Upon completion of the aquifer storage well, the following information shall be obtained during the first phase of the project and submitted along with the application for final authorization:
- (1) as-built drilling and completion data on the well;
- (2) all logging and testing data on the well;
- (3) formation fluid analyses;
- (4) injection fluid analyses;
- (5) injectivity and pumping tests determining well capacity and reservoir characteristics;
- (6) hydrogeologic modeling, with supporting data, predicting mixing zone characteristics and injection fluid movement and quality; and
- (7) other information as determined by the executive director as necessary for the protection of underground sources of drinking water.
Source Note:The provisions of this §331.186 adopted to be effective June 28, 1996, 21 TexReg 5443.