- A. A construction contract may include a provision for the retainage of a portion of payment due. Such retainage is not to exceed ten percent (10%) of the amount of the payment due. When the gross proper invoice of the prime contractor first equal or exceed fifty percent (50%) of the value of the contract, the amount of retainage withheld thereafter shall not exceed five percent (5%) of the total proper invoice.
- B. A subcontract may include a provision for the retainage of a portion of payment due. Such retainage is not to exceed ten percent (10%) of the amount of the payment due. When the gross proper invoice of the subcontractor or sub-subcontractor first equal or exceed fifty percent (50%) of the value of the subcontract, the retainage percentage withheld thereafter shall not exceed that percentage withheld from the entity withholding retainage.
- C. No later than twenty-one (21) calendar days after a certificate of substantial completion is issued for the project or separate usable phase of the project and upon adequate performance of the prime contractor and with approval of any applicable surety, retainage shall be released by the owner to the prime contractor less an amount no greater than one hundred fifty percent (150%) of the estimated costs to correct any incomplete or defective work as identified, itemized, and attached to the certificate of substantial completion. All remaining funds shall be released as each deficiency is satisfactorily completed. The prime contractor shall release within ten (10) calendar days of receipt, the share of those funds that have been withheld from other entities. All other entities shall release within seven (7) calendar days of receipt, the share of those funds that have been withheld from other entities.
Laws 2004, SB 1561, c. 256, § 6, eff. November 1, 2004.