250-RICR-140-05-6
C. Radius Plan: A radius plan, including all the information listed below, shall be submitted. A radius plan must be drawn to a minimum scale of one inch to two hundred feet (1" = 200 feet) adjusted to fit on standard 24 x 36 inch sheets and including all areas within a one quarter (1/4) mile radius out from all property lines on the site. The required information includes:
D. Site Plan: A site plan, including all of the information listed below for all areas within the site, shall be submitted. The site plan must be drawn to a minimum scale of one inch to one hundred feet (1" = 100 feet), adjusted to fit on standard 24 x 36 inch sheet(s). The required information includes:
14. Power and pipe lines and other utilities (e.g. water, sewer, gas, electric, telephone, etc.) including:
F. Operating Plan
2. The applicant must demonstrate an ability to comply with the General Operating Standards (§ 1.7 of this Subchapter), as well as the petroleum contaminated soil processing facility operating and design standards in §§ 6.2 and 6.3 of this Part respectively. The following information shall be included in the operating plan:
a. Operating Rates and Design Capacities
c. Operating Hours
d. Provisions for Limited Access (see also § 1.7(C) of this Subchapter)
f. Transportation Practices
g. Manifested Loads and Rejected Loads
h. Weighing Facilities
m. Facility Housekeeping Procedures
(1) Identification of the areas at the facility susceptible to:
o. Water Pollution
p. Residue Storage and Disposal
r. Processed Soil
s. Inspection
t. Routine Overhaul and Maintenance
u. Substitute Disposal and/or Transfer Arrangements
v. Personnel and Duties
(1) Staffing
w. Personnel Protection and Safety
x. Fire Control and Prevention Provisions
G. Closure Plan. This plan will include the following, at minimum:
E. Transportation Practices
1. Measures shall be employed to minimize precipitation run-on, prevent loss of soil or contaminants from the truck, and prevent a spill of material, while in transit. This applies to incoming soils and outgoing rejected contaminated soil or processed soil. Recommended measures include:
F. Acceptable Uses of Processed Soil
1. Any material processed by RIDEM licensed solid waste management facilities, or by out-of-state facilities and to be re-used within Rhode Island, may be used for any of the following applications:
G. Limits of Parameters in the Processed Soil
A. Process Equipment
B. Design of Storage Chamber for Incoming Contaminated Soil
7. Soil storage, prior to completion of the fingerprinting process, includes the following options:
C. Design of Holding Area for Processed Soil at Process Facility Site
A. The waste analysis plan must specify exactly what kind of materials the facility proposes to accept for processing. The soil shall be contaminated with only virgin petroleum products and associated spill clean-up debris. Language like "such as" or "etc" used in describing the incoming waste streams is unacceptable. In addition to the types of accepted material, numerical limits must be proposed for all significant contaminated soil parameters including, at a minimum, flashpoint, total petroleum hydrocarbons (per any equipment processing limitations), non-halogenated volatile organic compounds, halogenated volatile organic compounds, EP toxic metals (arsenic, barium, cadmium, chromium, lead, mercury, selenium, and silver), polychlorinated biphenyls (PCB), cyanide, and Ph. The acceptable physical state of the contaminated soil must also be specified. The waste analysis section of the operating plan must also provide a comprehensive waste verification procedure. This refers to efforts by the waste processing facility personnel to ensure that the soil received is contaminated by only virgin petroleum products and associated spill clean-up debris and that the possibility of accepting hazardous waste is minimized. Verification also allows the processor to assess if the processing equipment employed for soil clean-up will be adequate to handle the waste, given the levels of contaminant and any required limits of contamination in the cleaned product. Steps in the verification procedure include at least:
A. The following represents a minimal sampling and testing strategy. Additional sampling may be required at a given site, on a case-by-case basis, to adequately characterize the contaminated soil and to minimize the potential of accepting hazardous materials or materials that the soil processor is not permitted to accept.
