The Director of Cost Assessment and Program Evaluation, and the Secretary of the military department concerned or the head of the Defense Agency concerned (as applicable), shall each—
- (1) issue guidance requiring a discussion of risk, the potential impacts of risk on program costs, and approaches to mitigate risk in cost estimates for major defense acquisition programs and major subprograms;
- (2) ensure that cost estimates are developed, to the extent practicable, based on historical actual cost information that is based on demonstrated contractor and Government performance and that such estimates provide a high degree of confidence that the program or subprogram can be completed without the need for significant adjustment to program budgets; and
(3) include the information required in the guidance under paragraph (1)—
- (A) in any decision documentation approving a cost estimate within the baseline description or any other cost estimate for use at any event specified in section 3221(b)(6) of this title; and
- (B) in the next Selected Acquisition Report pursuant to sections 4351 through 4358 of this title in the case of a major defense acquisition program or major subprogram, or the next quarterly report pursuant to section 2445c of this title in the case of a major automated information system program.