Administrative Draw request. Administrative Draw requests are funded out of the portion of the Contract budget specified for administrative cost (administration line item of the Contract budget). These costs are not directly associated with an Activity. The administration line item will be disbursed as described in paragraphs (1) - (8) of this section:
- (1) Threshold 1. The initial administrative Draw request allows up to 10 percent of the administration line item to be drawn down prior to the start of any project Activity included in the Performance Statement of the Contract (provided that all Pre-Draw requirements, as described in the Contract, for administration have been met). Subsequent administrative funds will be reimbursed in proportion to the percentage of the work that has been completed as identified in paragraphs (2) - (8) of this section.
- (2) Threshold 2. Allows up to an additional fifteen (15) percent (twenty-five (25) percent of the total) of the administration line item to be drawn down after a start of project Activity has been demonstrated. For the purposes of this threshold, if Davis-Bacon labor standards are required for a given Program Activity, the "start of project Activity" is evidenced by the submission of a start of construction form. If labor standards are not required on a given project Activity that has commenced (and for which reimbursement is being sought), the submission of a Draw request that includes sufficient back-up documentation for expenses of non-administrative project Activities evidences a start of project Activity. Direct Delivery Costs charges will not constitute a start of project Activity.
- (3) Threshold 3. Allows up to an additional twenty-five (25) percent (fifty (50) percent of the total) of the administration line item to be drawn down after compliance with the twenty (20)-month threshold requirement has been demonstrated as described in §25.9 of this chapter (relating to Expenditure Thresholds and Closeout Requirements).
- (4) Threshold 4. Allows up to an additional twenty-five (25) percent (seventy-five (75) percent of the total) of the administration line item to be drawn down after compliance with the thirty-two (32)-month threshold requirement has been demonstrated as described in this chapter.
- (5) Threshold 5. Allows up to an additional fifteen (15) percent (ninety (90) percent of the total) of the administration line item to be drawn down after compliance with the forty-four (44)-month threshold requirement has been demonstrated as described in this chapter.
- (6) Threshold 6. Allows an additional five (5) percent (ninety-five (95) percent of the total) of the administration line item to be drawn down upon receipt of all required close-out documentation.
- (7) Threshold 7. Allows the final five (5) percent (one-hundred (100) percent of the total), less any administrative funds reserved for audit costs as noted on the Project Completion Report of the administration line item to be drawn down following receipt of the programmatic close-out letter issued by Department.
- (8) Threshold 8. Any funds reserved for audit costs will be released upon completion and submission of an acceptable audit. Only the portion of audit expenses reasonably attributable to the Contract is eligible.
Source Note:The provisions of this §25.8 adopted to be effective August 20, 2017, 42 TexReg 3965.