(a) The commission, by written order, will select projects for funding under the TA Set-Aside Program based on:
- (1) recommendations from the director of the division responsible for administering the TA Set-Aside Program;
- (2) the potential benefit to the state of the project; and
- (3) whether the project enhances the surface transportation system.
- (b) The commission is not bound by project selection recommendations provided by the department.
- (c) The department will notify the project sponsor of the selection.
- (d) The commission will specify a fixed amount of TA Set-Aside funds for each project. Project costs in excess of this amount are the responsibility of the project sponsor. The project sponsor may seek additional funds through the TA Set- Aside Program in subsequent program calls.
- (e) A project that is not selected must be resubmitted to receive consideration during subsequent program calls.
Source Note:The provisions of this §11.411 adopted to be effective January 4, 2017, 41 TexReg 10664.