1. Scenario 1: For projects where contaminated soil has been excavated and stockpiled and where the piles are "homogeneous" or "heterogeneous" defined as follows:
c. A contaminated pile or site, where there are visual differences in the appearance of spill material in different, defined areas or sectors of the pile or site and/or where contaminant monitoring devices provide significantly different readings in different, defined areas or sectors of the pile or site such that:
d. Case 1 - Homogeneous Pile or Site:
(3) In the laboratory, half of each of the five grab samples from five adjacent grids will be composited into one sample for test purposes and to represent that cumulative 100 cubic yards of soil. (Therefore, there will be one composite sample and one set of lab tests for each 100 cubic yard of soil, or portion thereof). If any of the composite sample's test indicate a problem (hazardous waste characteristics, material not acceptable per the applicant's permit, etc.) then the soil processor shall have several options:
e. Case 2 - Heterogeneous Pile or Site
(1) The procedures to be used are the same as in Case 1 for homogeneous piles or sites, except for the following:
2. Scenario 2: For projects where excavation and stockpiling is not possible due to space restrictions or environmental considerations:
b. In the laboratory, half of each of the five composite samples from five adjacent grids will, in turn, be composited into one sample for test purposes, and to be representative of that cumulative 100 yd3 of soil. (Therefore, there will be one composite sample and one set of lab tests for each 100 yd3 of soil, or portion thereof). In the event that any composite sample's tests indicate a problem (hazardous waste characteristics, material that is not acceptable per the applicant's permit, etc.) then the soil processor shall have several options:
B. A full scan, to include at minimum, the tests required in § 6.6(A) of this Part as well as tests for EPTOX metals, PCB, cyanide, and pH will be required for any of the following scenarios:
D. If the applicant does not select the option § 6.6(C) of this Part above and where § 6.6(B) of this Part has been determined not to apply, then a sub-set of the full scan tests shall be performed, when necessary, based on knowledge of the contaminant (e.g., EP toxic lead for a spill of leaded gas) and the following steps shall be taken to decide what lab tests will be performed on field samples of contaminated soil:
2. Each constituent or element that is at a concentration that is considered hazardous, according to the Rules and Regulations for Hazardous Waste Management (Subchapter 10 Part 1 of this Chapter), when it becomes a waste product (when it is spilled into the soil), shall be tested for, in the soil sample. Alternately, if the information provided includes only a range of concentrations of each constituent or element, then the highest concentration in this range shall be considered to be actual concentration in the spill virgin product. Examples include:
A. Fingerprinting is performed for numerous reasons, including:
B. Therefore, the minimum fingerprinting requirements shall include:
A. The following is a guideline that represents a minimum sampling and testing strategy. Additional sampling and testing may be desirable at a given facility, on a case-by-case basis, to adequately fingerprint the soil and to minimize potential of accepting hazardous waste. (Parameters to be analyzed in the tests are discussed in §§ 6.2(C) and 6.7 of this Part.)
4. If the processor's facility design and operating procedures are such that all truck loads from a given site are combined into one overall pile, after sampling for fingerprint analysis, then the following applies:
b. Fingerprint tests should be performed on a portion of each overall composite sample, with the results compared to the lab test results on generator site samples. If there is significant comparison differences for any of the composite samples, then the fingerprint tests should be repeated on the remaining portion of each composite sample, where results differed. A "significant comparison difference" shall mean, considerably lower flashpoints or considerably higher PCB levels in the fingerprint samples (per discretion of processor) and definitely any samples indicating flashpoints less than 100ºF or PCB levels greater than 50 ppm. If any of the repeat fingerprint tests verifies significant comparison difference for any of the composite samples, then the processor has options as follows:
5. If the processor's facility design and operating procedures are such that segregation of portion(s) of a generator's soil is maintained, after sampling for fingerprint analysis and until fingerprint tests on that soil are completed, then the following options apply:
b. The processor may use a modified version of in §§ 6.8(A)(4)(a) through (b) of this Part as follows:
(2) Fingerprint tests shall be performed on a portion of each overall composite sample, with the results compared to the lab test results on generator site samples. If there is significant comparison differences for any of the composite samples, then the fingerprint tests shall be repeated on the remaining portion of each composite sample, where results differed. If any of the repeat fingerprint tests verifies significant comparison differences for any of the composite samples, then the processor has options as follows:
A. The following is a guideline that represents a minimum sampling and testing strategy. Additional sampling and testing may be desirable at a given facility, on a case-by-case, or where required by the party that will be accepting the soil for re-use. Details of the actual tests and analyses will be based on any requirements of the accepting party.