(a) Issuance of Orders.— The following actions are not required for issuance of a task or delivery order under a task or delivery order contract:
(b) Multiple Award Contracts.— When multiple task or delivery order contracts are awarded under section 2304a(d)(1)(B) or 2304b(e) of this title, all contractors awarded such contracts shall be provided a fair opportunity to be considered, pursuant to procedures set forth in the contracts, for each task or delivery order in excess of $2,500 that is to be issued under any of the contracts unless—
(d) Enhanced Competition for Orders in Excess of $5,000,000.— In the case of a task or delivery order in excess of $5,000,000, the requirement to provide all contractors a fair opportunity to be considered under subsection (b) is not met unless all such contractors are provided, at a minimum—
(e) Protests.—
(1) A protest is not authorized in connection with the issuance or proposed issuance of a task or delivery order except for—
(Added Pub. L. 103–355, title I, § 1004(a)(1), , 108 Stat. 3252; amended Pub. L. 110–181, div. A, title VIII, § 843(a)(2), , 122 Stat. 237; Pub. L. 111–350, § 5(b)(14), , 124 Stat. 3843; Pub. L. 111–383, div. A, title VIII, § 825, title X, § 1075(f)(5)(A), , 124 Stat. 4270, 4376; Pub. L. 112–239, div. A, title VIII, § 830, , 126 Stat. 1842; Pub. L. 114–328, div. A, title VIII, §§ 825(b), 835(a), , 130 Stat. 2280, 2285.)
2016—Subsec. (b)(5). Pub. L. 114–328, § 825(b), added par. (5).
Subsec. (e)(1)(B). Pub. L. 114–328, § 835(a), substituted “$25,000,000” for “$10,000,000”.
2013—Subsec. (e)(3). Pub. L. 112–239 struck out par. (3) which read as follows: “Paragraph (1)(B) and paragraph (2) of this subsection shall not be in effect after .”
2011—Subsec. (a)(1). Pub. L. 111–350 substituted “section 1708 of title 41” for “section 18 of the Office of Federal Procurement Policy Act (41 U.S.C. 416)”.
Subsec. (e). Pub. L. 111–383, § 1075(f)(5)(A), made technical correction to directory language of Pub. L. 110–181, § 843(a)(2)(C). See 2008 Amendment note below.
Subsec. (e)(3). Pub. L. 111–383, § 825, amended par. (3) generally. Prior to amendment, par. (3) read as follows: “This subsection shall be in effect for three years, beginning on the date that is 120 days after the date of the enactment of the National Defense Authorization Act for Fiscal Year 2008.”
2008—Subsec. (d). Pub. L. 110–181, § 843(a)(2), added subsec. (d). Former subsec. (d) redesignated (e).
Subsec. (e). Pub. L. 110–181, § 843(a)(2)(C), as amended by Pub. L. 111–383, § 1075(f)(5)(A), added subsec. (e) and struck out former subsec. (e). Former text read as follows: “A protest is not authorized in connection with the issuance or proposed issuance of a task or delivery order except for a protest on the ground that the order increases the scope, period, or maximum value of the contract under which the order is issued.”
Pub. L. 110–181, § 843(a)(2)(A), redesignated subsec. (d) as (e). Former subsec. (e) redesignated (f).
Subsecs. (f), (g). Pub. L. 110–181, § 843(a)(2)(A), redesignated subsecs. (e) and (f) as (f) and (g), respectively.
Pub. L. 110–181, div. A, title VIII, § 843(a)(3)(B), , 122 Stat. 238, provided that:
“The amendments made by paragraph (2) [amending this section] shall take effect on the date that is 120 days after the date of the enactment of this Act [
Jan. 28, 2008], and shall apply with respect to any task or delivery order awarded on or after such date.”
For effective date and applicability of section, see section 10001 of Pub. L. 103–355, set out as an Effective Date of 1994 Amendment note under section 2302 of this title.
This section not to be construed as modifying or superseding, or as intended to impair or restrict, authorities or responsibilities under former 40 U.S.C. 759 or chapter 11 of Title 40, Public Buildings, Property, and Works, see section 1004(d) of Pub. L. 103–355, set out as a note under section 2304a of this title.