10 U.S.C. § 2366b
(a) Certification.— A major defense acquisition program may not receive Milestone B approval until the milestone decision authority—
(1) has received a business case analysis and certifies on the basis of the analysis that—
(3) further certifies that—
(b) Changes to Certification.—
(1) The program manager for a major defense acquisition program that has received certification under subsection (a) shall immediately notify the milestone decision authority of any changes to the program or a designated major subprogram of such program that—
(c) Submission to Congress.—
(d) Waiver for National Security.—
(2) Whenever the milestone decision authority makes such a determination and authorizes such a waiver—
(3) The requirement in paragraph (2)(B) shall not apply to a program for which a certification was required pursuant to section 2433a(c) of this title if the milestone decision authority—
(A) determines in writing that—
(g) Definitions.— In this section:
(Added Pub. L. 109–163, div. A, title VIII, § 801(a), , 119 Stat. 3366, § 2366a; amended Pub. L. 109–364, div. A, title VIII, § 805, , 120 Stat. 2314; Pub. L. 110–181, div. A, title VIII, § 812, , 122 Stat. 219; renumbered § 2366b, Pub. L. 110–417, [div. A], title VIII, § 813(a), (b), , 122 Stat. 4527; Pub. L. 111–23, title I, § 101(d)(4), title II, §§ 201(f), 205(a), , 123 Stat. 1710, 1720, 1724; Pub. L. 111–383, div. A, title VIII, §§ 813(d)(1), 814(c), title IX, § 901(j)(4), title X, § 1075(k)(1), , 124 Stat. 4265, 4266, 4324, 4378; Pub. L. 112–81, div. A, title VIII, §§ 801(b), (e)(2), 819(b), , 125 Stat. 1483, 1484, 1501; Pub. L. 112–239, div. A, title III, § 322(e)(2), title IX, § 904(e)(2), , 126 Stat. 1695, 1867.)
Prior Provisions A prior section 2366b was renumbered section 2366a of this title.
Amendments 2013—Subsec. (a)(3)(D). Pub. L. 112–239, § 904(e)(2), substituted “the Assistant Secretary of Defense for Research and Engineering, in consultation with the Deputy Assistant Secretary of Defense for Developmental Test and Evaluation” for “the Assistant Secretary of Defense for Research and Engineering”.
Subsec. (a)(3)(F). Pub. L. 112–239, § 322(e)(2), which directed amendment of subsec. (A)(3)(F) of this section by substituting “core logistics capabilities” for “core depot-level maintenance and repair capabilities, as well as the associated logistics capabilities”, was executed by making the substitution in subsec. (a)(3)(F) of this section to reflect the probable intent of Congress.
2011—Pub. L. 112–81, § 801(e)(2)(A), struck out “or Key Decision Point B” after “Milestone B” in section catchline.
Subsec. (a). Pub. L. 112–81, § 801(e)(2)(B), struck out “, or Key Decision Point B approval in the case of a space program,” after “Milestone B approval” in introductory provisions.
Subsec. (a)(3)(D). Pub. L. 111–383, § 901(j)(4), substituted “Assistant Secretary of Defense for Research and Engineering” for “Director of Defense Research and Engineering”.
Subsec. (a)(3)(E) to (G). Pub. L. 112–81, § 801(b)(1), added subpars. (E) and (F) and redesignated former subpar. (E) as (G).
Subsec. (b)(1). Pub. L. 111–383, § 814(c)(1)(A), substituted “any changes to the program or a designated major subprogram of such program” for “any changes to the program” in introductory provisions.
Subsec. (b)(1)(B). Pub. L. 111–383, § 814(c)(1)(B), substituted “otherwise cause the program or subprogram” for “otherwise cause the program”.
Subsec. (b)(2). Pub. L. 112–81, § 801(e)(2)(C), struck out “(or Key Decision Point B approval in the case of a space program)” after “Milestone B approval”.
Subsec. (d)(1). Pub. L. 112–81, § 801(e)(2)(C), struck out “(or Key Decision Point B approval in the case of a space program)” after “Milestone B approval” in two places.
