(a) Loan Closing. The loan closing must occur no more than nine (9) months from the date of the Commitment or similar document is executed, which may be extended in accordance with the provisions in this subchapter. In preparation for closing any Direct Loan, the Development Owner must submit the items described in paragraphs (1) - (7) of this subsection:
- (1) documentation of the prior or reasonable assurance of a concurrent closing with any superior lien holders or any other sources of funds determined to be necessary for the long-term financial feasibility of the Development and all due diligence determined by the Department to be prudent and necessary to meet the Department's rules and to secure the interests of the Department. Where the Department will have a first lien position and the Applicant provides documentation that closing on other sources is reasonably expected to occur within three (3) months, the Executive Director or authorized designee may approve a closing to move forward without the closing on other sources. The Executive Director as the authorized designee of the Department must require a personal guarantee, in form and substance acceptable to the Department, from a Principal of the Development Owner for the interim period;
- (2) when Department funds have a first lien position, assurance of completion of the Development in the form of payment and performance bonds in the full amount of the construction contract will be required or equivalent guarantee in the sole determination of the Department. Such assurance of completion will run to the Department as obligee. Development Owners also utilizing the USDA §515 program are exempt from this requirement but must meet the alternative requirements set forth by USDA;
- (3) Owner/General Contractor agreement and Owner/ Architect agreement;
- (4) survey of the Property that includes a certification to the Department, Development Owner, Title Company, and other lenders;
- (5) if layered with Housing Tax Credits, a fully executed limited partnership agreement between the General Partner and the tax credit investor entity (may be provided concurrent with closing);
- (6) a revised development cost schedule, sources and uses, operating proforma, planned cost categories for the use of Direct Loan funds, updated written financial commitments/term sheets and any additional budget schedules that have changed since the time of application. If the budget or sources of funds reflect material changes from what was approved by the Board that may affect the financial feasibility of the Development, the Department may request additional documentation to ensure that the Development continues to meet the requirements of Subchapter D of this chapter (relating to Underwriting and Loan Policy);
(7) if required for the Direct Loan, prior to closing, the Development Owner must have received verification of:
- (A) environmental clearance;
- (B) verification of HUD Site and Neighborhood clearance;
- (C) documentation necessary to show compliance with the Uniform Relocation Act and any other relocation requirements that may apply; and
- (D) any other documentation that is necessary or prudent to meet program requirements or state or federal law in the sole determination of the Department.
- (b) Loan Documents. The Development Owner is required to execute all loan closing documents required by and in form and substance acceptable to the Legal Division including but not limited to a promissory note, deed of trust, construction loan agreement (if the proceeds of the loan are to be used for construction), LURA, HOME contract, Architect and/or licensed engineer certification of understanding to complete environmental mitigation if such mitigation is identified in HUD's environmental clearance and by the Real Estate Analysis Division (REA) and assignment and security instruments whereby the Developer, the Development Owner, and/or any Affiliates (if applicable) grants the Department their respective right, title, and interest in and to other collateral, including without limitation the Owner/Architect agreement and the Owner/General Contractor agreement, to secure the payment and performance of the Development Owner's obligations under the loan documents. Repayment provisions will require repayment on a per unit basis for units that have not been rented to eligible households within eighteen (18) months of project completion; termination and repayment of the HOME award in full will be required for any development that is not completed within four (4) years of the date of funding commitment.
