Okla. Stat. tit. 61, § 121
Change Orders or Addenda
Effective Jul 1, 2004Laws 1974, HB 1665, c. 298, § 21, emerg. eff. August 1, 1974; Amended by Laws 1975, HB 1251, c. 266, § 9, emerg. eff. June 5, 1975; Amended by Laws 1989, HB 1257, c. 164, § 1, emerg. eff. May 8, 1989; Amended by Laws 1993, SB 414, c. 293, § 2, emerg. eff. June 3, 1993; Amended by Laws 1995, SB 250, c. 200, § 3, emerg. eff. May 19, 1995; Amended by Laws 1997, HB 1745, c. 72, § 1, eff. November 1, 1997 (superseded document available); Amended by Laws 1998, HB 2267, c. 118, § 1, emerg. eff. July 1, 1998 (superseded document available); Amended by Laws 2000, SB 1172, c. 363, § 11, emerg. eff. June 6, 2000 (superseded document available); Amended by Laws 2002, HB 2874, c. 294, § 22, eff. November 1, 2002 (superseded document available); Amended by Laws 2004, HB 1695, c. 328, § 2, emerg. eff. July 1, 2004 (superseded document available).
- A. Change orders or addenda to public construction contracts of One Million Dollars ($1,000,000.00) or less shall not exceed a fifteen percent (15%) cumulative increase in the original contract amount.
- B. Change orders or addenda to public construction contracts of over One Million Dollars ($1,000,000.00) shall not exceed the greater of One Hundred Fifty Thousand Dollars ($150,000.00) or a ten percent (10%) cumulative increase in the original contract amount.
- C. Change orders or cumulative change orders which exceed the limits of subsection A or B of this section shall require a readvertising for bids on the incomplete portions of the contract.
- D. If the awarding public agency does not have a governing body, the chief administrative officer of the awarding public agency shall approve change orders. The State Construction Administrator of the Construction and Properties Division of the Department of Central Services shall sign and execute all contracts and change orders, as they relate to state agencies.
- E. If the awarding public agency has a governing body, all change orders shall be formally approved by the governing body of the awarding public agency and the reasons for approval recorded in the permanent records of the governing body.
- F. The governing body of the Oklahoma Tourism and Recreation Department is authorized, upon approval of a majority of all of the members of the Oklahoma Tourism and Recreation Commission, to delegate to the Director of the agency the authority to approve change orders on a construction contract provided that the individual change order does not exceed Twenty-five Thousand Dollars ($25,000.00) in expenditure and complies with the limits established by this section. The Administrator of the Division shall sign and execute all contracts and change orders.
G. The Transportation Commission may, by rule, authorize the Director of the Department of Transportation to approve change orders in an amount of not to exceed Five Hundred Thousand Dollars ($500,000.00). Change orders approved by the Director shall be presented to the Transportation Commission during the next regular meeting and the reasons therefor recorded in the permanent records. The Oklahoma Transportation Authority may authorize the Director of the Authority to approve change orders in an amount not to exceed Two Hundred Fifty Thousand Dollars ($250,000.00). Change orders approved by the Director of the Authority shall be presented to the Oklahoma Transportation Authority during the next regular meeting and the reasons for the orders recorded in permanent records. All change orders for the Department of Transportation or the Oklahoma Transportation Authority shall contain a unit price and total for each of the following items:
- 1. All materials with cost per item;
- 2. Itemization of all labor with number of hours per operation and cost per hour;
- 3. Itemization of all equipment with the type of equipment, number of each type, cost per hour for each type, and number of hours of actual operation for each type;
- 4. Itemization of insurance cost, bond cost, social security, taxes, workers' compensation, employee fringe benefits and overhead cost; and
- 5. Profit for the contractor.
H.
- 1. If a construction contract contains unit pricing, and the change order pertains to the unit price, the change order will not be subject to subsection A or B of this section.
- 2. When the unit price change does not exceed Ten Thousand Dollars ($10,000.00), the unit price change order computation may be based on an acceptable unit price basis in lieu of cost itemization as required in paragraphs 1, 2, 3, 4 and 5 of subsection G of this section.
- I. Alternates or add items bid with the original bid and contained in the awarded contract as options of the awarding public agency shall not be construed as change orders under the provisions of the Public Competitive Bidding Act of 1974.
Laws 1974, HB 1665, c. 298, § 21, emerg. eff. August 1, 1974; Amended by Laws 1975, HB 1251, c. 266, § 9, emerg. eff. June 5, 1975; Amended by Laws 1989, HB 1257, c. 164, § 1, emerg. eff. May 8, 1989; Amended by Laws 1993, SB 414, c. 293, § 2, emerg. eff. June 3, 1993; Amended by Laws 1995, SB 250, c. 200, § 3, emerg. eff. May 19, 1995; Amended by Laws 1997, HB 1745, c. 72, § 1, eff. November 1, 1997 (superseded document available); Amended by Laws 1998, HB 2267, c. 118, § 1, emerg. eff. July 1, 1998 (superseded document available); Amended by Laws 2000, SB 1172, c. 363, § 11, emerg. eff. June 6, 2000 (superseded document available); Amended by Laws 2002, HB 2874, c. 294, § 22, eff. November 1, 2002 (superseded document available); Amended by Laws 2004, HB 1695, c. 328, § 2, emerg. eff. July 1, 2004 (superseded document available).