act of 1978 (as amended by subsection (a) of this section) [16 U.S.C. 824a–3(j)] shall apply to any project for which benefits under section 210 of the Public Utility Regulatory Policies Act of 1978 are sought and for which a license or exemption is issued by the Federal Energy Regulatory Commission after the enactment of this Act [], except as otherwise provided in paragraph (2), (3) or (4) of this subsection.
- “(2) Subsection (j) shall not apply to the project if the application for license or exemption for the project was filed, and accepted for filing by the Commission, before the enactment of this Act [].
- “(3) Paragraphs (1) and (3) of such subsection (j) shall not apply if the application for the license or exemption for the project was filed before the enactment of this Act [] and accepted for filing by the Commission (in accordance with the Commission’s regulations and procedures in effect on , including those relating to the requirement for environmental consultation) within 3 years after such enactment.
“(4)
- (A) Paragraph (3) of subsection (j) shall not apply for projects where the license or exemption application was filed after enactment of this Act [] if, based on a petition filed by the applicant for such project within 18 months after such enactment, the Commission determines (after public notice and opportunity for public comment of at least 45 days) that the applicant has demonstrated that he had committed (prior to the enactment of this Act) substantial monetary resources directly related to the development of the project and to the diligent and timely completion of all requirements of the Commission for filing an acceptable application for license or exemption. Such petition shall be publicly available and shall be filed in such form as the Commission shall require by rule issued within 120 days after the enactment of this Act. The public notice required under this subparagraph shall include written notice by the petitioner to affected Federal and State agencies.
- “(B) In the case of any petition referred to in subparagraph (A), if the applicant had a preliminary permit and had completed environmental consultations (required by Commission regulations and procedures in effect on ) prior to enactment, there shall be a rebuttable presumption that such applicant had committed substantial monetary resources prior to enactment.
- “(C) The applicant for a license or exemption for a project described in subparagraph (A) may petition the Commission for an initial determination under paragraph (1) of section 210(j) of the Public Utility Regulatory Policies Act of 1978 [16 U.S.C. 824a–3(j)(1)] prior to the time the license or exemption is issued. If the Commission initially finds that the project will have substantial adverse effects on the environment within the meaning of such paragraph (1), prior to making a final finding under that paragraph the Commission shall afford the applicant a reasonable opportunity to provide for mitigation of such adverse effects. The Commission shall make a final finding under such paragraph (1) at the time the license or exemption is issued. If the Federal Energy Regulatory Commission has notified the State of its initial finding and the State has not taken any action described in paragraph (2) of section 210(j) before such final finding, the failure to take such action shall be the basis for a rebuttable presumption that there is not a substantial adverse effect on the environment related to natural, recreational, cultural, or scenic attributes for purposes of such finding.
- “(D) If a petition under subparagraph (A) is denied, all provisions of section 210(j) of the Public Utility Regulatory Policies Act of 1978 [16 U.S.C. 824a–3(j)] shall apply to the project regardless of when the license or exemption is issued.”
Amendment by Pub. L. 99–495 effective with respect to each license, permit, or exemption issued under this chapter after , see section 18 of Pub. L. 99–495, set out as a note under section 797 of this title.
Pub. L. 102–486, title XIII, § 1335, , 106 Stat. 2984, provided that:
“Nothing in section 210 of the Public Utility Regulatory Policies Act of 1978 (
Public Law 95–617) [
16 U.S.C. 824a–3] requires a State regulatory authority or nonregulated electric utility to treat a cost reasonably identified to be incurred or to have been incurred in the construction or operation of a facility or a project which has been selected by the Department of Energy and provided Federal funding pursuant to the Clean Coal Program authorized by
Public Law 98–473 [see Tables for classification] as an incremental cost of alternative electric energy.”
Pub. L. 100–202, § 101(d) [title III, § 310], , 101 Stat. 1329–104, 1329–126, provided that:
- “(a) The amendments made by section 643(b) of the Energy Security Act (Public Law 96–294) [amending this section] and any regulations issued to implement such amendment shall apply to qualifying small power production facilities (as such term is defined in the Federal Power Act [16 U.S.C. 791a et seq.]) using solar energy as the primary energy source to the same extent such amendments and regulations apply to qualifying small power production facilities using geothermal energy as the primary energy source, except that nothing in this Act [see Tables for classification] shall preclude the Federal Energy Regulatory Commission from revising its regulations to limit the availability of exemptions authorized under this Act as it determines to be required in the public interest and consistent with its obligations and duties under section 210 of the Public Utility Regulatory Policies Act of 1978 [this section].
