- (a) Direct Loan awardees must execute an Award Letter and Loan Term Sheet provided by the Department within 30 calendar days after receipt of the letter. The Award Letter and Loan Term Sheet will be conditional in nature and provide a basic outline of the terms and conditions approved by the Board.
- (b) If a Direct Loan award is returned after Board approval, or if the Applicant or Affiliates fail to timely close the loan, begin and complete construction, or leave a portion of the Direct Loan award unexpended, penalties may apply under 10 TAC §11.9(f) (relating to Competitive HTC Selection Criteria) and/or the Department may prohibit the Applicant and all Affiliates from applying for MFDL funds for a period of two years.
- (c) Direct Loan awardees must submit a fully completed environmental review (if applicable) including any applicable reports to the Department within 90 days after the Board approval date. Direct Loan awardees that commit any choice limiting activities prior to obtaining environmental clearance may lead to termination of the Direct Loan award.
- (d) Direct Loan awardees must execute a Contract within 60 days of environmental clearance being obtained, or, if environmental clearance is not required, within 60 days after the Board approval date.
- (e) Loan closing must occur and construction must begin no later than three months from the effective date of a Contract.
- (f) The Development Owner is required to submit quarterly construction status reports to the Asset Management Division as described and by the deadlines specified in 10 TAC §10.402(h) (relating to Housing Tax Credit and Tax Exempt Bond Developments).
- (g) In addition to any other requirements as the result of any other Department funding sources, the Development Owner must submit a mid-construction development inspection request once the development has met 25% construction completion as indicated on the G703 Continuation Sheet. Inspection staff will issue a mid-construction development inspection letter that confirms that work is being done in accordance with the applicable codes, the construction contract, and construction documents. Up to 50% of the Direct Loan award will be released prior to issuance of the mid-construction development inspection letter.
- (h) Construction must be completed, as reflected by the development's certificate(s) of occupancy and Certificate of Substantial Completion (AIA Form G704), and a final development inspection request must be submitted to the Department within 18 months of the actual loan closing date, with the repayment period beginning on the first day of the 25th month following the actual date of loan closing. The final development inspection letter will verify committed amenities have been provided and confirm compliance with all applicable accessibility requirements.
- (i) Receipt of a Closed Final Development Inspection Letter, indicating that all deficiencies identified in the Final Inspection Letter have been corrected, must occur within 24 months of the actual date of loan closing. The Final Development Inspection may be conducted concurrently with a Uniform Physical Condition Standards (UPCS) inspection. However, any letters associated with a UPCS inspection will not satisfy the Closed Final Development Inspection Letter requirement.
- (j) Extensions to the benchmarks in subsections (a) - (i) of this section may only be approved by the Executive Director or authorized designee in accordance with §13.12 or §13.13 of this chapter as applicable;
- (k) Initial occupancy of all MFDL assisted Units by eligible tenants shall occur within six months of the final Direct Loan draw. Requests to extend the initial occupancy period must be accompanied by documentation of marketing efforts and a marketing plan. The marketing plan may be submitted to HUD for final approval, if required by the MFDL fund source;
- (l) Repayment will be required on a per Unit basis for Units that have not been rented to eligible households within 18 months of the final Direct Loan draw.
- (m) Termination of the Direct Loan award and repayment of all disbursed funds will be required for any Development that is not completed within four years of the effective date of a Direct Loan Contract.
(n) Loan Closing. In preparation for closing any Direct Loan, the Development Owner must submit the items described in paragraphs (1) - (7) of this subsection:
- (1) Documentation of the prior closing or concurrent closing with all sources of funds necessary for the long-term financial feasibility of the Development.
- (2) Due diligence determined by the Department to be prudent and necessary to meet the Department's rules and to secure the interests of the Department.
- (3) Where the Department will have a first lien position and the Applicant provides personal guarantees from all principals, as well as documentation that closing on other sources is reasonably expected to occur within three months, the Executive Director or authorized designee may approve a closing to move forward without the closing on other sources. The Executive Director or the authorized designee of the Department must require a personal guarantee, in form and substance acceptable to the Department, from a Principal of the Development Owner for the interim period.
- (4) When Department funds have a first lien position during the construction period, assurance of completion of the Development in the form of payment and performance bonds in the full amount of the construction contract or equivalent guarantee in the sole determination of the Department is required. Such assurance of completion will run to the Department as obligee. Development Owners utilizing the USDA §515 program are exempt from this requirement but must meet the alternative requirements set forth by USDA.
