- (a) The commission is the authority responsible for certifying whether a project has met the requirements for a clean energy project.
(b) An entity may apply to the commission for a certification that a project operated by the entity meets the requirements for a clean energy project. The application must be accompanied by:
- (1) a certificate from a qualified independent engineer that the project is operational and meets the standards provided by Sections 120.001(2)(A), (B), and (C); and
- (2) a fee payable to the commission.
- (c) The amount of the fee prescribed by Subsection (b)(2) is $50,000 unless the commission by rule determines that a fee in a greater amount is necessary to cover the commission's costs of processing an application.
Added by Acts 2009, 81st Leg., R.S., Ch. 1109 (H.B. 469), Sec. 3, eff. September 1, 2009.