Pub. L. 111–383, § 813(d)(1)(A), substituted “(as specified in paragraph (1), (2), or (3) of subsection (a))” for “(as specified in paragraph (1) or (2) of subsection (a))”.
Subsec. (d)(2)(B). Pub. L. 111–383, § 1075(k)(1), which directed amendment of directory language of Pub. L. 111–23, § 205(a)(1)(B), resulting in substitution of “paragraphs (1), (2), and (3)” for “paragraphs (1) and (2)” in text, was not executed because of the prior identical amendment by Pub. L. 111–383, § 813(d)(1)(B). See below.
Pub. L. 111–383, § 813(d)(1)(B), substituted “specified in paragraphs (1), (2), and (3) of subsection (a)” for “specified in paragraphs (1) and (2) of subsection (a)”.
Subsec. (d)(3). Pub. L. 112–81, § 819(b), added par. (3).
Subsec. (g)(2) to (4). Pub. L. 111–383, § 814(c)(2), added par. (2) and redesignated former pars. (2) and (3) as (3) and (4), respectively. Former par. (4) redesignated (5).
Subsec. (g)(5). Pub. L. 112–81, § 801(b)(2), added par. (5) and struck out former par. (5) which read as follows: “The term ‘Key Decision Point B’ means the official program initiation of a National Security Space program of the Department of Defense, which triggers a formal review to determine maturity of technology and the program’s readiness to begin the preliminary system design.”
Pub. L. 111–383, § 814(c)(2)(A), redesignated par. (4) as (5).
2009—Subsec. (a)(1)(B). Pub. L. 111–23, § 201(f), inserted “appropriate trade-offs among cost, schedule, and performance objectives have been made to ensure that” before “the program is affordable”.
Subsec. (a)(1)(C). Pub. L. 111–23, § 101(d)(4), inserted “, with the concurrence of the Director of Cost Assessment and Program Evaluation,” before “the product”.
Subsec. (a)(1)(D). Pub. L. 111–23, § 205(a)(3)(A), struck out “and” at end.
Subsec. (a)(2), (3). Pub. L. 111–23, § 205(a)(3)(B), (C), added par. (2) and redesignated former par. (2) as (3).
Subsec. (a)(3)(D). Pub. L. 111–23, § 205(a)(3)(D)(i), substituted “, as determined by the Milestone Decision Authority on the basis of an independent review and assessment by the Director of Defense Research and Engineering; and” for semicolon.
Subsec. (a)(3)(E), (F). Pub. L. 111–23, § 205(a)(3)(D)(ii), (iii), redesignated subpar. (F) as (E) and struck out former subpar. (E) which read as follows: “the program demonstrates a high likelihood of accomplishing its intended mission; and”.
Subsec. (d). Pub. L. 111–23, § 205(a)(1), designated existing provisions as par. (1) and substituted par. (2) for “Whenever the milestone decision authority makes such a determination and authorizes such a waiver, the waiver, the determination, and the reasons for the determination shall be submitted in writing to the congressional defense committees within 30 days after the waiver is authorized.”
Subsecs. (e) to (g). Pub. L. 111–23, § 205(a)(2), added subsec. (e) and redesignated former subsecs. (e) and (f) as (f) and (g), respectively.
2008—Pub. L. 110–417, § 813(a), (b), renumbered section 2366a of this title as this section.
Subsec. (a). Pub. L. 110–181, § 812(1), amended subsec. (a) generally. Prior to amendment, subsec. (a) consisted of pars. (1) to (10) relating to required certifications by milestone decision authority for major defense acquisition program to receive Milestone B approval, or Key Decision Point B approval in the case of a space program.
Subsec. (b). Pub. L. 110–181, § 812(3), added subsec. (b). Former subsec. (b) redesignated (c).
Subsec. (c). Pub. L. 110–181, § 812(4), designated existing provisions as par. (1) and added par. (2).
Pub. L. 110–181, § 812(2), redesignated subsec. (b) as (c). Former subsec. (c) redesignated (d).