“(b) The provisions of subsection (a) shall apply to a facility using solar energy as the primary energy source only if either of the following is submitted to the Federal Energy Regulatory Commission during the two-year period beginning on the date of enactment of this Act []:
- “(1) An application for certification of the facility as a qualifying small power production facility.
- “(2) Notice that the facility meets the requirements for qualification.”
Pub. L. 99–495, § 8(d), , 100 Stat. 1251, provided that:
- “(1) The Commission shall conduct a study (in accordance with section 102(2)(C) of the National Environmental Policy Act of 1969 [42 U.S.C. 4332(2)(C)]) of whether the benefits of section 210 of the Public Utility Regulatory Policies Act of 1978 [16 U.S.C. 824a–3] and section 210 of the Federal Power Act [16 U.S.C. 824i] should be applied to hydroelectric power facilities utilizing new dams or diversions (within the meaning of section 210(k) of the Public Utility Regulatory Policies Act of 1978).
- “(2) The study under this subsection shall take into consideration the need for such new dams or diversions for power purposes, the environmental impacts of such new dams and diversions (both with and without the application of the amendments made by this Act to sections 4, 10, and 30 of the Federal Power Act [16 U.S.C. 797, 803, 823a] and section 210 of the Public Utility Regulatory Policies Act of 1978 [16 U.S.C. 824a–3]), the environmental effects of such facilities alone and in combination with other existing or proposed dams or diversions on the same waterway, the intent of Congress to encourage and give priority to the application of section 210 of Public Utility Regulatory Policies Act of 1978 to existing dams and diversions rather than such new dams or diversions, and the impact of such section 210 on the rates paid by electric power consumers.
- “(3) The study under this subsection shall be initiated within 3 months after enactment of this Act [] and completed as promptly as practicable.
- “(4) A report containing the results of the study conducted under this subsection shall be submitted to the Committee on Energy and Commerce of the United States House of Representatives and the Committee on Energy and Natural Resources of the United States Senate while both Houses are in session.
- “(5) The report submitted under paragraph (4) shall include a determination (and the basis thereof) by the Commission, based on the study and a public hearing and subject to review under section 313(b) of the Federal Power Act [16 U.S.C. 825l(b)], whether any of the benefits referred to in paragraph (1) should be available for such facilities and whether applications for preliminary permits (or licenses where no preliminary permit has been issued) for such small power production facilities utilizing new dams or diversions should be accepted by the Commission after the moratorium period specified in subsection (e). The report shall include such other administrative and legislative recommendations as the Commission deems appropriate.
- “(6) If the study under this subsection has not been completed within 18 months after its initiation, the Commission shall notify the Committees referred to in paragraph (4) of the reasons for the delay and specify a date when it will be completed and a report submitted.”
Pub. L. 99–495, § 8(e), , 100 Stat. 1251, provided that:
“Notwithstanding the amendments made by subsection (a) of this section [amending section 824a–3 of this title], in the case of a project for which a license or exemption is issued after the enactment of this Act [], section 210 of the Public Utility Regulatory Policies Act of 1978 [16 U.S.C. 824a–3] shall not apply during the moratorium period if the project utilizes a new dam or diversion (as defined in section 210(k) of such Act) unless the project is either—
- “(1) a project located at a Government dam (as defined in section 3(10) of the Federal Power Act [16 U.S.C. 796(10)]) at which non-Federal hydroelectric development is permissible, or
- “(2) a project described in paragraphs (2), (3), or (4) of subsection (b) [set out as a note above].
For purposes of this subsection, the term ‘moratorium period’ means the period beginning on the date of the enactment of this Act and ending at the expiration of the first full session of Congress after the session during which the report under subsection (d) [set out as a note above] has been submitted to the Congress.”
For definitions of terms used in this section, see section 2602 of this title.
1 So in original. Probably should be followed by a comma.
2 See References in Text note below.
3 So in original. Probably should be followed by a period.