(a) To be eligible for a certificate of operation each boiler must meet the following:
- (1) comply with §65.200;
- (2) have a completed first inspection report;
- (3) if necessary, complete required repairs; and
- (4) pay the fees required under §65.300.
- (b) If the boiler has not been registered with the National Board, the owner or operator may apply to the department for a variance.
(c) Non-code boilers may not be installed or operated without written authorization from the department.
- (1) Non-code boilers, if installed, must be completely replaced to ensure the complete boiler meets or exceeds ASME code and this chapter.
- (2) Installing code compliant parts onto a non-code boiler does not make a non-code boiler ASME code compliant.
Source Note:The provisions of this §65.15 adopted to be effective June 15, 2015, 40 TexReg 3121.