880-RICR-00-00-3
B. The Port of Davisville is subject to the following federal regulations:
A. The following Definitions shall apply in this tariff:
10. "Ton" means 2,000 pounds (LBS) of weight.
B. When used, the following abbreviations shall mean:
A. The Terminal Tariff Charges provided for herein do not include insurance of any kind, nor will such insurance be covered by the QDC under their policies.
E. Cancellation Fee – Vessels that are 1) assigned a berth pursuant to the Port Rules; 2) do not cancel or amend their berthing applications more than 48 hours in advance of the scheduled arrival time; and 3) do not arrive within one (1) hour of their scheduled arrival time shall be charged a cancellation fee equal to the dockage charge the vessel would have otherwise paid.
A. The wharfage charges set forth in §3.8.8 of this Part shall apply to all cargo handled over the wharfs of the Port and shall be assessed against the consignee or its authorized agents.
C. Free Time shall be granted at the discretion of the QDC, and shall not impede any other vessels and/or cargo operations. Free Time shall be allowed according to the following circumstances:
1. Loading
2. Discharging
3. Cargo
c. Abandoned Cargo - Cargo remaining on the terminal facility in excess of forty-five (45) days will be considered abandoned and sold to satisfy any terminal charges that might be due to the QDC. Fifteen days prior to such sale, a registered return receipt letter of notice will be mailed to the owner of record. Any amount received beyond the charges due, will be forwarded to the owner of record of the cargo if claimed within one year of mailed notice.
D. Ships’ crew and workers going to and from an offshore installation or construction area shall not be charged a passenger fee.
C. Use of any Port facility outside of the normal business hours, as such hours are defined in § 2.10(B) of this Title shall be assessed an hourly Port Operations Fee as set forth in § 3.8.8 of this Part.
C. Crane Operator - All firms providing crane service at the Port shall be assessed 10% of gross rentals based on the equipment usage with a minimum charge of $500.00, exclusive of manpower required to operate said equipment, for the privilege of using the QDC property and all such firms will furnish the QDC a monthly report of their activities at the Port for billing purposes. Firms leasing property at the Port from the QDC are excluded from the above charge.
I. Failure to Provide Information – Failure to provide information as required by § 2.10.1(C) of this Title shall result in assessment of a fee set forth in § 3.8.8 of this Part.
A. The rates set forth in the schedule contained herein shall be applicable for Fiscal Year 2025 (beginning on the effective date of this Part), Fiscal Year 2026, and Fiscal Year 2027, as outlined below. Beginning in Fiscal Year 2028 (on July 1, 2027) and for every Fiscal Year thereafter, the rates herein shall increase by the greater of (i) 2.5%; or (ii) the change in the Consumer Price Index for All Urban Consumers (CPI-U) for the previous calendar year. (For example, for the increase due to be effective on July 1, 2027, the change from January 1, 2026 through December 31, 2026 will be used to calculate the increase for the Fiscal Year.) For future years, the rate will be rounded to the nearest ten-cent ($0.10) increment. QDC shall set and publish the new rate schedule prior to the start of each Fiscal Year. QDC, in its sole discretion, may opt out of the fee increase for any Fiscal Year.