Subsec. (d). Pub. L. 110–181, § 812(5), substituted “authority may, at the time of Milestone B approval (or Key Decision Point B approval in the case of a space program) or at the time that such milestone decision authority withdraws a certification or rescinds Milestone B approval (or Key Decision Point B approval in the case of a space program) pursuant to subsection (b)(2), waive” for “authority may waive” and “paragraph (1) or (2)” for “paragraph (1), (2), (3), (4), (5), (6), (7), (8), or (9)”.
Pub. L. 110–181, § 812(2), redesignated subsec. (c) as (d). Former subsec. (d) redesignated (e).
Subsec. (e). Pub. L. 110–181, § 812(6), substituted “subsection (d)” for “subsection (c)”.
Pub. L. 110–181, § 812(2), redesignated subsec. (d) as (e). Former subsec. (e) redesignated (f).
Subsec. (f). Pub. L. 110–181, § 812(2), redesignated subsec. (e) as (f).
2006—Subsec. (a)(1) to (7). Pub. L. 109–364, § 805(a)(1)–(3), added par. (1) and redesignated former pars. (1) to (6) as (2) to (7), respectively. Former par. (7) redesignated (10).
Subsec. (a)(8), (9). Pub. L. 109–364, § 805(a)(4), (5), added pars. (8) and (9).
Subsec. (a)(10). Pub. L. 109–364, § 805(a)(1), redesignated par. (7) as (10).
Subsec. (c). Pub. L. 109–364, § 805(b), substituted “(5), (6), (7), (8), or (9)” for “(5), or (6)”.
Effective Date of 2013 Amendment Amendment by section 322(e)(2) of Pub. L. 112–239 effective , immediately after enactment of Pub. L. 112–81, see section 322(f) of Pub. L. 112–239, set out as an note under section 2366a of this title.
Effective Date of 2011 Amendment Pub. L. 111–383, div. A, title VIII, § 813(d)(1), , 124 Stat. 4265, provided that the amendment made by section 813(d)(1) is effective as of .
Amendment by section 901(j)(4) of Pub. L. 111–383 effective , see section 901(p) of Pub. L. 111–383, set out as a note under section 131 of this title.
Pub. L. 111–383, div. A, title X, § 1075(k), , 124 Stat. 4378, provided that the amendment made by section 1075(k)(1) is effective as of , and as if included in Pub. L. 111–23 as enacted.
Certification and Review of Programs Entering Development Prior to Enactment of Section 2366b of Title 10 Pub. L. 111–23, title II, § 205(b), , 123 Stat. 1725, as amended by Pub. L. 111–383, div. A, title VIII, § 813(d)(2), , 124 Stat. 4266, which related to certification and review of programs entering development prior to enactment of section 2366b of this title, was repealed by Pub. L. 112–239, div. A, title VIII, § 814, , 126 Stat. 1830.
Formal Review Process for Bandwidth Requirements Pub. L. 110–417, [div. A], title X, § 1047(d), , 122 Stat. 4603, as amended by Pub. L. 111–84, div. A, title X, § 1033, , 123 Stat. 2449, provided that:
“(1) In general.— The Secretary of Defense and the Director of National Intelligence shall, as part of the Milestone B or Key Decision Point B approval process for any major defense acquisition program or major system acquisition program, establish a formal review process to ensure that—
- “(A) the bandwidth requirements needed to support such program are or will be met; and
- “(B) a determination will be made with respect to how to meet the bandwidth requirements for such program.
- “(2) Reports.— Not later than January 1 of each year, the Secretary of Defense and the Director of National Intelligence shall each submit to the congressional defense committees [Committees on Armed Services and Appropriations of the Senate and the House of Representatives], the Select Committee on Intelligence of the Senate, and the Permanent Select Committee on Intelligence of the House of Representatives a report on any determinations made under paragraph (1) with respect to meeting the bandwidth requirements for major defense acquisition programs and major system acquisition programs during the preceding fiscal year.”