- (a) At any time that a Subrecipient believes they may be at risk of meeting one of the criteria noted in subsection (l) of this section relating to criteria for deobligation of funds, notification must be provided to the Department unless excepted under subsection (m) of this section.
- (b) A written 'Notification of Possible Deobligation' will be sent to the Executive Director of the Subrecipient by the Department as soon as a criterion listed in subsection (l) of this section is at risk of being met. Written notice will be sent electronically and/or by mail. The notice will include an explanation of the criteria met. A copy of the written notice will be sent to the Board of Directors of the Subrecipient by the Department seven (7) business days after the notice to the Executive Director has been released. A Notification will not be sent, and the steps in this section not triggered, if an Amendment increasing funds by at least 20% has been provided to the Subrecipient in the prior 90 days.
- (c) Within fifteen (15) days of the date of the "Notification of Possible Deobligation" referenced in subsection (b) of this section, a Mitigation Action Plan must be submitted to the Department by the Subrecipient in the format prescribed by the Department unless excepted under subsection (m) of this section.
(d) A Mitigation Action Plan is not limited to but must include:
- (1) Explanation of why the identified criteria under this section occurred setting out all fully relevant facts.
- (2) Explanation of how the criteria will be immediately, permanently, and adequately mitigated such that funds are expended during the Contract Period. For example, if production or expenditures appear insufficient to complete the Contract timely, the explanation would need to address how production or expenditures will be increased in the short- and long-term to restore projected full and timely execution of the contract.
- (3) If applicable because of failure to produce Unit Production or Expenditure targets under the existing Production Schedule, a detailed narrative of how the Production Schedule will be adjusted, going forward, to assure achievement of sufficient, achievable Unit Production and Expenditures to ensure timely and compliant full utilization of all funds.
- (4) An explanation of how the other criteria under this section will be mitigated. For example, if Unit Production criteria for a time period were not met, then the explanation will need to include how the other criteria will not be triggered.
- (5) If relating to a Unit Production or expenditure criteria, a description of activities currently being undertaken including an accurate description of the number of units in progress, broken down by number of units in each of these categories: units that have been qualified, audited, assessed, contracted, inspected, and invoiced and as reflected in an updated Production Schedule.
- (6) Provide any request for a reduction in Contracted Funds, reasons for the request, desired Contracted Funds and revised Production Schedule reflecting the reduced Contracted Funds.
- (e) At any time after sending a Notification of Deobligation, the Department or a third-party assigned by the Department may monitor, conduct onsite visits or other assessments or engage in any other oversight of the Subrecipient that is determined appropriate by the Department under the facts and circumstances.
- (f) The Department or a third-party assigned by the Department will review the Mitigation Action Plan, and where applicable, assess the Subrecipient's ability to meet the revised Production Schedule or remedy other concern.
- (g) After the Department's receipt of the Mitigation Action Plan, the Department will provide the Subrecipient a written Corrective Action Notice which may include one or more of the criteria identified in this section (relating to deobligation and other mitigating actions) or other acceptable solutions or remedies.
(h) The Subrecipient has seven (7) calendar days from the date of the Corrective Action Notice to appeal the Corrective Action Notice to the Executive Director. Appeals may include:
- (1) Request to retain for the full Fund Award if Partial Deobligation was indicated;
- (2) Request for only partial Deobligation of the full Contracted Fund if full Deobligation was indicated in the Corrective Action Notice;
- (3) Request for other lawful action consistent with the timely and full completion of the contract and Production Schedule for all Contracted Funds.
- (i) In the event that an appeal is submitted to the Executive Director, the Executive Director may grant extensions or forbearance of targets included in the Production Schedule, continued operation of a Contract, authorize Deobligation, or take other lawful action that is designed to ensure the timely and full completion of the Contract for all Contracted Funds.
- (j) In the event the Executive Director denies an appeal, the Subrecipient will have the opportunity to have their appeal presented at the next meeting of the Department's governing board for which the matter may be posted in accordance with law and submitted for final determination by the Board.
- (k) In the event an appeal is not submitted within seven (7) calendar days from the date of the Corrective Action Notice, the Corrective Action Notice will automatically become final without need of any further action or notice by the Department, and the Department will amend/terminate the contract with the Subrecipient to effectuate the Corrective Action Notice.
(l) The criteria noted in this subsection will prompt the Deobligation process under this rule. If the criteria are met, then notification and ensuing processes discussed elsewhere in this subchapter will apply.
- (1) Subrecipient fails to provide the Department with a Production Schedule for their current Contract within 30 days of receipt of the draft Contract. The Production Schedule must be signed by the Subrecipient Executive Director/Chief Executive Officer and approved by the Department in writing;
- (2) By the third program reporting deadline, for DOE units, Subrecipient must report at least one unit weatherized and inspected by a certified Quality Control Inspector ("QCI");
- (3) By the fifth program reporting deadline, less than 25% of total expected unit production has occurred based on the Production Schedule, or less than 20% of total Awarded Funds have been expended;
- (4) By the seventh program reporting deadline, less than 50% of total expected unit production has occurred based on the Production Schedule, or less than 50% of total Awarded Funds have been expended;
- (5) The Subrecipient fails to submit a required monthly report explaining any variances between the Production Schedule and actual results on Production Schedule criteria;
(m) Notification of deobligation will not be required to be sent to a Subrecipient, and a Mitigation Action Plan will not be required to be provided to the Department, if any one or more of the following are satisfied:
- (1) The total cumulative unit production for the Subrecipient, based on the monthly report as reported in the Community Affairs contract system, is at least 75% of the total cumulative number of units to be completed as of the end of the month according to the Subrecipient's forecast unit production within the Production Schedule for the time period applicable (i.e. cumulative through the month for which reporting has been made).
- (2) The total cumulative expenditures for the Subrecipient, based on the monthly report as reported in the Community Affairs contract system, is at least 75% of the total cumulative estimated expenditures to be expended as of the end of the month according to the Subrecipient's forecast expenditures within the Production Schedule for the time period applicable (i.e., cumulative through the month for which reporting has been made).
- (3) The Subrecipient's monthly reports as reported in the Community Affairs contract system, for the prior two months, as required under the Contract, reflects unit production that is 80% or more of the expected unit production amount to be completed as of the end of the month according to the Subrecipient's forecast unit production within the Production Schedule.
- (n) Subrecipients which have funds deobligated under this section that fully expend the reduced amount of their Contract, will have access to the full amount of their following Program Year WAP allocation. Subrecipients which have had funds deobligated under this section that fail to fully expend the reduced amount of their Contract will automatically have their following Program Year WAP allocation deobligated by the lesser of 24.99% or the proportional amount that had been deobligated in the prior year.
Source Note:The provisions of this §6.405 adopted to be effective December 4, 2016, 41 TexReg 9270.