- (a) Application. This rule applies to all transmission service providers (TSPs) operating in the ERCOT region.
- (b) Report. Each TSP must annually submit to the commission costs to interconnect electric generating facilities, including battery storage facilities, and retail loads connected to the ERCOT transmission system at transmission level voltage as prescribed by a commission approved form. For 2025, each TSP must submit the required information by filing it on the interchange filer located on the commission's website by October 31, 2025. Starting in 2026, the required information must be submitted by October 15th of each year using the commission's compliance reporting portal unless another method of submission is provided by commission staff.
Source Note:The provisions of this §25.75 adopted to be effective October 22, 2025, 50 TexReg 6875.