| SERVICE | FY 25 RATE | FY 26 RATE | FY 27 RATE | Refer to Section | ||
| 1. DOCKAGE | 1.1 | Self-Propelled VSL > 450' LOA / Foot / 24 hours | $5.51 | $5.90 | $6.31 | 3.8.1.A |
| 1.2 | Self-Propelled VSL > 450' LOA – Minimum Charge | $2,479.73 | $2,653.31 | $2,839.04 | 3.8.1.A | |
| 1.3 | Self-Propelled VSL < or = 450' LOA / Foot / 24 hours | $4.41 | $4.72 | $5.05 | 3.8.1.A | |
| 1.4 | Self-Propelled VSL < or = 450' LOA – Minimum Charge | $267.50 | $286.23 | $306.26 | 3.8.1.A | |
| 1.5 | Self-Propelled VSL in Idle Status / 24 hours | $551.05 | $589.62 | $630.90 | 3.8.1.A | |
| 1.6 | Non-Self-Propelled VSL / 24 hours | $802.50 | $858.68 | $918.78 | 3.8.1.A | |
| 1.7 | Cruise or Passenger VSL / net registered ton / 24 hours | $0.44 | $0.47 | $0.50 | 3.8.1.A | |
| 2. WHARFAGE | 2.1 | Unboxed Automobiles (cars, pickups, SUVs) / unit | $4.39 | $4.69 | $5.02 | 3.8.2 |
| 2.2 | Rubber Tired Self-Propelled RORO < 23' LOA / unit | $7.00 | $7.00 | $7.00 | 3.8.2 | |
| 2.3 | Rubber Tired Self-Propelled RORO > 23' LOA / unit | $14.00 | $14.00 | $14.00 | 3.8.2 | |
| 2.4 | Rubber Tired Self-Propelled RORO > 45' LOA and / or > 9' wide / unit | $21.00 | $21.00 | $21.00 | 3.8.2 | |
| 2.5 | Dry or Liquid Bulk - as arranged, Minimum Charge | $267.50 | $286.23 | $306.26 | 3.8.2 | |
| 2.6 | Container - On terminal Stripped / Stuffed > or = 40' / container | $35.27 | $37.74 | $40.38 | 3.8.2 | |
| 2.7 | Container - On terminal Stripped / Stuffed < or = 40' / container | $27.55 | $29.48 | $31.54 | 3.8.2 | |
| 2.8 | Container - Off terminal Stripped / Stuffed > or = 40' / container | $36.65 | $39.21 | $41.96 | 3.8.2 | |
| 2.9 | Container - Off terminal Stripped / Stuffed < or = 40' / container | $30.86 | $33.02 | $35.33 | 3.8.2 | |
| 2.10 | Empty Container / container | $14.69 | $15.72 | $16.82 | 3.8.2 | |
| 2.11 | General Cargo - NOS / ton | $1.47 | $1.57 | $1.68 | 3.8.2 | |
| 2.12 | General Cargo - NOS – Minimum Charge | $267.50 | $286.23 | $306.26 | 3.8.2 | |
| 2.13 | Lumber per 1,000 feet board | $1.24 | $1.33 | $1.42 | 3.8.2 | |
| 2.14 | Lumber, Minimum Charge | $267.50 | $286.23 | $306.26 | 3.8.2 | |
| 2.15 | Steel - Greater of per ton or per 40 CFT | $1.40 | $1.50 | $1.60 | 3.8.2 | |
| 2.16 | Steel Minimum | $267.50 | $286.23 | $306.26 | 3.8.2 | |
| 3. Demurrage | 3.1 | Covered Areas per item per day for the 1st two days | $4.41 | $4.72 | $5.05 | 3.8.3 |
| 3.2 | Covered Areas per item per day for days 3 through 6 | $7.35 | $7.87 | $8.42 | 3.8.3 | |
| 3.3 | Covered Areas per item per day for days 7+ | $14.69 | $15.72 | $16.82 | 3.8.3 | |
| 3.4 | Uncovered Areas per item per day for the 1st two days | $2.94 | $3.15 | $3.37 | 3.8.3 | |
| 3.5 | Uncovered Areas per item per day for days 3 through 6 | $5.87 | $6.29 | $6.73 | 3.8.3 | |
| 3.6 | Uncovered Areas per item per day for days 7+ | $11.76 | $12.58 | $13.46 | 3.8.3 | |
