(a) Velocities.
- (1) A force main must be a minimum of 4.0 inches in diameter, unless it is used in conjunction with a grinder pump station. The executive director may approve pipes with a diameter less than 4.0 inches where grinder pumps are used, on a case-by-case basis in writing.
- (2) For a lift station with two pumps, the minimum velocity is 3.0 feet per second with one pump in operation.
(3) For a lift station with three or more pumps:
- (A) the minimum velocity in a force main is 2.0 feet per second with only the smallest pump operating at full speed; and
- (B) a minimum flushing velocity of 5.0 feet per second or greater must occur in a force main at least twice daily.
- (4) The engineering report must certify that a pipeline with a velocity greater than 6.0 feet per second can withstand high and low negative surge pressures in the event of sudden pump failure.
(b) Detention Time.
- (1) Force main detention time calculations must be included in the engineering report.
- (2) Force main detention time calculations must be performed using a range of flow rates that represent the flows expected to be delivered to a force main by an upstream pump station during any 24-hour period.
- (c) Water Hammer. A force main design must include effective surge control measures to manage pressure due to water hammer that may exceed the working strength of a force main pipe.
(d) Connection to Gravity Main.
- (1) A force main must terminate at a collection system manhole or at a manhole or preliminary treatment unit at a wastewater treatment facility.
- (2) The discharge end of a force main inside a manhole must be restrained to prevent movement and must produce non-turbulent flow.
- (3) A collection system receiving wastewater from a force main must be designed to accept the maximum pump discharge from the force main without surcharging.
- (e) Pipe Separation. A separation distance between a force main and any water supply pipe must meet the minimum separation requirements established in §217.53(d) of this title (relating to Pipe Design).
(f) Odor Control.
- (1) A force main must terminate such that the flowline of the force main entering the manhole matches the flowline of the gravity pipe leaving the manhole.
- (2) A force main must be designed to abate anticipated odor. An owner shall implement odor control measures necessary to prevent a collection system from becoming a nuisance.
(g) Air Release Valves in Force Mains.
- (1) Any high point along the vertical force main alignment must include an air release valve or a combination of air release and air vacuum valves.
- (2) An air release valve must have an isolation valve between the air release valve and the force main.
- (3) An air release valve must be inside of a vault that is at least 48 inches in diameter and has a vented access opening of at least 30 inches in diameter.
- (4) An air release valve must be made of corrosion-resistant material.
- (h) Valves. A force main must have valves spaced at no more than 2,000 foot intervals to facilitate initial testing and subsequent maintenance and repairs.
- (i) Fatigue Life. The engineering report must include calculations that show the strength of the force main pipe at the end of the 50-year design life. The calculations must consider the fluctuations between a pressurized and depressurized operating state.
(j) Alignment Changes.
- (1) Bending a segmented pipe is prohibited, unless the pipe joints are welded or heat-fused.
- (2) Force main alignment changes must be accomplished using manufactured bend fittings.
- (3) Force main pipe joints must include mechanical joint restraints or thrust blocks at all bends unless pipe vibration calculations justify the absence of a joint restraint or thrust block.
Source Note:The provisions of this §217.67 adopted to be effective August 28, 2008, 33 TexReg 6843; amended to be effective December 4, 2015, 40 TexReg 8254.