(5) Documentation required for closing includes, but is not limited to:
- (A) Draft Owner/General Contractor agreement and draft Owner/Architect agreement prior to closing with final executed copies required by the day of closing;
- (B) Survey of the Property that includes a certification to the Department, Development Owner, Title Company, and other lenders;
- (C) Plans and specifications for review by the Department's inspection staff. Inspection staff will issue a plan review letter that is intended to assist in identifying early concerns associated with the Department's final construction requirements;
- (D) If layered with Housing Tax Credits, a fully executed limited partnership agreement between the General Partner and the tax credit investor entity (may be provided concurrent with closing);
- (E) Final Development information, including but not limited to a final development cost schedule, sources and uses, operating pro forma, annual operating expenses, cost categories for the Direct Loan funds, updated written financial commitments or term sheets and any additional financing exhibits that have changed since the time of application.
(6) If required by the fund source, prior to Contract Execution unless an earlier period is described in Chapter 10 or 11 of this title, the Development Owner must provide verification of:
- (A) Environmental clearance;
- (B) Site and Neighborhood clearance;
- (C) Documentation necessary to show compliance with the Uniform Relocation Assistance and Property Act and any other relocation requirements that may apply; and
- (D) Any other documentation that is necessary or prudent to meet program requirements or state or federal law in the sole determination of the Department.
- (7) The Direct Loan Contract as executed, which will be drafted by counsel or its designee for the Department. No changes proposed by the Developer or Developer's counsel will be accepted unless approved by the Department's Legal Division or its designee.
(o) Loan Documents. The Development Owner is required to execute all loan closing documents required by and in form and substance acceptable to the Department's Legal Division.
- (1) Loan closing documents include but are not limited to a promissory note, deed of trust, construction loan agreement (if the proceeds of the loan are to be used for construction), LURA, Architect and/or licensed engineer certification of understanding to complete environmental mitigation if such mitigation is identified in HUD's environmental clearance or the Real Estate Analysis Division (REA) Underwriting Report and assignment and security instruments whereby the Developer, the Development Owner, and/or any Affiliates (if applicable) grants the Department their respective right, title, and interest in and to other collateral, including without limitation the Owner/Architect agreement and the Owner/General Contractor agreement, to secure the payment and performance of the Development Owner's obligations under the loan documents. In the event the Development receives funding that requires the Department's funding to be in a subordinate position, the individual who is able to control the Development (all such individuals if more than one possess such power jointly and severally) will execute a personal guaranty in favor or the Department that in the event that the Development fails to fulfill its requirements of affordability for the required period, and as a result the Department is required to repay funds to the U.S. Department of Housing and Urban Development using non-federal funds and the net proceeds available to the Department after a foreclosure, deed in lieu of foreclosure, or similar disposition of the Development are insufficient to make such repayment, the guarantor(s) will jointly and severally guarantee repayment of that amount.
- (2) Repayment provisions will require repayment on a per unit basis for units that have not been rented to eligible households within 18 months of the final Direct Loan draw; termination and repayment of the Direct Loan award in full will be required for any Development that is not completed within four years of the date of Direct Loan Contract execution.
- (3) Loan terms and conditions may vary based on the type of Development, Real Estate Analysis underwriting report, and the set-aside under which the award was made.
