- (a) The Department will monitor the entire construction phase for all applicable requirements according to the level of risk. After Final Construction during the Affordability Period, the Department will periodically monitor the Development to assure that the initial compliance review was correct.
- (b) Owners are required to submit evidence of final construction within thirty (30) days of completion in a format prescribed by the Department. In addition, the Architect of Record must submit a certification that the Development was built in compliance with all applicable laws and the Engineer of Record (if applicable) must submit a certification that the Development was built in compliance with the design requirements.
- (c) The Department will conduct a final inspection after receipt of notification of final construction. During the inspection, the Department will confirm that committed amenities have been provided and will inspect for compliance with the applicable accessibility laws. In addition, a Uniform Physical Condition Standards inspection may be completed.
- (d) Owners will be provided a written notice after the final inspection. If any deficiencies are noted, a corrective action period will be provided.
- (e) Forms 8609 and final retainage will not be released until the Owner receives written notice from the Department that all noted deficiencies have been resolved.
- (f) During any construction inspection, if the Owner and the Department are unable to agree that an identified issue is a violation, the Owner must request Alternative Dispute Resolution (ADR). The process for engaging ADR is outlined in §10.622 of this chapter (relating to Alternative Dispute Resolution).
Source Note:The provisions of this §10.602 adopted to be effective December 27, 2012, 37 TexReg 9908.