N.M. Code R. § 17.11.22.14
D. Installation interval – new facilities required. Where new facilities are needed to provide designed service, the ILEC shall install the service within forty-five (45) calendar days, unless the customer requests a later date. If the order is not completed within forty-five (45) calendar days or the later date requested by the customer, the customer shall receive a credit of the nonrecurring charge except when the ILEC can establish that delay was caused by circumstances beyond its reasonable control.
(1) When the delay is caused by circumstances beyond the ILEC's reasonable control and the commission has granted a waiver of the held order standard pursuant to 17.11.22.25 NMAC, the period of delay shall be added to the time period allowed for installation of the service.
(2) An ILEC shall report any case in which it claims the delay is caused by circumstances beyond the reasonable control of the ILEC to the affected customer who shall have the right to challenge the exception.
E. Credits for failure to comply with installation interval. The following credits shall apply when an ILEC fails to meet designed services installation intervals during the preceding calendar year.
% installed within installation interval Amount per day late to be credited to customer for failure to meet held order standard 85% to 100% no credit applies 75% to 84% $ 200 65% to 74% $ 500 55% to 64% $1,000 45% to 54% $1,500 35% to 44% $3,000 0 to 34% $5,000
% installed within installation interval
Amount per day late to be credited to customer for failure to meet held order standard
85% to 100%
no credit applies
75% to 84%
$ 200
65% to 74%
$ 500
55% to 64%
$1,000
45% to 54%
$1,500
35% to 44%
$3,000
0 to 34%
$5,000
[17.11.22.14 NMAC - Rp, 17.11.22.14 NMAC, 2-1-06]