S.D. Codified Laws § 34A-2-119.1 (2026)
There is hereby imposed an annual stormwater fee on each construction and industrial site that is required to operate under a general water pollution control permit issued under chapter 34A-2. The annual fee imposed in § 34A-2-117 is as follows:
(3) The secretary may promulgate rules, pursuant to chapter 1-26, to establish an annual tiered fee for each industrial site that is required to operate under a general water pollution control permit for stormwater discharges associated with industrial activities as defined under 40 CFR Part 126 as amended to January 1, 2018, and issued under chapter 34A-2. The tiered fee structure shall equitably assess an annual fee to cover the reasonable costs of developing and administering the stormwater permitting requirements for industrial activities that include:
The annual fee is in addition to any other fee or tax levied by law. The fee imposed by this section shall be remitted to the state along with any form as may be prescribed by the state. The fees shall be deposited in the surface water discharge and pretreatment permit administrative subfund established in § 34A-2-121.
Disturbed Area (Acres)
Fee ($)
Less than 5
100
5 to less than 40
250
40 to less than 80
500
80 or more
750
The fee is payable by the owner of the site. For any construction site permitted before July 1, 2018, the first annual stormwater fee payment is due on January 31, 2019. Any future annual fee accrues on January first of each year and is due on January thirty-first until the permit coverage is terminated. For any construction site permitted after June 30, 2018, the first annual stormwater fee payment is due when the owner submits the notice of intent to be covered under the general permit for stormwater discharges associated with construction activity. For any permit that continues beyond one year, the annual stormwater fee accrues on the anniversary of the notice of intent submission and is due thirty days later; and
Source: SL 2018, ch 212 , § 3.