(p) Disbursement of Funds. The Borrower must comply with the requirements in paragraphs (1) - (11) of this subsection in order to receive a disbursement of funds to reimburse eligible costs incurred. Submission of documentation related to the Borrower's compliance with these requirements may be required with a request for disbursement:
- (1) All requests for disbursement must be submitted through the Department's Housing Contract System, using the MFDL draw workbook or such other format as the Department may require;
- (2) Documentation of the total construction costs incurred and costs incurred since the last disbursement of funds must be submitted. Such documentation must be signed by the General Contractor and certified by the Development architect and is generally in the form of an AIA Form G702 or G703;
- (3) Disbursement requests must include a down-date endorsement to the Direct Loan (mortgagee) title policy or Nothing Further Certificate that includes a title search through the date of the Architect's signature on AIA form G702. For release of retainage the down-date endorsement to the Direct Loan title policy or Nothing Further Certificate must be dated at least 30 calendar days after the date of the completion as certified on the Certificate of Substantial Completion (AIA Form G704) with $0 as the work remaining to be completed. Disbursement requests for acquisition and closing costs are exempt from this requirement;
- (4) At least 50% of the funds will be withheld from the initial disbursement of loan funds to allow for periodic disbursements;
- (5) The initial draw request for the Development must be entered into the Department's Housing Contract System no later than 10 business days prior to the one year anniversary of the effective date of the Direct Loan Contract;
- (6) Up to 75% of Direct Loan funds may be drawn before providing evidence of Match. Thereafter, the Borrower must provide evidence of Match being credited to the Development prior to release of the final 25% of funds;
(7) Developer fee disbursement shall be limited by paragraph (9) of this subsection and further conditioned upon:
- (A) For Developments in which the loan is secured by a first lien deed of trust against the Property, 75% shall be disbursed in accordance with percent of construction completed. 75% of the total allowable fee will be multiplied by the percent completion, as documented by the construction contract and as may be verified by an inspection by the Department. The remaining 25% shall be disbursed at the time of release of retainage; or
- (B) For Developments in which the loan is not secured by a first lien deed of trust or the Development is also utilizing Housing Tax Credits, developer fees will not be reimbursed by the Department except as follows. If all other lenders and syndicator in a Housing Tax Credit development (if applicable) provide written confirmation that they do not have an existing or planned agreement to govern the disbursement of developer fees and expect that Department funds shall be used to fund developer fees, they shall be reimbursed in the same manner as described in subparagraph (A) of this paragraph; and
- (C) The Department may reasonably withhold any disbursement in accordance with the Loan Documents and if it is determined that the Development is not progressing as reasonably necessary to meet the benchmarks for the timely completion of construction of the Development as set forth in the loan documents, or that cost overruns have put the Development Owner's ability to repay its Direct Loan or complete the construction at risk in accordance with the terms of the loan documents and within budget. If disbursement has been withheld under this subsection, the Development Owner must provide evidence to the satisfaction of the Department that the Development will be timely completed and occupied in order to continue receiving funds. If Disbursement is withheld for any reason, disbursement of any remaining developer fee will be made only after construction of the Development has been completed, and all requirements for expenditure and occupancy have been met;
- (8) Expenditures must be allowable and reasonable in accordance with federal and state rules and regulations. The Department shall review each expenditure requested for reasonableness. The Department may request the Development Owner make modifications to the disbursement request and is authorized to modify the disbursement procedures set forth herein and to establish such additional requirements for payment of Department funds to Development Owner as may be necessary or advisable for compliance with all program requirements;
- (9) Table funding requests will not be considered unless the Direct Loan Contract has been executed and all necessary documentation has been completed and submitted to the Department at least 10 calendar days prior to planned closing;
(10) Following 50% construction completion, any funds will be released in accordance with the percentage of construction completion. Ten percent of requested Hard Costs will be retained and will not be released until the final draw request. If the Development is receiving funds from more than one MFDL source, the retainage requirement will apply to each fund source individually. All of the items described in subparagraphs (A) - (G) of this paragraph are required in order to approve the final draw request:
- (A) Fully executed Certificate of Substantial Completion (AIA Form G704) with $0 as the cost estimate of work that is incomplete;
- (B) A down date endorsement to the Direct Loan title policy or Nothing Further Certificate dated at least 30 calendar days after the date of completion as certified on the Certificate of Substantial Completion (AIA Form G704);
- (C) For Developments not layered with Housing Tax Credits, a Closed Final Development Inspection Letter from the Department;
- (D) For Developments subject to the Davis-Bacon Act, evidence from the Senior Labor Standards Specialist that the final wage compliance report was received and approved or confirmation that HUD maintains Davis-Bacon oversight as a result of a HUD-insured first lien loan;
- (E) Certificate(s) of Occupancy (if New Construction);
- (F) Development completion reports, which includes, but is not limited to, documentation of full compliance with the Uniform Relocation Act/104(d), Match Documentation requirements, and Section 3 of the Housing and Urban Development Act of 1968, as applicable to the Development, and any other applicable requirement; and
- (G) If applicable to the Development, certification from Architect or a licensed engineer that all HUD and REA environmental mitigation conditions have been met.
- (11) The final draw request must be submitted within 24 months from loan closing. Extensions to this deadline may only be granted in accordance with §13.12(3) of this chapter (relating to Pre-Closing Amendments to Direct Loan Terms).
Source Note:The provisions of this §13.11 adopted to be effective December 30, 2018, 43 TexReg 8414.