(c) Disbursement of Funds (including developer fees). The Development Owner must comply with the requirements in paragraphs (1) - (9) of this subsection for a request for disbursement of funds to reimburse eligible costs incurred. Submission of documentation related to the Development Owner's compliance with these requirements may be required with a request for disbursement:
- (1) except for disbursement requests made for acquisition and closing costs or requests made for soft costs only, a down-date endorsement to the title policy not older than the Architect's certification date on AIA form G702 or sixty (60) calendar days, whichever is later. For release of retainage the down-date endorsement must be dated at least thirty (30) calendar days after the date of the construction completion as certified on the Certificate of Substantial Completion (AIA Form G704);
- (2) for hard construction costs, documentation of the total construction costs incurred and costs incurred since the last disbursement of funds must be submitted. Such documentation must be signed by the General Contractor and certified by the Development architect and is generally in the form of an AIA Form G702 or G703;
- (3) the Department will require that at least 50 percent of the funds be withheld from the initial disbursement to allow for periodic disbursements, or such lesser amount provided it meets all federal requirements. For HOME Direct Loans: The initial draw request for the development must be entered no later than ten business days prior to the one year anniversary of the commitment date (as defined in 24 CFR Part 92) or funds may be cancelled in HUD's IDIS system;
- (4) if applicable, up to 75 percent of Direct Loan funds may be drawn before providing evidence of Match. Thereafter, each Development Owner must provide evidence of Match in the form of a formal contract or commitment with the vendor clearly delineating the donated portion of the contract price, invoices showing the forgiven amount, or other equally verifiable third party documentation prior to release of the final 25 percent of funds. If funds are requested on the day of closing, an executed formal contract specifying the terms of the Match must be provided;
(5) Developer fee disbursement shall be conditioned upon:
- (A) for Developments in which the loan is secured by a first lien deed of trust against the Property, 75 percent shall be disbursed in accordance with percent of construction completed (i.e. 75 percent of the total allowable fee will be multiplied by the percent completion) as documented by the construction contract and as may be verified by an inspection by the Department. The remaining 25 percent shall be disbursed at the time of release of retainage; or
- (B) for Developments in which the loan is not secured by a first lien deed of trust or the Development is also utilizing Housing Tax Credits, developer fees will not be reimbursed by the Department unless the other lenders and syndicator confirm in writing that they do not have an existing or planned agreement to govern the disbursement of developer fees and expect that Department funds shall be used to fund developer fees. Provided this requirement is met, developer fees shall be reimbursed in the same manner as described in subparagraph (A) of this paragraph; and
- (C) the Department may reasonably withhold any disbursement of developer fees if it is determines that the Development is not progressing as necessary to meet the benchmarks for the timely completion of construction of the Development that is set forth in the loan documents, or that cost overruns have put the Development Owner's ability to repay its Direct Loan or complete the construction of the Development Owner's ability to repay its Direct Loan or complete the construction of the Development in accordance with the terms of the loan documents and within budget at risk. Once a reasonable alternative that is deemed acceptable by the Department has been provided, disbursement of the remaining fee may occur;
- (6) expenditures must be allowable and reasonable in accordance with federal, state, and local rules and regulations. The Department shall determine the reasonableness of each expenditure requested. The Department may request the Development Owner make modifications to the disbursement request and is authorized to modify the disbursement procedures set forth herein and to establish such additional requirements for payment of Department funds to Development Owner as may be necessary or advisable for compliance with all program requirements. For HOME Direct Loans: Pre-award costs for predevelopment activities, as specified in the loan documents, are allowable only if they were incurred less than 24 months prior to the commitment date (as defined in 24 CFR Part 92) and were associated with the Application Round in which the project was awarded;
(7) table funding requests will not be considered unless:
- (A) a "Commitment to a specific local project" as defined in 24 CFR Part 92 has been made, if applicable; and
- (B) ten (10) days prior to anticipated closing, all table funding draw documentation has been completed and submitted to the Department;
- (8) each Development Owner must request a progress inspection from Department staff once the property passes 25 percent construction completion based on the AIA G702-703. Up to 50 percent of the HOME award will be released prior to receipt of documentation that the progress inspection has occurred;
(9) Following fifty percent construction completion, the remaining HOME funds will be released in accordance with the percentage of construction completion, not to exceed ninety percent of award, at which point funds will be held as retainage until the final draw request. Retainage will be held until all of the items described in subparagraphs (A) - (G) of this paragraph are received:
- (A) Certificate of Substantial Completion (AIA Form G704);
- (B) A down date endorsement dated at least 30 calendar days after the date of completion as certified on the Certificate of Substantial Completion (AIA Form G704);
- (C) For developments not layered with Housing Tax Credits, a Closed Final Development Inspection Letter from the Department;
- (D) For developments subject to the Davis-Bacon Act, evidence from the Senior Labor Standards Specialist that the final wage compliance report was received and approved;
- (E) Receipt of Certificates of Occupancy for New Construction or a Certificate of Substantial Completion (AIA Form G704); from the Development Architect for Rehabilitation;
- (F) Development completion reports which may include documentation of full compliance with the Uniform Relocation Act, Davis-Bacon Act, and Section 3 of the Housing and Urban Development Act of 1968, as applicable to the Development, and any other applicable requirement; and
- (G) If applicable to the Development, certification from Architect or a licensed engineer that all HUD and REA environmental mitigation conditions have been met.
Source Note:The provisions of this §10.403 adopted to be effective December 9, 2014, 39 TexReg 9518.