| 4. OFF-SHORE SERVICE & CONSTRUCTION VESSELS | 4.1 | Offshore Wind Vessels > 250' LOA / 24 hours | $4,500.00 | $4,500.00 | $4,500.00 | 3.8.4 |
| 4.2 | Offshore Wind Vessels > 125' LOA and < 250' LOA / 24 hours | $3,500.00 | $3,500.00 | $3,500.00 | 3.8.4 | |
| 4.3 | Offshore Wind Vessels < 125' LOA, docked for > or = 8 hours and up to 24 hours | $2,500.00 | $2,500.00 | $2,500.00 | 3.8.4 | |
| 4.4 | Offshore Wind Vessels < 125' LOA, docked for < 8 hours | $1,000.00 | $1,000.00 | $1,000.00 | 3.8.4 | |
| 5. SERVICE CHARGES | 5.1 | Port Security - Weekday Rate < 9 hours | $465.45 | $498.03 | $532.89 | 3.8.5 |
| 5.2 | Port Security - Weekday Rate > 9 hours | $1,605.00 | $1,717.35 | $1,837.56 | 3.8.5 | |
| 5.3 | Port Security - Weekend / Holiday Rate < 9 hours | $695.50 | $744.19 | $796.28 | 3.8.5 | |
| 5.4 | Port Security - Weekend / Holiday Rate > 9 hours | $1,872.50 | $2,003.58 | $2,143.83 | 3.8.5 | |
| 5.5 | Port Operations Fee | $69.55 | $74.42 | $79.63 | 3.8.5 | |
| 5.6 | Crane hire, Mobile Harbour Crane / Hour (Plus Fuel) | $500.00 | $525.00 | $550.00 | 3.8.6 | |
| 5.7 | Crane hire, Rough Terrain Crane / Hour (Plus Fuel) | $350.00 | $375.00 | $400.00 | 3.8.6 | |
| 5.8 | Crane Operator / Hour | $50 | $55 | $60 | 3.8.6 | |
| 5.9 | Crane Operator - Minimum | $535.00 | $572.45 | $612.52 | 3.8.6 | |
| 5.10 | Mobile Harbour Crane Fuel Surcharge / Hour of Use | $125.00 | $125.00 | $125.00 | 3.8.6 | |
| 5.11 | Rough Terrain Crane Fuel Surcharge / Hour of Use | $75 | $75 | $75 | 3.8.6 | |
| 5.12 | Water Connection Charge (Plus Usage) | $214.00 | $228.98 | $245.01 | 3.8.7.A | |
| 5.13 | Truck Loading or Unloading / Vehicle Manifested Outside of Rhode IslandI | $10.70 | $11.45 | $12.25 | 3.8.7.B | |
| 5.14 | Haz-Mat Cargo Wharfage Fee, Minimum Charge | $1,070.00 | $1,144.90 | $1,225.04 | 3.8.7.C | |
| 5.15 | Haz-Mat Cargo Dockage Fee, Minimum Charge | $1,070.00 | $1,144.90 | $1,225.04 | 3.8.7.C | |
| 5.16 | Passenger Embarking or Debarking / Passenger (other than those listed separately, below) | $5.82 | $6.23 | $6.66 | 3.8.7.D | |
| 5.17 | Passenger Under 12 Years Old / Passenger | $1.83 | $1.96 | $2.09 | 3.8.7.D | |
| 5.18 | Passenger in Transit | $4.40 | $4.71 | $5.03 | 3.8.7.D | |
| 5.19 | Cruise Ship Passenger - No Cabin / Passenger | $4.40 | $4.71 | $5.03 | 3.8.7.D | |
| 5.20 | Cruise Ship Passenger - No Cabin - Under 12 Y.O. / Passenger | $2.93 | $3.14 | $3.36 | 3.8.7.D | |
| 6. PENALTIES | 6.1 | Non-Emailed Berth Application | $267.50 | $286.23 | $306.26 | 3.8.7.G |
| 6.2 | Fee for Third Change to Berth Application | $267.50 | $286.23 | $306.26 | 3.8.7.H | |
| 6.3 | Hourly charge for Noncompliance with Berth Assignment | $107.00 | $114.49 | $122.50 | 3.8.7.F | |
| 6.4 | Spill Penalty per Incidence | $1,070.00 | $1,144.90 | $1,225.04 | 3.8.7.E | |
| 6.5 | Fee for Failure to Provide Information per Incidence (Percentage of All Other Charges for Use Event) | 10% | 10% | 10% | 3.8.7.I |