(A) The owner must provide and maintain a written checklist for the daily operating procedures which shall include at least the following:
- (1) setting up the site equipment and public amenities;
- (2) inspecting and testing of all equipment before beginning daily operations;
- (3) inspecting and testing the communication system for proper operation;
- (4) inspecting and testing of the jump equipment;
- (5) review of the jump procedures with all bungee staff;
- (6) review of all emergency procedures with all bungee staff;
- (7) conducting test jumps on all bungee cords to be used that day.
(B) The owner must maintain a permanent log of the following daily activities for each bungee site:
- (1) confirmation that daily operating procedures were performed and compilation of the corresponding checklist;
- (2) compilation of the checklists on jump procedures;
- (3) the number of jumps made on each bungee cord which must be done by referencing the permanent identification number of each cord used.
HISTORY: 1994 Act No. 408, Section 32, eff 60 days after May 24, 1994.