- (a) After the public comment period or the conclusion of any notice and comment hearing, the executive director shall send notice by first-class mail of the proposed final action on the application to any person who commented during the public comment period or at the hearing, and to the applicant.
(b) The notice must include the following:
- (1) the response to any comments submitted during the public comment period;
- (2) identification of any change in the conditions of the draft permit and the reasons for the change;
- (3) a description and explanation of the process for public petitions to the EPA;
- (4) the date by which the petition must be filed; and
- (5) a statement that any person affected by the decision of the executive director may petition the Administrator.
Source Note:The provisions of this §122.345 adopted to be effective July 30, 1997, 22 TexReg 6867.