The purpose of this section is to identify the threshold documentation that is specific to the request for Supplemental Allocation submission, unless specifically indicated or otherwise required by Department rule. Only those documents listed herein may be submitted.
- (1) Certification, Acknowledgement and Consent of Development Owner. A certification of the information in this subchapter as well as Subchapter B of this chapter must be executed by the Development Owner and addresses the specific requirements associated with the Development. The Person executing the certification is responsible for ensuring all individuals referenced therein are in compliance with the certification and that they have given it with all required authority and with actual knowledge of the matters certified. Applicants must certify that there has been no change to the Applicant Eligibility or Original Owner Certification since the Original Application was submitted.
- (2) Site Requirements and Restrictions. The Applicant must certify that there have been no changes from the Original Application that would require additional disclosure or mitigation, or render the proposed Development Site ineligible. Any change must be addressed under the requirements of §10.405 of this title (relating to Amendments and Extensions).
(3) Financing Requirements. Supplemental Credit Applications must include updated exhibits and supporting information required under §11.204(7) of this chapter (relating to Required Documentation for Application Submission), along with construction contracts or contractor bids with a detailed schedule of values to support the Development Cost Schedule. The Financing Narrative should describe changes to the financial structure of the Supplemental Credit Application since the Original Application was submitted. Applicants should utilize 2021 rents in their updated exhibits; any resulting changes to operating expenses must include an explanation and rationale for the changes. Requests must include evidence from the Applicant's equity investor that the additional credits will be purchased and state the dollar value associated with that purchase. Eligible cost increases are not limited to construction costs, additionally, all cost increases must be substantiated. Supplemental Credit Applications that include Rehabilitation or Adaptive Reuse activities must include a letter from the Original Application Scope and Cost Review provider certifying that the scope of the project has not changed from the Original Application; the Development Cost Schedule must be supported by either:
- (A) construction contracts or contractor bids, or
- (B) an updated Scope and Cost Review Supplement.
- (4) Site Control. Applicants must certify that there has been no change to Site Control, other than extensions or purchase by the Applicant, since the Original Application was submitted. If the nature of Site Control has changed, Supplemental Credit Applicants must submit the appropriate documentation as described in §11.204(10) of this chapter (relating to Site Control).
- (5) Zoning. (§2306.6705(5)) If the zoning status of the Development has changed since the Original Application, the Supplemental Credit Application must include all requirements of §11.204(11) of this chapter (relating to Zoning).
Source Note:The provisions of this §11.1007 adopted to be effective December 23, 2021, 46 TexReg 8589.