43 Tex. Admin. Code § 21.41
Roadways adjacent to utility construction sites shall be kept free from debris, roadway construction material, and mud. At the end of every construction day, construction equipment and materials shall be removed as far from the roadway edges as feasible. When utility installation is complete, the right-of-way shall be reshaped to its original condition or better and the area reseeded or resodded to reduce erosion. Should settlement or erosion occur within six months after utility installation, the utility shall reshape, reseed, or resod the area.
Source Note:The provisions of this §21.41 adopted to be effective May 29, 1989, 14 TexReg 2370.