- (a) Changes after approval of engineering feasibility report. Applicant shall notify the executive administrator of any changes to the project that occur after the approval of the report but prior to the start of construction. The executive administrator shall review the proposed changes and notify the Applicant if additional engineering or other information is required.
- (b) Changes during construction. Any proposed change to the construction contract must be submitted to the executive administrator in the form of a formal change order; the change will be reviewed for compliance with program requirements. Depending upon the scope and complexity of the proposed change, approval by the executive administrator also may require amendments to other engineering and environmental documents.
Source Note:The provisions of this §371.81 adopted to be effective August 4, 2010, 35 TexReg 6680.