Okla. Stat. tit. 61, § 202.1
Design-Build and At-Risk Construction Management Project Delivery Methods - Approval - Exemptions - Rules - Public Notice
Effective Jul 1, 2003Laws 2000, HB 1250, c. 365, § 2, emerg. eff. June 6, 2000; Amended by Laws 2003, SB 246, c. 277, § 1, emerg .eff. July 1, 2003 (superseded document available).
- A. The design-build and at-risk construction management project delivery methods shall not be used without the written approval of the Director of Central Services or an act of the Legislature specifying design-build or at-risk construction management for a project. In all instances where the design-build project or at-risk construction management delivery method is authorized, construction administration shall be performed by the State Construction Administrator, the Administrator's designee or designees, or otherwise by contract or contract provision approved by the Director of Central Services for construction administration by another party.
- B. The provisions of subsection A of this section shall not apply to projects by contract pursuant to an interagency agreement under Section 581 of Title 74 of the Oklahoma Statutes or to projects a state agency performs solely with the staff of the agency.
- C. The Department of Central Services shall, pursuant to the Administrative Procedures Act, promulgate rules to effect procedures and processes necessary to the fulfillment of its responsibilities under subsection A of this section.
Laws 2000, HB 1250, c. 365, § 2, emerg. eff. June 6, 2000; Amended by Laws 2003, SB 246, c. 277, § 1, emerg .eff. July 1, 2003 (superseded document available).