(a) Any person or entity intending to initiate a LRPUT shall notify the executive director in writing of the intent to fill land by means of a LRPUT. Owners/operators of LRPUTs are required to provide information to the executive director as part of the notification document as described in paragraph (1) of this subsection. Approval in writing by the executive director (authorization to proceed) is required before the reclamation project may be initiated. The executive director may withhold authorization to proceed if the information submitted is not deemed to be complete. The executive director shall have 60 days to review the notification documents for completeness. The executive director may request additional information if the executive director determines that the notification submittal does not address all applicable requirements of this subchapter. The following information shall be submitted in the notification document or attachments thereto.
- (1) The owner/operator of the LRPUT shall disclose in the notification the location of the project on a state highway map, United States Geological Survey map or similar, and provide a legal description of the property. The general location on the site where fill activities will take place shall be shown on one or more of these maps;
(2) A property owner's affidavit shall be submitted at the time of notification of intent to initiate a LRPUT and shall include the following:
- (A) legal description of the property on which the LRPUT will occur; and
- (B) acknowledgment that the owner has a responsibility to file with the county deed records an affidavit to the public advising that a reclamation project utilizing tire pieces exists on the site, and providing details about the location of the filled area within the property boundaries, areal extent of the fill project, coordinates or survey data, and the approximate volume or weight of tires which were used as fill, at such time as the fill project has been completed;
- (3) The approximate volume of tire pieces proposed to be placed below ground, or the equivalent number of whole tires, and the approximate size and depth of the depression or borrow area to be filled shall be disclosed in the notification document;
- (4) The approximate period of time during which the project will be conducted shall be disclosed, with estimated start and finish dates;
- (5) The method of placement and commingling of the tire shreds to achieve a mix of tire pieces with the inert fill material in a proportion no greater than 50% of tire material by volume.
(6) A statement signed and sealed by a professional engineer licensed to practice in Texas shall be submitted in the notification to the executive director to certify that the LRPUT is designed in a manner that will comply the following standards.
- (A) The LRPUT shall not cause a discharge of solid waste or pollutants adjacent to or into the waters of the state, including ground water, that is in violation of the requirements of the Texas Water Code, §26.121;
- (B) The LRPUT shall not adversely affect human health, public safety or the environment, either during fill operations or after the reclamation project is complete; and
- (C) Tire or tire pieces shall not be placed below ground in a manner that constitutes disposal as defined in Texas Health and Safety Code §361.003(7);
(7) An affidavit signed by the property owner shall be submitted certifying that:
- (A) the borrow area, hole or disturbed land area existed before the project; was excavated for another purpose; and was not excavated for the burial of tire pieces;
- (B) the LRPUT will be completed in a manner that will comply with all regulations set forth in this subchapter and any other rules of the commission or any other local, state or federal agency which apply; and
- (C) the local fire marshal has been notified of the tire placement or fill activity.
- (8) An affidavit signed by the operator shall be submitted certifying that he or she is familiar with the application and all supporting data; is aware of all commitments represented in the notification; is familiar with all pertinent requirements in these regulations; and agrees to develop and operate the project in accordance with the application, applicable local and state regulations, and any special provisions that may be imposed by the executive director.
- (9) The owner or operator shall mail a copy of the notification documents and attachments to the appropriate mayor and county judge if the proposed project is to be located within the corporate limits or extraterritorial jurisdiction of a city; or the appropriate county judge if the proposed project is to be located within an unincorporated area of a county; and the appropriate regional council of government. Proof of mailing shall be provided in the form of return receipts for registered mail.
- (10) Upon the filing of the notification documents, the facility owner or operator shall provide notice to the general public by means of a notice by publication and a notice by mail. Each notice shall specify both the name, affiliation, address, and telephone number of the applicant and of the commission employee who may be reached to obtain more information about the LRPUT project. The notices shall specify that the notification documents have been provided to the county judge and that they are available for review by interested parties. The applicant shall publish notice in the county in which the facility is located, and in adjacent counties. The notice shall be published once a week for three weeks. The applicant should attempt to obtain publication in a Sunday edition of a newspaper. The notice by certified mail, return receipt requested, shall be sent to all adjacent landowners and all owners of property within 500 feet of the boundary of the project; the health authorities of the city and county in which the project will be located, if applicable; and the appropriate state senator and representative for the area encompassing the project.
- (b) Undisturbed land shall not be excavated for the purpose of filling the same land with a mixture of tires and debris or soil. Any borrow area, hole or other disturbed land area to be used for a LRPUT must have existed before the project, and it must have been excavated or soil removed for a purpose other than for the burial of tire pieces.
- (c) The LRPUT shall not result in a public nuisance.
- (d) The owner or operator of the LRPUT shall notify the local fire marshal or fire department serving the area of the tire placement or fill activity.
- (e) All tires used to fill land shall be split, quartered or shredded. Whole tires shall not be placed below ground.
- (f) The owner and operator of the LRPUT shall comply with all applicable local ordinances, including any public safety, or zoning and land use laws.
- (g) Shredded, split or quartered tires placed below ground shall be mixed in a proportion no greater than approximately 50% by volume with inert material acceptable for filling land. If greater than 50% of tire pieces by volume are placed below ground, the site is considered a tire monofill and is subject to §328.65 of this title (relating to Tire Monofill Permit Required).
- (h) Tire pieces shall be placed no closer than 18 inches to the final grade or ground surface. A soil cover unadulterated with tire pieces shall make up at least the upper 18 inches of the reclamation project.
- (i) The owner or operator of the LRPUT shall register as a scrap tire facility if a shredding operation is conducted on site for processing tires.
(j) The owner or operator of the LRPUT shall register as a scrap tire storage site under §328.60 of this title (relating to Scrap Tire Storage Site Registration) if:
- (1) operations requiring storage of more than 500 used or scrap tires (or weight equivalent tire pieces or any combination thereof) on the ground or more than 2,000 used or scrap tires (or weight equivalent tire pieces or any combination thereof) in enclosed and lockable containers would qualify the site as a registered tire storage site under §328.60 of this title (relating to Scrap Tire Storage Site Registration); and
- (2) the construction of the LRPUT extends beyond 90 days from the date of delivery of tires or tire pieces to the site.
- (k) The executive director shall issue an identifying number at the time the approval letter for the LRPUT is issued. This identifying number shall be referenced in any correspondence relating to a particular LRPUT for which such a number is issued.
- (l) A person may provide the commission with written comments on any notification of a LRPUT project. The executive director shall review any written comments when they are received within 30 days of mailing the notice. The written information received will be utilized by the executive director in determining what action to take on the application for a LRPUT.
- (m) Following completion of all fill activities for the LRPUT, the owner or operator shall submit to the executive director, for review and approval, a documented certification signed by a registered professional engineer verifying that the project has been completed in accordance with this subchapter, the notification documents, and all attachments. Once approved, this certification shall be placed in the file.
Source Note:The provisions of this §328.66 adopted to be effective September 5, 1999, 24 TexReg 6761.