(a) Applicability.
- (1) This section applies to a transportation project if there are likely to be significant environmental impacts. The project sponsor will prepare an EIS that is a detailed public disclosure document that evaluates the impacts of the project.
- (2) This section applies to a transportation project that is a state transportation project or an FHWA transportation project, except that subsection (f) of this section applies only if the project is an FHWA transportation project.
(b) Content.
(1) An EIS must include:
- (A) a discussion of the purpose and need for the project;
- (B) an evaluation of all reasonable alternatives satisfying the purpose and need, their associated social, economic, and environmental impacts, an evaluation of alternatives eliminated from detailed study, and a determination of the preferred alternative;
- (C) a summary of studies conducted to determine the nature and extent of environmental impacts;
- (D) a description of the environmental impact of the project, any unavoidable adverse environmental impacts and associated measures to minimize harm, and any irreversible and irretrievable commitments of resources involved if the project is implemented;
- (E) a description of the direct, indirect, and cumulative effects of the project; and
- (F) a discussion of compliance with all applicable laws or reasonable assurances that the requirements can be met, and a description of the mitigation measures that are to be incorporated as EPICs into the project.
- (2) Coordination. The project sponsor will comply with §2.12 of this chapter (relating to Project Coordination), and will include in the EIS the results of coordination conducted before final approval of the EIS and a summary of the contacts with participating agencies and the comments received.
- (3) Public participation. The project sponsor will comply with §2.103 of this chapter (relating to Public Participation for an Environmental Impact Statement or Supplemental Environmental Impact Statement) and will include in the EIS the results of public participation and the comments received.
- (4) Organization. To the maximum extent possible, an EIS should summarize, incorporate by reference and include as appendices any separately prepared environmental reports supporting the EIS's conclusions, rather than repeat the detailed information from environmental reports in the body of the EIS.
(c) Processing the EIS.
(1) The project sponsor will in the following order:
- (A) publish a notice of intent and develop a coordination plan under §2.103 of this chapter;
- (B) conduct public participation and coordination in the manner and at the times prescribed by law;
- (C) prepare the draft EIS (DEIS);
- (D) publish the notice of availability of the DEIS;
- (E) conduct the public hearing;
- (F) prepare the final EIS (FEIS);
- (G) publish the notice of availability of the FEIS; and
- (H) prepare a draft record of decision (ROD).
- (2) The project sponsor will prepare a supplemental DEIS, a supplemental FEIS, or both if required by §2.86 of this subchapter (relating to Supplemental Environmental Impact Statements).
(d) Preparation of DEIS.
- (1) The project sponsor will prepare a DEIS that meets the requirements of subsection (b) of this section. A preferred alternative may be designated, if appropriate. The preferred alternative may be developed to a higher level of detail than other alternatives. The higher level detail must be limited to work necessary for preliminary design, as described by paragraph (5) of this subsection. The department delegate will review, and will approve the development of the preferred alternative to a higher level of detail if appropriate, and only if that development does not prevent the department from making an impartial decision as to whether to accept another alternative under consideration in the environmental review process.
- (2) The DEIS is subject to the department delegate's approval before it is made available to the public as a department document. For highway projects processed under Subchapter C of this chapter (relating to Environmental Review Process for Highway Projects), the DEIS is approved for public review on the department delegate's completing the technical review of the DEIS under §2.49 of this chapter (relating to Technical Review).
- (3) After the department delegate approves the DEIS, the project sponsor will circulate the DEIS and give notice of its availability in accordance with §2.103 of this chapter.
- (4) After the DEIS is circulated, public hearing held, and comments reviewed, the project sponsor will prepare an FEIS, or a supplemental DEIS if required.
(5) For the purposes of paragraph (1) of this subsection, preliminary design is the part of design work on a project that supports one or more of the activities listed in this paragraph but does not include an activity that is an irreversible commitment of resources that forecloses the implementation of reasonable and prudent alternatives. The activities include:
- (A) evaluation of alternative courses of action;
- (B) preparation of information to satisfy EPICs requirements;
- (C) work taken to reduce project risks for the final design and construction phase of the project, including geotechnical investigations, utility surveys, hazardous materials assessments, and other investigations and analyses; and
- (D) work taken to document a base case as part of an effort to define the requirements that apply to final design or construction.
(e) Preparation of FEIS.
- (1) The project sponsor will prepare an FEIS that meets the requirements of subsection (b) of this section and will prepare a public hearing record under §2.109 of this chapter (relating to Public Hearing).
- (2) After the department delegate approves the FEIS, the project sponsor will circulate the FEIS and publish notice of its availability in accordance with §2.103 of this chapter.
- (3) The department delegate will complete and sign a ROD not earlier than the 30th day after the date of the publication of the availability of the FEIS notice in the Texas Register. The ROD will present the basis for the decision, summarize the department's responses to comments received, and summarize any mitigation measures and commitments.
- (4) The department delegate will publish notice of the availability of the ROD in accordance with §2.103 of this chapter.
- (5) Until the required ROD is signed, no further approvals may be given except for administrative activities taken to secure further project funding.
- (6) If after a ROD is issued for a project the department approves an alternative that was not identified as the preferred alternative, the department delegate will prepare a revised ROD and will publish notice of the availability of the revised ROD in accordance with §2.103 of this chapter.
- (f) FHWA transportation project. For an FHWA transportation project, in addition to subsections (a) - (e) of this section, the department delegate and project sponsor must comply with any federal laws, including FHWA's rules, applicable to the processing of the project as an EIS. If federal law, including FHWA's rules, conflicts with this chapter, federal law controls to the extent of the conflict. At the conclusion of technical review, the department delegate will forward the environmental review document and any other relevant documentation to FHWA with an appropriate recommendation.
Source Note:The provisions of this §2.84 adopted to be effective April 16, 2012, 37 TexReg 1727.