N.M. Code R. § 14.7.9.12
See this Chapter of the IECC except as provided below.
D. Section 405 Electrical power and lighting systems. See this section of the IECC except as provided below.
(4) Section C405.13 Electric vehicle power transfer infrastructure. Add this section to
(a) Section C405.13.1 Quantity. Add this section to the IECC. The number of required EV spaces and EV capable spaces shall be determined in accordance with this section and Table C405.13.1 based on the total number of automobile parking spaces and shall be rounded up to the nearest whole number. For R-2 buildings, the table requirements shall be based on the total number of dwelling units or the total number of automobile parking spaces, whichever is less.
(iv) Requirements for a Group S-2 parking garage shall be determined by the occupancies served by that parking garage. Where new automobile spaces do not serve specific occupancies, the values for Group S-2 parking garage in Table C405.13.1 shall be used.
Exception: Parking facilities, serving occupancies other than R-2 with fewer than 10 automobile parking spaces.
(b) Table C405.13.1 Required EV Power Transfer Infrastructure. Add this table to the IECC.
TABLE C405.13.1 REQUIRED EV POWER TRANSFER INFRASTRUCTURE
Occupancy EVSE Spaces *EV Capable Spaces Group A 5% 10% Group B 5% 5% Group E 5% 5% Group F 2% 5% Group H 1% 0% Group I 5% 10% Group M 5% 10% Group R-1 5% 15% Group R-2 5% 15% Group R-3 and R-4 2% 5% Group S exclusive of Parking Garages 1% 0% Group S-2 Parking Garages 5% 10%
Occupancy
EVSE Spaces
*EV Capable Spaces
Group A
5%
10%
Group B
5%
5%
Group E
5%
5%
Group F
2%
5%
Group H
1%
0%
Group I
5%
10%
Group M
5%
10%
Group R-1
5%
15%
Group R-2
5%
15%
Group R-3 and R-4
2%
5%
Group S exclusive of Parking Garages
1%
0%
Group S-2 Parking Garages
5%
10%
*EV Capable Spaces are in addition to the required EVSE Spaces.
(c) Section C405.13.2 EV Capable Spaces. Add this section to the IECC. Each EV capable space used to meet the requirements of section C405.13.1 shall comply with the following:
(d) Section C405.13.3 EVSE Spaces. Add this section to the IECC. An installed EVSE with multiple output connections shall be permitted to serve multiple EVSE spaces. Each EVSE installed to meet the requirements of section C405.13.1, serving either a single EVSE space or multiple EVSE spaces, shall comply with the following:
(f) Section C405.13.4.1 System capacity. Add this section to the IECC. The electrical distribution equipment supplying the branch circuit(s) serving each EV capable space and EVSE space shall comply with one of the following:
(g) Section C405.13.4.2 Circuit Capacity. Add this section to the IECC. The branch circuit serving each EV capable space and EVSE space shall comply with one of the following:
(h) Section C405.14.4.3 System and circuit capacity management. Add this
section to the IECC. Where system and circuit capacity management are selected in section C405.13.5.1(2) or section C405.13.5.2(2), the installation shall comply with sections C405.13.4.3.1 and C405.13.4.3.2.
(i) Section C405.13.4.3.1 System capacity management. Add this section to
the IECC. The maximum equipment load on the electrical distribution equipment supplying the branch circuits(s) serving EV capable spaces and EVSE spaces controlled by an energy management system shall be the maximum load permitted by the energy management system, but not less than 3.3 kVA per space.
(j) Section C405.13.4.3.2 Circuit Capacity Management. Add this section to
the IECC. Each branch circuit serving multiple EVSE spaces or EV capable spaces controlled by an energy management system shall comply with one of the following:
the IECC. Parking facilities shall be provided with electric vehicle power transfer infrastructure in accordance with design requirements and Sections C405.13.1 through C405.13.6.
D. Section C408 Maintenance Information and System Commissioning. See this section of the IECC except as provided below.
(1) Section C408.2 Mechanical systems and service water-heating systems
commissioning and completion requirements. Delete this section of the IECC and substitute with the following: Prior to the final mechanical and plumbing inspections, the registered design professional or approved agency, shall provide evidence of mechanical systems commissioning and completion in accordance with the provisions of this section. Construction document notes shall clearly indicate provisions for commissioning requirements in accordance with this section and are permitted to refer to specifications for further requirements. Copies of all documentation shall be given to the building owner or owners authorized agent.
Exceptions: The following systems are exempt:
(b) Systems included in Section C403.5 that serve individual dwelling units and sleeping units.
(3) Figure C408.2.4 Commissioning compliance checklist. Delete this figure from the IECC and substitute with the following figure:
FIGURE C408.2.4
COMMISSIONING COMPLIANCE CHECKLIST
Project Information: ________________________________ Project Name:__________________________
Project Address: _________________________________________________________________________
Commissioning Authority: __________________________________________________________________
Commissioning Plan (Section C408.2.1)
q Commissioning Plan was used during construction and includes all items required by Section C408.2.1
q Systems Adjusting and Balancing shall be completed per plans and specifications.
q HVAC Equipment Functional Testing shall be completed per plans and specifications.
q HVAC Controls Functional Testing shall be completed per plans and specifications.
q Economizer Functional Testing shall be completed per plans and specifications.
q Lighting Controls Functional Testing shall be completed per plans and specifications.
q Service Water Heating System Functional Testing shall be completed per plans and specifications.
q Manual, record documents and training shall be completed per plans and specifications.
q Preliminary Commissioning Report shall be submitted to the owner and includes all items required by Section C408.2.4.
q The above-referenced items are scheduled to be provided on:
I, the commissioning provider, do hereby certify that I am providing the owner or owner’s representative with documentation as to the mechanical, service water heating and lighting systems commissioning in accordance with the 2021 IECC.
_____________________________________________ ____________________
Signature of Commissioning Provider Date
____________________________________________ ____________________
Signature of Building Owner/Owner’s Representative Date
_____________________________________________________________________________
[14.7.6.12 NMAC – Rp, 14.7.9.12 NMAC, 01/30/2024]